Apply the learning
Use these fictional practice sheets. They do not create, sign or approve workplace records.
Construction and CDM site inspection
Sample relevant questions, identify objective evidence and assign an owned corrective action. A completed form alone does not prove control.
- Are the applicable client, designer and contractor roles identified and appointments recorded where required? Evidence to seek: Review the project arrangements and confirm the actual dutyholder interfaces.
- Is pre-construction information relevant and available to those planning the work? Evidence to seek: Sample services, asbestos, ground, design and existing-structure information.
- Are work-at-height risks avoided where possible and suitable protection and rescue arrangements in place? Evidence to seek: Observe the task, access equipment, edge protection, inspection and rescue arrangements.
- Are excavations, buried services and ground conditions controlled before and during work? Evidence to seek: Sample service information, locating, excavation support, access and competent inspections.
- Are dust and fume controls effective at the point of generation? Evidence to seek: Observe cutting, drilling or a relevant task; verify extraction or suppression and housekeeping.
The live SHAREhub tool may require an account. The included fictional exercise remains available offline and never creates a real workplace record.
Construction management (CDM)
Identify the task limits, responsibilities and support or escalation route. Compare the arrangement with the fictional case; do not adopt a template without checking the actual workplace.
- An office refurbishment uses an electrician and a flooring contractor. The client assumes that being below notification thresholds removes CDM duties. Is that correct?
- No. Check the project’s duties and appointments independently of notification thresholds, and verify the required planning and welfare before work starts.
- Prepare a client pre-start decision list for a fictional refurbishment.
The live SHAREhub tool may require an account. The included fictional exercise remains available offline and never creates a real workplace record.
Construction supervisor shift walk-round
Select the checks that would establish usable controls during this shift. State who must act if a check fails and what evidence is needed before release.
- Have today's workers completed the site induction? Evidence to seek: Observe safely against the approved local criterion or check the named record. Yes confirms the whole question; No needs a finding and action; N/A needs a reason. Do not defeat safeguards, open live enclosures or perform an unsafe test.
- Has the supervisor briefed today's task-specific method? Evidence to seek: Observe safely against the approved local criterion or check the named record. Yes confirms the whole question; No needs a finding and action; N/A needs a reason. Do not defeat safeguards, open live enclosures or perform an unsafe test.
The live SHAREhub tool may require an account. The included fictional exercise remains available offline and never creates a real workplace record.
Optional visual practice and worked application
Use these fictional exercises to compare evidence and rehearse decisions. They do not alter course completion or assessment requirements. You can work through the same choices on paper.
Small refurbishment with two contractors: read the evidence
A commercial client arranges a short refurbishment with an electrician and a separate building contractor. The client assumes that a non-notifiable programme means no CDM appointments or construction phase plan are needed.
The failure in this example
Notification has been used as a substitute for deciding which project duties apply. Project planning, coordination and welfare do not disappear because a notification threshold is not reached.
A better arrangement
Establish the applicable project roles and competent appointments, provide the relevant pre-construction information and resources, and verify proportionate planning, coordination and welfare before construction starts.
Worked record: who owns the decision?
The commercial client ensures suitable arrangements and appointments; the appointed project roles coordinate their own design and construction phases.
Match the evidence roles in this task
A commercial client arranges a short refurbishment with an electrician and a separate building contractor. The client assumes that a non-notifiable programme means no CDM appointments or construction phase plan are needed.
Place each statement under the evidence role it describes. These roles support one task decision; they are not interchangeable.
- The client identifies the project needs, resources and suitable appointments. Client arrangement. This statement addresses client arrangement. The client identifies the project needs, resources and suitable appointments.
- The relevant principal/project roles coordinate design and construction risks within their control. Phase coordination. This statement addresses phase coordination. The relevant principal/project roles coordinate design and construction risks within their control.
- The statutory notification question is checked separately for the actual jurisdiction and forecast programme. Notification decision. This statement addresses notification decision. The statutory notification question is checked separately for the actual jurisdiction and forecast programme.
Small refurbishment with two contractors: test the arrangement
Notification has been used as a substitute for deciding which project duties apply. Project planning, coordination and welfare do not disappear because a notification threshold is not reached. Establish the applicable project roles and competent appointments, provide the relevant pre-construction information and resources, and verify proportionate planning, coordination and welfare before construction starts.
Worked record: evidence to obtain
Work location/jurisdiction, the foreseeable contractor interfaces, role/control definitions and written appointments where required, relevant information, the usable construction phase plan and start arrangements.
Worked record: decision and owner
Establish the applicable project roles and competent appointments, provide the relevant pre-construction information and resources, and verify proportionate planning, coordination and welfare before construction starts. The commercial client ensures suitable arrangements and appointments; the appointed project roles coordinate their own design and construction phases.
Why the weak assurance fails
Notification has been used as a substitute for deciding which project duties apply. Project planning, coordination and welfare do not disappear because a notification threshold is not reached.
Choose evidence that supports the review
A commercial client arranges a short refurbishment with an electrician and a separate building contractor. The client assumes that a non-notifiable programme means no CDM appointments or construction phase plan are needed. The team is reviewing what can support acceptance.
Select the two statements which support the example’s review. Leave the two unsupported shortcuts unselected.
- The project team has checked the actual contractor interfaces and applicable GB or NI duties. Relevant evidence. This is useful evidence for this example. Work location/jurisdiction, the foreseeable contractor interfaces, role/control definitions and written appointments where required, relevant information, the usable construction phase plan and start arrangements.
- A proportionate construction phase plan explains how the overlapping tasks and welfare are managed. Relevant evidence. This is useful evidence for this example. Work location/jurisdiction, the foreseeable contractor interfaces, role/control definitions and written appointments where required, relevant information, the usable construction phase plan and start arrangements.
- A non-notifiable forecast is used to cancel all project planning and appointment decisions. Insufficient evidence. This does not resolve the example’s acceptance gap. Notification has been used as a substitute for deciding which project duties apply. Project planning, coordination and welfare do not disappear because a notification threshold is not reached.
- Each contractor has a generic risk assessment, so nobody checks their shared work area. Insufficient evidence. This does not resolve the example’s acceptance gap. Notification has been used as a substitute for deciding which project duties apply. Project planning, coordination and welfare do not disappear because a notification threshold is not reached.
Small refurbishment with two contractors: follow the changed condition
The sequence changes so the two contractors work in the same area at the same time. Follow the decision route; it supplies learning outcomes, not permission for real work.
A meaningful change
The sequence changes so the two contractors work in the same area at the same time. Revisit the basis of the affected decision instead of extending an earlier acceptance beyond its scope.
Worked record: what remains on hold?
Notification has been used as a substitute for deciding which project duties apply. Project planning, coordination and welfare do not disappear because a notification threshold is not reached. The example remains unresolved until the required roles, appointments and project information have been established.
Worked record: what would support later acceptance?
Work location/jurisdiction, the foreseeable contractor interfaces, role/control definitions and written appointments where required, relevant information, the usable construction phase plan and start arrangements. The commercial client ensures suitable arrangements and appointments; the appointed project roles coordinate their own design and construction phases.
Follow the changed-condition decision
A commercial client arranges a short refurbishment with an electrician and a separate building contractor. The client assumes that a non-notifiable programme means no CDM appointments or construction phase plan are needed. Changed condition: The sequence changes so the two contractors work in the same area at the same time.
Follow the evidence gates and compare the outcome of an unresolved condition with an established one.
- Has the reviewer established that the required roles, appointments and project information have been established?
- Yes, the stated basis is established: That resolves this evidence question; check the separate readiness condition next. Next: Has the responsible owner established that the construction phase plan and coordination arrangements reflect the changed contractor overlap?
- No, the basis remains unresolved: Do not infer acceptance from an incomplete or conflicting basis. Notification has been used as a substitute for deciding which project duties apply. Project planning, coordination and welfare do not disappear because a notification threshold is not reached. Next: Example outcome: retain the hold point — Establish the applicable project roles and competent appointments, provide the relevant pre-construction information and resources, and verify proportionate planning, coordination and welfare before construction starts.
- Has the responsible owner established that the construction phase plan and coordination arrangements reflect the changed contractor overlap?
- Yes, the required readiness evidence is established: In this fictional exercise, both evidence gates are established. Real work still follows its own authorised release. Next: Example outcome: record the verified basis for the authorised decision — Record the evidence, owner and limits of this example’s decision. The sequence changes so the two contractors work in the same area at the same time. is a reason to review it again; the course does not authorise actual work.
- No, readiness or competent cover is still missing: An agreed principle is not a usable arrangement. Resolve the missing condition before affected work proceeds. Next: Example outcome: arrange the missing protection or support — The commercial client ensures suitable arrangements and appointments; the appointed project roles coordinate their own design and construction phases. Re-plan the affected work and obtain evidence that the required readiness condition is met.
- Example outcome: retain the hold point
Establish the applicable project roles and competent appointments, provide the relevant pre-construction information and resources, and verify proportionate planning, coordination and welfare before construction starts.
- Example outcome: arrange the missing protection or support
The commercial client ensures suitable arrangements and appointments; the appointed project roles coordinate their own design and construction phases. Re-plan the affected work and obtain evidence that the required readiness condition is met.
- Example outcome: record the verified basis for the authorised decision
Record the evidence, owner and limits of this example’s decision. The sequence changes so the two contractors work in the same area at the same time. is a reason to review it again; the course does not authorise actual work.
Refurbishment coordination exercise
Build a fictional task/interface assessment for this two-contractor refurbishment. Identify each work interface and owner, then compare the record with the applicable CDM appointments and construction phase plan; the tool does not replace them.
Fictional record — task and concern: A commercial client arranges a short refurbishment with an electrician and a separate building contractor. The client assumes that a non-notifiable programme means no CDM appointments or construction phase plan are needed.
Fictional record — decision: Establish the applicable project roles and competent appointments, provide the relevant pre-construction information and resources, and verify proportionate planning, coordination and welfare before construction starts.
Fictional record — owner: The commercial client ensures suitable arrangements and appointments; the appointed project roles coordinate their own design and construction phases.
Fictional record — verification and review: Work location/jurisdiction, the foreseeable contractor interfaces, role/control definitions and written appointments where required, relevant information, the usable construction phase plan and start arrangements. Review trigger: The sequence changes so the two contractors work in the same area at the same time.