CDM essentials for clients and small projects · detailed source study
Optional reference study from the SHAREhub topic pages and selected source records used for this course. The core learning-time estimate excludes this extended reference.
Where does this CDM guide apply?
Where does this CDM guide apply?
Source: appointed-relevent-parties-cdm--scope
Use the project location and actual construction scope before selecting a dutyholder route; this is a build-stage guide, not a project appointment or legal opinion. CDM applies to defined construction work, including many alterations, repairs and demolitions, but not every routine maintenance task. Confirm scope against the relevant regulations. Great Britain uses CDM 2015; Northern Ireland uses its distinct CDM 2016. These pages focus on client and project dutyholders rather than building-control appointments, which are separate roles.
Make appointments from the whole project
Source: appointed-relevent-parties-cdm--review-start
Map the entire project, including trades arriving at different stages, before deciding the appointment route. A single contractor on today's site does not establish that the project is a single-contractor project. Commercial and domestic client routes also differ. Map the entire project, including trades arriving at different stages, before deciding the appointment route. A single contractor on today's site does not establish that the project is a single-contractor project. Construction clients must identify the actual dutyholders before work is organised. Apply it: Which part of this plan would you check at the workface before authorising the task? Construction clients must identify the actual dutyholders before work is organised.
Where a project involves, or is likely to involve, more than one contractor, the client must appoint a principal designer and principal contractor in writing as soon as practicable and before construction begins. Scope, contractor capability, pre-construction information, plan, permit if needed and hand-back. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Contractor isolates services, segregates the occupied area and follows the plan; client coordinates building access. Inspect finished area, reinstate routes and record any residual information needed for future work. Apply it: At which point would you hold this example, and what evidence would allow it to proceed? Designers and contractors may miss asbestos, services or structural constraints.
Incompatible activities can expose workers and other people at the same time. Work starts before a competent owner resolves the method and protection. Use the full topic for the detailed mechanism, task limits and source scope. Apply it: Where is this harm route present in the actual work, and which control breaks it before anyone is exposed? Eliminate: Design plant maintenance so roof-edge access is avoided. Reduce: Assess ground-level or protected-location servicing. Isolate: Provide suitable permanent edge protection and safe access. Control: Coordinate the construction plan, permit and briefing. PPE: Use assessed residual fall protection with a rescue route. Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged.
Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision? Keep one card or the full set for social sharing, team briefings and learning. Each PDF contains one card per page. Read the full topic for explanations, questions and source links.
Map the entire project, including trades arriving at different stages, before deciding the appointment route. Map the entire project, including trades arriving at different stages, before deciding the appointment route. A single contractor on today's site does not establish that the project is a single-contractor project. Construction clients must identify the actual dutyholders before work is organised. Apply it: Which part of this plan would you check at the workface before authorising the task? Use the evidence to improve the actual work arrangement. Construction clients must identify the actual dutyholders before work is organised.
Where a project involves, or is likely to involve, more than one contractor, the client must appoint a principal designer and principal contractor in writing as soon as practicable and before construction begins. Scope, contractor capability, pre-construction information, plan, permit if needed and hand-back. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Fictional example: a practical application of the existing topic lesson. Contractor isolates services, segregates the occupied area and follows the plan; client coordinates building access. Inspect finished area, reinstate routes and record any residual information needed for future work. Apply it: At which point would you hold this example, and what evidence would allow it to proceed?
Connect the task, the route to the person and the control that can fail. Designers and contractors may miss asbestos, services or structural constraints. Incompatible activities can expose workers and other people at the same time. Work starts before a competent owner resolves the method and protection. Use the full topic for the detailed mechanism, task limits and source scope. Apply it: Where is this harm route present in the actual work, and which control breaks it before anyone is exposed? Start with the stronger practicable options and verify their effect. Eliminate: Design plant maintenance so roof-edge access is avoided. Reduce: Assess ground-level or protected-location servicing. Isolate: Provide suitable permanent edge protection and safe access. Control: Coordinate the construction plan, permit and briefing.
PPE: Use assessed residual fall protection with a rescue route. Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged. Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Follow the official sources below and retain the task-specific evidence. Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision?
Simplified learning guide. Use the full topic and the actual work arrangements; existing technical-review and approval statuses still apply. Workplace scenarios labelled fictional are illustrative examples. Identify the people or organisations actually controlling design and construction, obtain suitable capability evidence and make the required roles clear in writing. Notification is an independent decision and cannot replace the appointment test. Use the applicable GB or NI instrument for the location. Compare two illustrative jobs. A householder’s bathroom repair with one contractor uses the applicable domestic-client and sole-contractor planning route; confirm who carries the transferred client duties.
A commercial refurbishment using a builder and later specialist installer is assessed as the whole multi-contractor project, even if their attendance does not overlap; the client records the required principal appointments. Both need a proportionate construction phase plan before construction, and notification remains a separate decision. Illustrative example. A commercial refurbishment uses a builder first and a specialist installer later; the client assumes there is only one contractor because they never overlap. Decision. Review appointments against the whole project contractor pattern and actual design/construction control before start. Evidence to check. Retain project scope, forecast trades, client type, capability checks and written role/document responsibilities. Hold or escalation point. Do not use non-overlap or a notification outcome as a shortcut around the appointment decision. Follow-up.
Revisit when design, procurement or contractor scope changes and brief the affected parties. Open CDM appointment and safe-start gate Read with: HSE CDM dutyholder summary · HSE domestic clients · HSENI CDM 2016 overview · HSE commercial clients.
What is the first CDM appointment decision?
What is the first CDM appointment decision?
Source: appointed-relevent-parties-cdm--decision
Count contractors expected across the whole project, including successive trades and likely subcontractors, then distinguish appointment from notification. Sources for this explanation: HSE CDM dutyholder summary; HSE domestic clients; HSENI CDM 2016 overview.
What must be settled before construction starts?
Source: appointed-relevent-parties-cdm--key-points
A clear client, capable principal roles where required, useful information, realistic time, welfare and a project-specific construction phase plan must be in place. The client owns suitable arrangements and must not offload them by naming an adviser. A principal designer needs influence over pre-construction decisions; a principal contractor needs time to plan the construction phase. Designers should eliminate foreseeable risks where possible, contractors must plan their work, and workers need information and consultation. After a change, revisit roles, plans, design and file rather than treating the original appointment as a one-off form. Sources for this explanation: HSE commercial clients; HSENI CDM 2016 overview.
When and how must principal dutyholders be appointed?
Source: appointed-relevent-parties-cdm--when-required
For a known or reasonably foreseeable multi-contractor project, a commercial client appoints a designer in control and a contractor in writing as soon as practicable, before construction begins. Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE principal designers · HSE planning for construction work. The principal designer should start early enough to influence concept and design risk. The principal contractor must be appointed early enough to help plan the construction phase and prepare the plan. If a commercial client omits either appointment, the client must fulfil that principal role duty; it remains responsible for the project arrangements.
For a domestic client who does not appoint, regulation 7 assigns principal-designer duties to the designer in control and principal-contractor duties to the contractor in control; client duties also transfer under the domestic route. A later second trade triggers a fresh assessment immediately, not only at the next contract renewal. Sources for this explanation: HSE commercial clients; HSE domestic clients; HSENI CDM 2016 overview.
What does each CDM dutyholder actually do?
Source: appointed-relevent-parties-cdm--dutyholders
The client sets suitable arrangements; the principal designer coordinates pre-construction risk; the principal contractor coordinates construction; designers and contractors control their own work. Sources for this explanation: HSE CDM dutyholder summary; HSENI CDM 2016 overview.
How should the client test an appointment?
Source: appointed-relevent-parties-cdm--appointment-evidence
Check the role definition, actual control, project-specific skills, knowledge, experience and organisational capability before recording a clear written appointment. Ask who will make design and site decisions, what time and resources they have, and how they will coordinate the other parties. The check should match risk and complexity. Relevant experience, team availability, supervision, previous performance and design or construction expertise may help. Membership, insurance, third-party schemes and training records can support a proportionate assessment but none is a universal substitute for capability or a fixed CDM legal checklist. Sources for this explanation: HSE CDM dutyholder summary; HSE CDM frequently asked questions.
What must a commercial client do after appointing others?
Source: appointed-relevent-parties-cdm--client-duties
Keep suitable project arrangements under review and ensure information, time, resources, welfare, plan and file are provided or produced as required. The client should provide pre-construction information it holds and obtain missing information proportionately. It must ensure the principal designer and principal contractor carry out their roles, rather than substituting a signature for oversight. Ensure the construction phase plan is prepared before site work and the health and safety file is handed over at project completion where required. Multiple clients should agree the statutory lead arrangement in writing where the regulations allow, while preserving information-sharing duties. Sources for this explanation: HSE commercial clients; HSENI CDM 2016 overview.
How do the two principal roles coordinate?
Source: appointed-relevent-parties-cdm--pd-pc
The principal designer makes design risk and pre-construction information usable; the principal contractor turns it into site coordination and feeds construction changes back. Source basis: HSE principal designers · HSE principal contractors · HSE L153 Managing health and safety in construction · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended). Sources for this explanation: HSE principal designers; HSE principal contractors.
What should designers and contractors check in daily work?
Source: appointed-relevent-parties-cdm--contractors-designers
Designers should remove or reduce foreseeable risk before specifying site controls; contractors must plan and supervise their tasks and coordinate interfaces. A designer might specify permanent roof-edge access rather than rely on repeated temporary edge protection. A contractor must challenge an impracticable design and share method and sequence impacts. Work at height, asbestos, silica, services, structural stability and public access need their own task assessment and controls. A generic RAMS pack is not evidence that the whole project is coordinated, and PPE is a last layer after stronger controls.
Information must cross the project phase boundary
Source: appointed-relevent-parties-cdm--release-cdm-handoffs
This worked coordination record describes a commercial project in Great Britain. Apply the correct GB or Northern Ireland rules and the separate domestic-client route where relevant. A project involving more than one contractor needs principal-role consideration even when the trades work at different times. Excavation example: number the evidence before work: 1 client/site information on services and past use; 2 designer’s relevant risk information; 3 contractor’s checked site conditions and method; 4 resolved changes and relevant handover information. A model view cannot verify any of these records. Notification is a separate check. Do not use the notification threshold to decide whether CDM duties or required appointments apply. Follow the appointment decision and keep the change loop active.
Read with: HSE: CDM dutyholders · HSE: principal designers.
Which CDM documents must exist and who owns them?
Source: appointed-relevent-parties-cdm--documents
Pre-construction information, the construction phase plan and, on multi-contractor projects, the health and safety file serve different decisions and handovers. Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE L153 Managing health and safety in construction · HSE F10 construction notification. Sources for this explanation: HSE planning for construction work; HSE L153 Managing health and safety in construction; HSENI CDM 2016 overview.
What are the before, during and hand-back hold points?
What are the before, during and hand-back hold points?
Source: appointed-relevent-parties-cdm--checks
Use stage gates: check scope and roles before start, control change while work proceeds, and verify the plan, site and file at hand-back.
How can the ISO 45001 hierarchy of controls guide risk reduction by CDM dutyholders?
Source: appointed-relevent-parties-cdm--operational-examples
Match the route to the entire project and revisit it when trades, design, location or hazards change. Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE CDM dutyholder summary · HSENI CDM 2016 overview. These BuildOut Ltd cases are teaching examples. They do not replace a site-specific construction phase plan, competent design, statutory appointment or local emergency procedure. On a refurbishment with several contractors, the client must identify the principal designer and principal contractor route early enough for them to influence planning; an appointment letter alone does not remove a roof-edge fall risk.
The design team first asks whether plant can be maintained from inside the building, eliminating edge access. A ground-level or protected-location service route may substitute for roof work. Where access remains, permanent edge protection and a safe access arrangement are engineering controls selected against the actual structure. A construction-phase plan, permit, briefing and inspection are administrative layers; fall-protection PPE is residual and requires an assessed rescue route. ERICPD Eliminate/Reduce/Isolate/Control map to those choices, while the five-level hierarchy keeps physical design ahead of paperwork. The client checks that the roles, pre-construction information and design decisions are recorded; the principal designer coordinates the residual design risk; the principal contractor checks the installed edge protection and site interface before release.
The competent engineer verifies fixings, loads and inspection criteria for the actual system. ERICPD Discipline means maintaining the barrier and reviewing changes, not blaming a trade worker for a missing design control. If contractor count changes, the plan is absent, the protection is incomplete or the roof condition is unknown, hold the affected work and resolve the appointment, design and construction decisions before access. Sources for this explanation: HSE F10 construction notification; HSENI new construction project notification; HSE domestic clients. ERICPD is a planning crossmap. Its prompts do not add a sixth rung or rank Isolate above engineering. Discipline verifies and sustains every control level.
The hierarchy of controls in ISO 45001:2018 comes under Clause 8.1.2 (Eliminating hazards and reducing OH&S risks), which is located within Clause 8 ("Operation"). ESEAP: Elimination, Substitution, Engineering controls, Administrative controls and PPE. Control order: HSE hierarchy of controls and IOSH hierarchy of control guidance.
What is the compact CDM study model?
Source: appointed-relevent-parties-cdm--study
Separate five decisions: project scope, number of contractors, capable written appointments, project information and plan, then the independent notification threshold. For IOSH Construction learning, explain who is the client, who actually controls design and construction phases, when the roles start, what each must pass on and what evidence proves coordination. This compact study model is a learning aid only. On a live project, use the current regulations and specific arrangements rather than memorising a generic role list.
Which CDM law applies in Great Britain and Northern Ireland?
Source: appointed-relevent-parties-cdm--legal
CDM 2015 is GB law; CDM (Northern Ireland) 2016 is the separate NI instrument. Similar duties do not make either instrument UK-wide. Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE CDM 2015 legal summary · HSENI CDM 2016 overview. Both regimes cover all in-scope construction projects and require written principal appointments where more than one contractor is involved or reasonably foreseeable. Both require a construction phase plan for every project and a health and safety file for a multi-contractor project. Domestic-client duty transfer is set out in each regime.
The notification test is more than 30 working days with more than 20 workers simultaneously at any point, or more than 500 person-days. Use GB F10 and NI NI10 respectively. A commercial client has the notification duty; on a domestic project regulation 7 passes that duty to the sole contractor, principal contractor or a principal designer with a written agreement to take client duties. Check each instrument for the project; NI schedules and numbering differ. Sources for this explanation: Construction (Design and Management) Regulations 2015; Construction (Design and Management) Regulations (Northern Ireland) 2016.
How could BuildOut Ltd run the appointment process?
Source: appointed-relevent-parties-cdm--business-example
BuildOut Ltd should use a project gate that links the client brief, contractor forecast, written roles, information flow and safe start decision. BuildOut Ltd undertakes construction and refurbishment. On a commercial roof project it asks whether two trades will be engaged, including specialist subcontractors at different stages. Its client representative appoints a capable principal designer while the roof and service design can still change, and a principal contractor with time to plan access, welfare, occupied-premises segregation and trade interfaces. BuildOut gives both principals existing drawings, surveys and service information. The principal contractor signs off a usable construction phase plan before mobilisation; the principal designer keeps design and future maintenance information coordinated.
The client reviews actual site controls and receives the health and safety file at hand-back. When a new trade or unknown service appears, the affected work stops while scope, roles and information are reset.
What competence, training and supervision are needed?
Source: appointed-relevent-parties-cdm--training
Match skills, knowledge, experience, organisational capability, training and supervision to the actual role and risk; no universal CDM card or certificate replaces that assessment. Clients need enough understanding to commission and check the roles, even if they seek specialist support. Principal designers need design control and the ability to coordinate significant risks; principal contractors need capacity to coordinate site work. Workers need relevant task instruction, site-specific induction and supervision. Use proportionate evidence, exercises and observed performance. A training card may help with an individual check, but it is not automatic proof that an organisation can lead this particular project. Record the project decision, dutyholder competence, assessor and reassessment trigger; a training card alone does not appoint a principal role.
Do standards or accreditations satisfy CDM?
Do standards or accreditations satisfy CDM?
Source: appointed-relevent-parties-cdm--standards
Voluntary management standards and procurement schemes may help organise assurance, but only the correct statutory roles and real project controls satisfy CDM duties. ISO 45001 can structure planning, responsibilities, worker participation, checking and improvement. It does not appoint a principal designer or principal contractor, prepare a project plan or prove site controls. Accreditation, insurance and RAMS may be useful evidence depending on the task, but they are not universal statutory appointment conditions. Standards for temporary works, equipment or building design may be relevant to a specific project and must be selected by a competent designer against the actual task.
How should leaders assure CDM delivery?
Source: appointed-relevent-parties-cdm--management-system
Review the quality of decisions and actual controls at project gates, not merely whether a form exists. Set responsibility for scope, appointment, information, plan, change and hand-back. Sample projects for early appointment, site-specific information, workable plans, welfare, worker consultation and file quality. Act on repeated late changes or unclosed defects. Keep a clear record of who authorised each hold and restart. Use incident and near-miss learning to improve design and procurement in the next project.
What indicates that CDM appointments are failing?
Source: appointed-relevent-parties-cdm--warning-signs
Late or unsigned appointments, a principal designer without design control, no plan before work or unmanaged trade interfaces need immediate correction. Other warning signs include generic information packs, undisclosed asbestos or services, a principal contractor with no time to plan, missing welfare, a plan that does not match the site, workers unable to identify the project lead, and a file assembled only after completion. Stop the affected work when a critical unknown or uncontrolled risk is present, then obtain the right design, management and site decision before restart.
Small single-contractor refurbishment
Source: appointed-relevent-parties-cdm--example--one-contractor
Task Material And Setting: BuildOut Ltd repairs a small office partition with one contractor and no expected trade subcontractors; the goal is safe hand-back. People And Prerequisites: Office users, contractor and visitors; locate services, asbestos information and occupied routes before starting. Before: Client identifies site constraints and selects a capable contractor; the contractor prepares a proportionate written construction phase plan and welfare arrangements. During: Contractor isolates services, segregates the occupied area and follows the plan; client coordinates building access. Hold Or Stop: Unexpected second contractor, unknown material or missing service data: stop affected work and reassess appointment and controls. Completion And Hand Back: Inspect finished area, reinstate routes and record any residual information needed for future work.
Evidence: Scope, contractor capability, pre-construction information, plan, permit if needed and hand-back.
Two trades working at different times
Source: appointed-relevent-parties-cdm--example--two-trades
Task Material And Setting: BuildOut Ltd commissions a roof repair followed by an electrician to reroute a cable; the goal is safe coordinated work. People And Prerequisites: Roofers, electrician, occupants and public; the trades need not be on site together for the multi-contractor trigger. Before: Client appoints a designer in control as principal designer and a contractor as principal contractor in writing before construction; checks capability and provides roof, access and service information. During: Principal designer resolves design and maintenance risks; principal contractor plans sequencing, edge protection, site controls and a construction phase plan. Hold Or Stop: No written appointment, unsafe access or unclear service isolation: hold the affected start and escalate to the client.
Completion And Hand Back: Principal designer or successor completes the health and safety file; client accepts the file and any residual risk information. Evidence: Written appointments, risk decisions, plan, coordination brief and file receipt.
A second contractor is added after mobilisation
Source: appointed-relevent-parties-cdm--example--late-subcontractor
Task Material And Setting: A sole-contractor fit-out needs a specialist ventilation installer after opening the ceiling; the goal is to reset control before interface work. People And Prerequisites: Both trades, BuildOut team and building users; concealed services and dust alter the sequence. Before: Pause and revise the project contractor forecast; the client makes written principal appointments as soon as practicable and checks whether the principal designer can influence remaining design. During: Share new information, revise the plan and coordinate access, isolation, temporary works and handover. Hold Or Stop: Do not let the specialist begin because the original job was called single-contractor; unknown ceiling materials or missing principal role means hold.
Completion And Hand Back: Update the file and drawings, verify services and close the change with client sign-off. Evidence: Change notice, appointments, revised plan, briefings and hand-back.
Domestic extension with several trades
Source: appointed-relevent-parties-cdm--example--home-extension
Task Material And Setting: A householder engages a builder, electrician and roofer for an extension; the goal is a safe domestic project. People And Prerequisites: Household members, neighbours and trades; the home is not being improved as a business activity. Before: Identify the designer in control and contractor in control. Domestic client duties normally pass to the principal contractor, or to the principal designer by written agreement; principal roles still apply. During: Principal contractor coordinates trades, site security, welfare and a plan; principal designer addresses build and future-maintenance risk. Hold Or Stop: No clear lead for the construction phase, unprotected household access or undocumented design change: stop and agree control.
Completion And Hand Back: Hand over relevant file information and make the home safe for use. Evidence: Role and duty transfer record, plan, site checks and file handover.
Design change during construction
Source: appointed-relevent-parties-cdm--example--design-change
Task Material And Setting: A beam position changes after BuildOut Ltd opens a floor; the goal is to avoid unsafe improvised support and future maintenance traps. People And Prerequisites: Workers, occupants and future maintainers; structural engineer and principal designer input are needed. Before: Record the changed condition and hold structural work pending competent design and temporary-works assessment. During: Designer checks buildability and future access; principal designer and contractor coordinate revised sequence and information. Hold Or Stop: No approved design, unclear load path or incompatible temporary works: stop and keep the area controlled. Completion And Hand Back: Verify as-built details, update the plan and health and safety file and authorise restart or hand-back. Evidence: Design instruction, calculations, briefings, inspection and updated file.
Large project notification decision
Large project notification decision
Source: appointed-relevent-parties-cdm--example--notification
Task Material And Setting: As a commercial client, BuildOut Ltd plans 35 working days with 20 workers at peak and 540 person-days; the goal is to notify the correct regulator while managing all duties. People And Prerequisites: Commercial client, designers, contractors and regulator; programme estimates are documented. Before: The 540 person-days exceeds the separate notification threshold even though peak staffing is below 21; the commercial client verifies the estimate and notifies HSE by F10 in GB or HSENI by NI10 in NI. During: Maintain written principal appointments because more than one contractor is expected, plus the plan, welfare and coordination. Hold Or Stop: Do not use notification as permission to start or assume a sub-threshold project is exempt from CDM.
Completion And Hand Back: Update notification if required and retain the submission with project records. Evidence: Programme calculation, appointments, plan and notification reference.
Unsafe opening and missing information
Source: appointed-relevent-parties-cdm--example--uncontrolled-opening
Task Material And Setting: During an occupied-building refurbishment, workers uncover an unrecorded void and damaged service; the goal is to protect people and reset the plan. People And Prerequisites: Workers, occupants and visitors; actual structure and energisation state are unknown. Before: Use site rules, reporting and a named authority for changed conditions; keep public access segregated. During: Stop the affected activity, make the area safe without disturbing the service, and obtain competent survey/design advice. Hold Or Stop: Do not proceed on an assumption that the drawing is current, or let another trade enter without revised information. Completion And Hand Back: Client, principal designer and principal contractor review revised design, plan, briefings and safe hand-back. Evidence: Stop record, survey, design decision, plan revision, briefing and release.
Decide scope, the plan and appointments before notification
Source: cdm--review-start
Keep three decisions visible. First identify construction work and the applicable GB or NI regime. Then establish who must prepare and use the construction phase plan and whether principal appointments are needed. Finally apply the separate notification test to the programme and labour forecast. Being below a notification threshold does not answer either planning question. Keep three decisions visible. First identify construction work and the applicable GB or NI regime. CDM makes clients, designers and contractors plan, coordinate and control construction risk from design through handover. Apply it: Which part of this plan would you check at the workface before authorising the task? CDM makes clients, designers and contractors plan, coordinate and control construction risk from design through handover.
Great Britain uses CDM 2015 and Northern Ireland uses CDM (NI) 2016. CDM project register. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Assess: Screens project scope, dutyholder role, notification, high-risk work and information needs. Evidence / response: CDM project register. Analyse: Reviews design risk, site constraints, services, asbestos, welfare and contractor interfaces. Evidence / response: PCI review and risk workshop. Apply it: At which point would you hold this example, and what evidence would allow it to proceed? Late appointments: Design and planning risk is missed. Generic CPP: Real site risks are not controlled. Missing PCI: Asbestos, services or structural hazards are discovered late.
Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Avoid risks: Remove hazards through design or method. Evaluate unavoidable risks: Assess remaining risks before work starts. Combat risks at Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision?
Keep one card or the full set for social sharing, team briefings and learning. Each PDF contains one card per page. Read the full topic for explanations, questions and source links. Keep three decisions visible. Keep three decisions visible. First identify construction work and the applicable GB or NI regime. CDM makes clients, designers and contractors plan, coordinate and control construction risk from design through handover. Apply it: Which part of this plan would you check at the workface before authorising the task? Use the evidence to improve the actual work arrangement. CDM makes clients, designers and contractors plan, coordinate and control construction risk from design through handover. Great Britain uses CDM 2015 and Northern Ireland uses CDM (NI) 2016. CDM project register.
Apply it: What evidence would show that the change improves this task, rather than only completing a record? Fictional example: a practical application of the existing topic lesson. Assess: Screens project scope, dutyholder role, notification, high-risk work and information needs. Evidence / response: CDM project register. Analyse: Reviews design risk, site constraints, services, asbestos, welfare and contractor interfaces. Evidence / response: PCI review and risk workshop. Apply it: At which point would you hold this example, and what evidence would allow it to proceed? Connect the task, the route to the person and the control that can fail. Late appointments: Design and planning risk is missed. Generic CPP: Real site risks are not controlled. Missing PCI: Asbestos, services or structural hazards are discovered late.
Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Start with the stronger practicable options and verify their effect. Avoid risks: Remove hazards through design or method. Evaluate unavoidable risks: Assess remaining risks before work starts. Combat risks at Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Follow the official sources below and retain the task-specific evidence. Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status.
Apply it: Which official source and full-topic section will you use to resolve the next decision? Simplified learning guide. Use the full topic and the actual work arrangements; existing technical-review and approval statuses still apply. Workplace scenarios labelled fictional are illustrative examples. Follow a small repair as the scope changes. One contractor plans the initial work; when a second trade is likely to join, the client must revisit the principal-role decision and coordination before that work starts. Use
CDM Dutyholders and Appointments
for the appointment evidence and Construction Phase Plan for the live site arrangements. For a domestic project, use the existing client-transfer explanation rather than assuming the householder carries every commercial-client task. Illustrative example. A fictional single-contractor repair expands to include a separate electrical contractor. Decision. The client and project lead revisit principal appointments and coordination, and revise the plan before the additional work begins. Evidence to check. Work scope, contractor forecast, role and appointment record, live plan and separate notification calculation. Hold or escalation point. Hold the changed work if the responsible roles or coordination arrangements are unresolved. Follow-up. Review programme, interfaces and the notification forecast whenever scope or labour changes. Read with: HSE CDM 2015 · HSE CDM FAQ · HSE dutyholder responsibilities.
Coordinate the project before work begins
Coordinate the project before work begins
Source: cdm--practical-cdm
Client information, design coordination and construction-phase planning form a connected route. Notification is a separate check, rather than permission to start unsafe work. Establish the work, location, parties and pre-construction information, including what is uncertain. Apply the relevant single/multiple-contractor arrangements and principal roles where required. Information must reach those who need it to plan and control the work. Prepare and use the construction phase plan; check welfare, interfaces, responsibilities and changes. Consider the applicable notification requirement separately. The location marker and records are teaching aids, not a service survey, excavation permit or automatic confirmation of CDM compliance. Further guidance: HSE: construction.
What are the key facts about CDM?
Source: cdm--key-facts
The key facts are that CDM applies across the project lifecycle, assigns dutyholders and requires risk control before work starts.
What are the Construction Design and Management Regulations?
Source: cdm--what-is-it
The Construction Design and Management Regulations are construction health and safety regulations that require projects to be planned, coordinated and controlled from concept to completion. CDM exists because construction risks are often created long before a worker steps onto site. A design can make roof access safer or dangerous. A client can allow enough time and budget or force rushed work. A contractor can plan a safe sequence or improvise around missing information. The regulations create named dutyholders so responsibility does not disappear between organisations. They require cooperation, coordination and communication between the people who commission, design and build.
A strong CDM project feels organised: the right people are appointed early, hazards are known, the construction phase plan is specific, welfare is ready, workers are briefed, contractors are coordinated and the health and safety file is useful at handover.
What work is covered by CDM?
Source: cdm--scope
CDM covers a wide range of building, civil engineering and engineering construction work, including construction, alteration, repair, maintenance, demolition and dismantling. CDM is broader than many people think. It can apply to new build, refurbishment, fit-out, demolition, maintenance, repair, redecoration, commissioning, decommissioning, excavation, site clearance, service installation and work on structures. The practical test is not whether the job feels large or formal. The question is whether construction work is being carried out. A one-day roof repair, intrusive maintenance task or small commercial refurbishment can still need CDM planning. Some routine activities may sit outside CDM if they are not construction work, but they may still fall under other health and safety law.
When in doubt, the safer professional approach is to define the work, identify hazards and plan proportionate controls.
How do the general principles of prevention shape CDM?
Source: cdm--principles
The general principles of prevention require dutyholders to avoid risks where possible and control unavoidable risks at source. CDM is built around prevention. Designers and contractors should not jump straight to PPE or warning signs. They should first ask whether the hazard can be avoided, designed out, substituted, isolated or controlled by safer sequencing and collective measures. This is why early design review is so powerful. A permanent edge-protected access route is better than repeated scaffold improvisation. Ground beams designed around known services are better than discovering utilities during excavation. A maintained plantroom with access space is better than forcing future maintenance into awkward or unsafe positions.
The prevention principles also support better health control: design out silica cutting where possible, plan dust control, avoid manual handling through mechanical aids and ensure welfare is available from the start.
Who are the CDM dutyholders?
Source: cdm--dutyholders
The CDM dutyholders are clients, designers, principal designers, principal contractors, contractors and workers. Each dutyholder has a different influence point. Clients control brief, time, budget and appointments. Designers influence risk through design. Principal designers coordinate pre-construction risk. Principal contractors coordinate construction. Contractors control their own work. Workers cooperate and report risks. The principal designer and principal contractor must be appointed in writing where the project involves, or is likely to involve, more than one contractor. If the client fails to appoint them when required, the client can retain duties that should have been properly allocated. Domestic clients are treated differently from commercial clients. In most domestic projects, the client duties pass to other dutyholders unless specific written arrangements are made.
Which CDM documents are most important?
Source: cdm--documents
The central CDM records are useful pre-construction information, a construction phase plan, a health and safety file where required, and location-specific notification when the threshold is met. CDM paperwork should help people make decisions. It should not exist as a disconnected pack of generic templates. Pre-construction information should tell the project team about existing hazards and constraints. The construction phase plan should explain how the actual work will be managed. The health and safety file should help future work be safer. A small project may need a simple construction phase plan. A complex project may need detailed sequencing, interface management, emergency arrangements, temporary works, fire strategy, logistics and contractor coordination. The best documents are updated as the project changes.
If asbestos, buried services, design changes, temporary works, weather, lifting plans or sequencing changes, the documents should change too.
When must a construction project be notified?
Source: cdm--notification
CDM applies before notification is considered. Notify only if a statutory threshold is forecast to be met, using the correct GB or NI regulator route. Both HSE and HSENI describe a project as notifiable when construction work is scheduled to last longer than 30 working days and have more than 20 people on site at any time, or when it exceeds 500 person-days. The tests are alternatives. Keep a dated programme and labour forecast, review them as the project changes and notify in time when the test is met. These thresholds do not decide whether a principal designer, principal contractor, construction phase plan, welfare or cooperation are needed.
In Great Britain the client normally uses HSE’s F10 route, with special arrangements for domestic projects and some regulator-specific sites. In Northern Ireland the client notifies HSENI under CDM (NI) 2016 using its NI route, commonly NI10; the GB F10 is not the NI notification. Verify the receiving authority and form on the current regulator page, especially for specialist sites. The HSENI NI10 PDF linked below is marked non-accessible; request an accessible route from HSENI if needed.
What should happen during the pre-construction phase?
What should happen during the pre-construction phase?
Source: cdm--preconstruction
The pre-construction phase should identify foreseeable risks, plan design decisions, provide information and prepare for safe construction. Pre-construction is where the project can avoid many hazards cheaply and intelligently. The team should review site constraints, asbestos, surveys, buried services, ground conditions, access, public interface, existing structures, temporary works, logistics, fire, lifting, health risks and future maintenance. The principal designer coordinates health and safety in the pre-construction phase on multi-contractor projects. Designers should not simply pass every risk to the contractor. They should eliminate where possible, reduce where they cannot eliminate, and communicate significant residual risks clearly. The client should ensure enough time and resources are available. Rushed design, poor surveys and late contractor appointment often create avoidable risk on site.
How should the construction phase be controlled?
Source: cdm--construction-phase
The construction phase should be controlled through a project-specific plan, coordination, supervision, communication, welfare, inspections and change control. The construction phase plan should be in place before construction begins. It should explain how the site will be managed, how high-risk work will be controlled, how contractors will coordinate, how the public will be protected and how emergency arrangements will work. The principal contractor coordinates the construction phase on multi-contractor projects. That means more than collecting RAMS. It includes site induction, sequencing, interface management, traffic routes, fire control, temporary works, welfare, worker consultation and monitoring that controls are actually used. Change control is essential. Design changes, additional trades, late materials, weather, sequencing changes and unexpected ground or structural conditions can all create new risks.
What welfare arrangements are required under CDM?
Source: cdm--welfare
CDM requires suitable welfare facilities to be available from the start and maintained throughout construction work. Welfare is a basic control, not a comfort extra. Toilets, washing facilities, drinking water, rest areas, changing facilities and arrangements for hot food or drink where needed all affect hygiene, dignity, fatigue, dust control, skin protection and worker welfare. Poor welfare undermines health controls. Workers exposed to cement, dust, asbestos, lead, biological agents or contaminated ground need washing and changing arrangements. Workers doing hard physical work need rest and hydration. Clients and contractors should confirm welfare arrangements before work starts, especially on short projects where teams may otherwise improvise.
What should happen at handover and close-out?
Source: cdm--handover
CDM close-out should provide useful health and safety information for future operation, maintenance, cleaning, refurbishment and demolition. The health and safety file should not be a box of unused documents. It should tell future dutyholders what they need to know: residual structural risks, maintenance access, buried services, asbestos information, fire precautions, plant details, hazardous materials and unusual design assumptions. The principal designer prepares and updates the health and safety file during the project, then it is handed to the client. If the principal designer's appointment ends before the project finishes, arrangements are needed so the file remains current. Close-out should also review lessons learned. Design decisions, contractor performance, incidents, near misses and late changes should feed into future projects.
How should CDM compliance be checked?
Source: cdm--assurance
CDM compliance should be checked through active monitoring, document review, site verification, worker feedback and close-out evidence. A CDM audit should not only check whether documents exist. It should test whether the documents are useful, current and being used by the people making decisions. First-line assurance is daily supervision: inductions, briefings, permits, welfare checks and control observations. Second-line assurance is project or H&S review: appointments, PCI, CPP, design risk, contractor performance and inspections. Third-line assurance is independent audit or client review of the project management system. Findings should be ranked and assigned to named owners. A finding is not closed because someone updates a document; it is closed when the corrected arrangement is working on site.
Which legal duties apply to CDM?
Source: cdm--legal
Use CDM 2015 for Great Britain and CDM (Northern Ireland) 2016 for Northern Ireland; check hazard-specific law in the same jurisdiction. Clients must make suitable arrangements and provide relevant pre-construction information. Where more than one contractor is involved or likely, the principal designer and principal contractor roles need appointment; the construction phase plan is not limited to notifiable jobs. Designers eliminate or reduce foreseeable risk and pass on significant residual information. Contractors plan, manage and monitor their work and cooperate with the project team. The precise legal route and any domestic-client transfer depend on GB or NI law and project facts. England Building Regulations dutyholder roles are a separate building-control regime.
A project may need both sets of decisions, but do not treat England building-control law as GB-wide or NI CDM law. Work at height, asbestos, fire, lifting and welfare obligations also require their own location-specific legal check.
How could BuildOut Ltd manage CDM?
Source: cdm--business-example
BuildOut Ltd would manage CDM through a project register, appointment checks, design-risk coordination, construction phase planning, welfare verification, contractor control and handover close-out. a fictional construction and fit-out contractor delivering refurbishment, small works, maintenance, demolition-enabling works and multi-trade commercial projects BuildOut starts every job with a CDM triage. The project coordinator records the client, site, scope, number of contractors, likely notification status, high-risk activities, existing information, required appointments and whether BuildOut is acting as contractor, principal contractor or designer. For multi-contractor work, written appointment checks are completed before the construction phase begins. The project team collects pre-construction information such as asbestos surveys, service drawings, structural information, access restrictions, fire constraints, public interface, welfare and emergency arrangements.
During construction, the site manager works from a project-specific construction phase plan. Subcontractors are coordinated through pre-start meetings, daily briefings, permits, inspections and change control. Welfare is checked before mobilisation and weekly thereafter. Design changes are fed back to the principal designer and the health and safety file owner. BuildOut uses assurance at three levels. Supervisors complete binary site checks. H&S advisers review higher-risk projects and sample evidence. Senior management reviews project close-out, incidents, contractor performance and health and safety file quality. Actions are ranked, owned and verified before closure.
What should each role learn and demonstrate?
What should each role learn and demonstrate?
Source: cdm--training
Learning must match the decisions people make, from recognising danger to checking that controls work. Briefings should tell people how to act, but attendance alone does not show competence. Assess the real decision or task, record who assessed it and revisit after a material change, failed control or incident. A local authorisation is task-specific; no universal external certificate is implied.
How does CDM support qualification study and professional development?
Source: cdm--study-development
CDM helps learners understand construction risk governance, dutyholders, planning, coordination, welfare and control of high-risk work. For the IOSH Construction Certificate, CDM is a core organising topic. Learners should know the dutyholders, project documents, notification thresholds, welfare expectations, construction phase controls and how design risk is eliminated or reduced. For the IOSH National General Certificate, CDM supports contractor control, management arrangements, risk assessment and construction hazards. For Diploma study, it supports governance, assurance, lifecycle risk and client leadership. A strong scenario answer should explain who should have done what, when. CDM questions are rarely just about a form; they are about whether dutyholders planned, coordinated and monitored the work well enough to prevent harm.
How can a management system sustain effective decisions?
Source: cdm--management-system
Give each hazard or support route an owner, a control, a check and a response to failure. Project records should show early appointments, design decisions, construction phase plan updates, site observations, worker consultation and useful handover information. A leader should test an actual change in design or programme and verify that the right dutyholders and controls were updated. An owner should sample actual work and corrective actions, not accept a policy or certificate as evidence that the controls work. The free GB regulator guide HSE Managing for health and safety (HSG65) explains a plan–do–check–act approach: assign controls and owners, involve workers, check work as done, and correct failures. For Northern Ireland, use HSENI risk assessment guidance for the local duty.
A certificate alone does not demonstrate that a control works.
What are the warning signs that CDM is not being managed?
Source: cdm--warning-signs
Warning signs include late appointments, generic plans, missing pre-construction information, poor welfare, weak contractor control and no useful handover file. CDM failure usually shows before an accident. The client cannot explain arrangements. The principal designer is appointed after design decisions are made. The principal contractor receives little information. Contractors arrive with generic RAMS. Welfare is incomplete. Workers do not understand the plan. Another warning sign is paperwork without influence. If the construction phase plan does not shape inductions, logistics, permits and inspections, it is not controlling the job. Poor close-out also matters. If the health and safety file is incomplete, future maintenance workers inherit risk that could have been communicated.
Show how the live plan changes the workface
Source: construction-phase-plan--review-start
A meaningful small-job plan names the work and responsible people, the actual site hazards and controls, access, welfare, emergency arrangements and how change will be managed. It should be short enough to use and specific enough to guide the first day. Notification is a separate decision, not an exemption from planning. A meaningful small-job plan names the work and responsible people, the actual site hazards and controls, access, welfare, emergency arrangements and how change will be managed. It should be short enough to use and specific enough to guide the first day. Every construction project needs a suitable construction phase plan before construction begins. Apply it: Which part of this plan would you check at the workface before authorising the task?
Every construction project needs a suitable construction phase plan before construction begins. Make it proportionate to the work, with site rules, management arrangements and specific GB Schedule 3 / NI Schedule 4 risk measures. CPP, PCI review and project risk register. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Assess and plan: Uses tender and pre-construction information to prepare project-specific CPPs. Evidence / response: CPP, PCI review and project risk register. Implement: Turns CPP into site rules, inductions, RAMS, permits and inspections. Evidence / response: Induction records, site plan and permit pack. Apply it: At which point would you hold this example, and what evidence would allow it to proceed?
Generic plan: The CPP may not reflect site risk. No welfare detail: Basic legal and worker needs may be missed. No GB Schedule 3 / NI Schedule 4 consideration: High-risk work may be underplanned. Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Eliminate: Redesign service route to avoid cutting where feasible. Substitute: Use prefabricated or lower-dust method after compatibility check. Engineering: Matched dust capture and a physical occupied-area boundary. Administrative: Permit, access schedule, briefing and inspection. PPE: Task RPE for residual exposure, not substitute for source capture. Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged.
Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision? Keep one card or the full set for social sharing, team briefings and learning. Each PDF contains one card per page. Read the full topic for explanations, questions and source links.
A meaningful small-job plan names the work and responsible people, the actual site hazards and controls, access, welfare, emergency arrangements and how change will be managed. A meaningful small-job plan names the work and responsible people, the actual site hazards and controls, access, welfare, emergency arrangements and how change will be managed. It should be short enough to use and specific enough to guide the first day. Every construction project needs a suitable construction phase plan before construction begins. Apply it: Which part of this plan would you check at the workface before authorising the task? Use the evidence to improve the actual work arrangement. Every construction project needs a suitable construction phase plan before construction begins.
Make it proportionate to the work, with site rules, management arrangements and specific GB Schedule 3 / NI Schedule 4 risk measures. CPP, PCI review and project risk register. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Fictional example: a practical application of the existing topic lesson. Assess and plan: Uses tender and pre-construction information to prepare project-specific CPPs. Evidence / response: CPP, PCI review and project risk register. Implement: Turns CPP into site rules, inductions, RAMS, permits and inspections. Evidence / response: Induction records, site plan and permit pack. Apply it: At which point would you hold this example, and what evidence would allow it to proceed?
Connect the task, the route to the person and the control that can fail. Generic plan: The CPP may not reflect site risk. No welfare detail: Basic legal and worker needs may be missed. No GB Schedule 3 / NI Schedule 4 consideration: High-risk work may be underplanned. Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Start with the stronger practicable options and verify their effect. Eliminate: Redesign service route to avoid cutting where feasible. Substitute: Use prefabricated or lower-dust method after compatibility check. Engineering: Matched dust capture and a physical occupied-area boundary. Administrative: Permit, access schedule, briefing and inspection. PPE: Task RPE for residual exposure, not substitute for source capture.
Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged. Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Follow the official sources below and retain the task-specific evidence. Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision? Simplified learning guide.
Use the full topic and the actual work arrangements; existing technical-review and approval statuses still apply. Workplace scenarios labelled fictional are illustrative examples. Check one plan action at the workface: for example, can the promised welfare be used and does the public exclusion route match the occupied building? If a second trade, intrusive work or a changed access route is introduced, revisit coordination, role decisions and briefings before that scope starts. Use CDM and the appointment guide for those separate decisions rather than duplicating them inside the plan. Illustrative example. A fictional single-contractor domestic repair expands into a more intrusive package involving another trade. Decision. The project lead revises the live arrangements and checks the client and principal-role decisions before the changed work.
Evidence to check. Current scope, site information, welfare and access checks, role decisions and workers’ understanding of revised controls. Hold or escalation point. Do not start changed work using a plan that describes only the original repair. Follow-up. Verify at the workface that the new exclusion and welfare arrangements work, then retain the revision reason. Read with: HSE planning for construction work · HSE principal contractor duties · HSE CIS80 construction phase plan.
Make the plan match today’s workface
Make the plan match today’s workface
Source: construction-phase-plan--practical-construction-phase-plan
A useful small-job plan connects people, sequence, controls, welfare and emergency access to the actual site. Update it when conditions change. Name who controls the work and describe the activity sequence and interfaces with occupied areas. Show welfare, emergency access, public boundaries and the particular controls needed for the job. Brief those doing the work, check the site matches the plan and revise it after relevant change. A plan extract is not a service survey, temporary-works design or excavation release. Further guidance: HSE: construction.
What are the key points about construction phase plans?
Source: construction-phase-plan--key-points
The key points are that the CPP is required before work starts, must be proportionate, must be project-specific and must be used as a live control document.
What is a construction phase plan?
Source: construction-phase-plan--what-is-it
A construction phase plan is the written project plan for managing health, safety and welfare during construction work. The CPP sits between pre-construction planning and work as done on site. It should take the project information, design decisions, known hazards, site constraints and programme, then explain how the construction phase will be organised and controlled. Its value is practical: it gives the project team a common operating framework before people, plant and materials arrive on site. A good CPP is specific to the project. It identifies who is in charge, how contractors will cooperate, what site rules apply, what welfare is provided, how emergencies will be managed, which high-risk activities need special arrangements and how the principal contractor or contractor will monitor the work.
The plan should be detailed enough to manage foreseeable risks but simple enough for the project team to use. A long generic document can fail because people cannot find the controls that matter. A short plan can be suitable for simple work if it genuinely covers the risks and arrangements.
When is a construction phase plan required?
Source: construction-phase-plan--when-required
Prepare it before construction starts for every construction project; notification thresholds and principal-contractor appointment are separate tests. The HSE planning page states that a plan is required for a GB project whether one or several contractors are involved. The contractor prepares it on a single-contractor project; the principal contractor prepares it on a project with more than one contractor. HSENI’s CDM 2016 page sets out the NI route and also requires a plan for all projects. A project can need a plan without meeting the separate regulator-notification threshold. The plan must exist before work, not be completed after mobilisation.
Who is responsible for the construction phase plan?
Source: construction-phase-plan--dutyholders
Responsibility depends on the project structure, but the principal contractor or contractor must prepare the plan before construction begins. The client must make suitable arrangements for managing the project and ensure that the principal contractor or contractor has enough time and resources to plan the work safely. The principal designer provides relevant information from the pre-construction phase, including design risks and information needed for the construction phase. The principal contractor leads planning, management, monitoring and coordination during the construction phase where more than one contractor is involved. They must prepare, implement, review and revise the CPP. Contractors must cooperate, follow the plan, provide information about their work and manage the health and safety of their own workers.
How can the ISO 45001 hierarchy of controls guide risk controls in a construction phase plan?
Source: construction-phase-plan--contents
State how the project will be managed and how its actual high-risk work will be controlled, rather than filing generic policies. Use project scope, site layout, named dutyholders, site rules, access, welfare, emergency and first aid arrangements, consultation, coordination and change control. For GB Schedule 3 / NI Schedule 4 work, identify the specific risk and controls. On a refurbishment beside occupied offices, locate the dust boundary, lifting route, isolation, fire compartmentation and public interface, with owners and hold points. Link to detailed methods and permits without dumping every document into the plan. HSE L153 supports a proportionate approach. ERICPD is a planning crossmap. Its prompts do not add a sixth rung or rank Isolate above engineering. Discipline verifies and sustains every control level.
The hierarchy of controls in ISO 45001:2018 comes under Clause 8.1.2 (Eliminating hazards and reducing OH&S risks), which is located within Clause 8 ("Operation"). ESEAP: Elimination, Substitution, Engineering controls, Administrative controls and PPE. Control order: HSE hierarchy of controls and IOSH hierarchy of control guidance. HSE’s five-level hierarchy sets out elimination, substitution, engineering, administrative controls and PPE for GB. ERICPD is complementary. Choose measures for the actual task and location, and verify physical control performance separately from briefing or permit completion. For the occupied-office cut, HSE capture guidance informs the matched equipment checks. Before authorising cutting, the site manager verifies capture, airflow and the physical boundary against the actual material and layout. Maintain the system and check before each phase and during work.
Failed capture or boundary integrity holds cutting; restore and verify performance before recorded restart. A permit or briefing does not establish physical control performance.
How should GB Schedule 3 / NI Schedule 4 high-risk work be addressed?
Source: construction-phase-plan--schedule-3
GB Schedule 3 / NI Schedule 4 work should be identified in the CPP with specific measures rather than buried in generic risk assessments. GB CDM 2015 Schedule 3 and NI CDM 2016 Schedule 4 identify work involving particular risks. See the NI statutory rule for the local list. These are not the only risks that matter, but they are a strong prompt for the CPP because they often need extra planning, competence, supervision, permits, design input or specialist control. The plan should explain how these risks will be managed for the actual project.
How does pre-construction information feed into the CPP?
Source: construction-phase-plan--pre-construction
Pre-construction information should give the principal contractor or contractor the information needed to plan the construction phase safely. The CPP should not be written in isolation. It should be shaped by information from the client, principal designer, designers, surveys, investigations, existing building information, asbestos records, service drawings, ground information, structural constraints, occupancy, public interfaces and environmental conditions. Weak CPPs often fail because the plan does not absorb design and site information. For example, a refurbishment CPP that ignores asbestos records, hidden services, occupied-building constraints or fragile rooflights will not manage the real project risk.
How should the CPP be kept live?
How should the CPP be kept live?
Source: construction-phase-plan--live-document
The CPP should be reviewed and revised whenever the work, people, sequence, risks or controls change. A construction site changes constantly. New subcontractors arrive, workfaces open and close, temporary works are installed, weather changes, materials are delivered, access routes move and design queries arise. A CPP that is not reviewed becomes less reliable as the project progresses. Keeping the plan live does not mean rewriting it every day. It means having a clear process for updates, version control, briefing changes and checking that revised arrangements are actually used. Changes should flow into inductions, toolbox talks, RAMS, permits, site rules, drawings and inspection checks.
What should a small-project construction phase plan include?
Source: construction-phase-plan--small-projects
A small-project CPP should be simple, proportionate and focused on the real risks of the job. Small projects still need a plan, but they do not need a large corporate manual. A good small-project CPP may be a concise document that sets out the job, who is responsible, site rules, welfare, emergency arrangements, key hazards, controls, workers involved and how changes will be handled. The danger with small jobs is informality. Short duration does not remove the need to control asbestos, work at height, electricity, dust, manual handling, welfare, public protection or fire. The plan should help the contractor think before work starts.
How do GB and NI routes differ?
Source: construction-phase-plan--devolved
The plan requirement is shared in purpose but GB CDM 2015 and NI CDM 2016 are separate instruments and regulators. In GB, HSE principal-contractor guidance assigns the plan to the principal contractor on multi-contractor work and to the contractor on a single-contractor project. In NI, HSENI CDM 2016 gives corresponding local roles. The relevant client appoints principal dutyholders when there is more than one contractor; domestic-client arrangements need the local guidance checked. Notification to HSE or HSENI is a distinct threshold and does not excuse a missing plan.
How does the CPP link to building safety and the health and safety file?
Source: construction-phase-plan--building-safety
The CPP should control construction-phase risk while also helping capture information needed for future maintenance, use and alteration. The CPP is primarily about health and safety during construction, but it should connect to the information flow for the completed asset. Design changes, temporary works decisions, concealed services, fire-stopping, structural changes, access arrangements and residual hazards may need to be captured for the health and safety file or wider building information requirements. For applicable higher-risk building work in England, the CPP should not be treated as the only compliance document. It should sit alongside building regulation, fire safety, quality assurance and golden-thread information arrangements so construction decisions are controlled and recorded properly. The construction phase plan is required for every project.
GB L153 distinguishes the health and safety file, required for projects involving more than one contractor, from the plan. NI has its separate CDM 2016 instrument and local file/plan duties. For applicable higher-risk building work in England, BSR golden-thread guidance describes client, principal designer and principal contractor information arrangements. Do not apply that England regime as a UK-wide rule. Capture relevant as-built information through controlled updates and handover.
What evidence shows a CPP is working?
Source: construction-phase-plan--evidence
Evidence should show that the CPP is understood, implemented, checked and updated during the project. A CPP that sits in a file is not evidence of control. Useful evidence includes inductions, site-rule briefings, supervisor inspections, contractor coordination meetings, permit records, welfare checks, emergency drills, action close-out, design change briefings, worker consultation and revision history. Field evidence matters. If the CPP says pedestrians are segregated but the site layout shows workers crossing plant routes, the plan is not working. If it says welfare is available but washing facilities are missing, the plan is not working. If it says high-risk work is controlled by permits but permits are copied or missing, the plan is not working.
Which legal duties and thresholds matter?
Source: construction-phase-plan--legal
Plan duty, principal appointments and project notification are distinct decisions; apply the work-location instrument. GB CDM 2015 requires a suitable construction phase plan before the construction phase begins; the HSE planning page explains roles. The NI CDM 2016 statutory rule governs NI. The plan should set out site rules and specific measures for GB Schedule 3 / NI Schedule 4 work, as set out in the linked NI statutory rule. A domestic or small job still needs a proportionate plan; a complex project needs more depth. Check notification and appointment facts separately, and review the plan whenever sequence, contractor interfaces or hazards change.
How could BuildOut Ltd manage construction phase plans?
Source: construction-phase-plan--business-example
BuildOut Ltd would manage CPPs as live project control documents linked to tender planning, site setup, contractor coordination, inspections and project review. A fictional construction and refurbishment contractor delivering fit-out, maintenance, civils, small demolition, plant operations, subcontracted specialist work and multi-site projects. BuildOut creates a CPP before work starts for each project. For a simple single-contractor job, the plan is concise and covers site rules, welfare, emergency arrangements and key task controls. For multi-contractor refurbishment, the plan includes dutyholder appointments, pre-construction information, asbestos and services information, traffic routes, public protection, fire arrangements, temporary works, permits, contractor coordination and inspection frequency. The site manager uses the CPP during induction, daily briefings and subcontractor coordination.
High-risk work such as hot works, lifting, demolition, excavation, electrical isolation, work at height and confined spaces is controlled through RAMS, permits, competent supervisors and field checks. The CPP revision log is updated when design changes, new contractors arrive or the site layout changes. BuildOut's regional manager audits CPP quality by sampling whether the plan matches the site. They check welfare, traffic segregation, emergency routes, work-at-height controls, dust controls, contractor briefings, permit quality and action close-out. Lessons from incidents and near misses are fed back into future CPP templates and supervisor training.
What should each role learn and demonstrate?
Source: construction-phase-plan--training
Learning must match the decisions people make, from recognising danger to checking that controls work. Briefings should tell people how to act, but attendance alone does not show competence. Assess the real decision or task, record who assessed it and revisit after a material change, failed control or incident. A local authorisation is task-specific; no universal external certificate is implied.
How can a management system sustain effective decisions?
How can a management system sustain effective decisions?
Source: construction-phase-plan--management-system
Give each hazard or support route an owner, a control, a check and a response to failure. Keep plan, site controls, worker feedback, inspections and changes connected. Audit actual boundaries and hold points rather than document completion alone. An owner should sample actual work and corrective actions, not accept a policy or certificate as evidence that the controls work. The free GB regulator guide HSE Managing for health and safety (HSG65) explains a plan–do–check–act approach: assign controls and owners, involve workers, check work as done, and correct failures. For Northern Ireland, use HSENI risk assessment guidance for the local duty. A certificate alone does not demonstrate that a control works.
What warning signs show a construction phase plan is weak?
Source: construction-phase-plan--warning-signs
Warning signs include generic wording, missing site rules, poor welfare, absent GB Schedule 3 / NI Schedule 4 controls, unmanaged contractors and a plan that is not updated when the site changes. A weak CPP usually looks either too thin or too bloated. A plan that says little about the real project will not guide the work. A huge generic file may hide the important controls. The practical test is whether a supervisor, worker or contractor can use the plan to understand how the site is controlled today.
Documents to download
Source: construction-phase-plan--editable-documents
Download editable resources from the SHAREhub environment. Checklists, forms and spreadsheets are blank; procedures contain a complete example to adapt.
Construction project risk register
: Blank register. Record construction point risks, existing controls, further actions and verification, with an illustrative scoring guide. Corrective action tracker: Blank tracker. Track owners, due dates, completion evidence and verification, with overdue alerts and a completion guide.
Corrective action management procedure
: Completed example procedure. A complete example workflow for assigning actions, reviewing progress, escalating delays and verifying effective closure.
Source tables and records 1
CDM role-based action routes
Table ID: appointed-relevent-parties-cdm-role-routes
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Role
Commercial client or project sponsor
- Act before or during work
Define scope, time and resources; make required written principal appointments and provide pre-construction information.
- Evidence and hold point
Appointment record, information issue and project gates; hold a start with missing roles.
Row 2
- Role
Domestic client
- Act before or during work
Ask who is in control; client duties normally pass to the sole or principal contractor, or principal designer by written agreement.
- Evidence and hold point
Record the actual lead and give property information; do not assume a householder performs professional CDM duties.
Row 3
- Role
Principal designer and designers
- Act before or during work
Eliminate or reduce foreseeable risks through design and coordinate design information.
- Evidence and hold point
Design risk decisions and file inputs; stop unclear design or unsafe change.
Row 4
- Role
Principal contractor and contractors
- Act before or during work
Prepare or follow the plan, coordinate trades, welfare, induction, site access and worker consultation.
- Evidence and hold point
Plan, briefings and site checks; hold work at uncontrolled interfaces.
Row 5
- Role
Workers and supervisors
- Act before or during work
Follow site rules, cooperate, report danger and raise changed conditions.
- Evidence and hold point
Briefing and stop/report route; do not improvise through missing information.
Row 6
- Role
Procurement, safety and audit roles
- Act before or during work
Check proportionate capability, role scope, information flow and actual implementation.
- Evidence and hold point
Project-specific assessment and verified closure, not certificate collection alone.
Read the complete comparison table
| Row | Role | Act before or during work | Evidence and hold point |
|---|---|---|---|
| 1 | Commercial client or project sponsor | Define scope, time and resources; make required written principal appointments and provide pre-construction information. | Appointment record, information issue and project gates; hold a start with missing roles. |
| 2 | Domestic client | Ask who is in control; client duties normally pass to the sole or principal contractor, or principal designer by written agreement. | Record the actual lead and give property information; do not assume a householder performs professional CDM duties. |
| 3 | Principal designer and designers | Eliminate or reduce foreseeable risks through design and coordinate design information. | Design risk decisions and file inputs; stop unclear design or unsafe change. |
| 4 | Principal contractor and contractors | Prepare or follow the plan, coordinate trades, welfare, induction, site access and worker consultation. | Plan, briefings and site checks; hold work at uncontrolled interfaces. |
| 5 | Workers and supervisors | Follow site rules, cooperate, report danger and raise changed conditions. | Briefing and stop/report route; do not improvise through missing information. |
| 6 | Procurement, safety and audit roles | Check proportionate capability, role scope, information flow and actual implementation. | Project-specific assessment and verified closure, not certificate collection alone. |
Project route and required actions
Table ID: appointed-relevent-parties-cdm-decision-route
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Situation
One contractor expected
- Appointment and document route
No principal designer or principal contractor appointment solely for this project; sole contractor prepares a construction phase plan before work.
- Do not confuse with
Notification may still apply if its separate threshold is reached.
Row 2
- Situation
More than one contractor expected or reasonably foreseeable
- Appointment and document route
Commercial client appoints both principal roles in writing as soon as practicable and before construction; principal contractor plans the phase and the health and safety file is prepared. For domestic clients, use the regulation 7 defaults below.
- Do not confuse with
Trades need not overlap on site.
Row 3
- Situation
Domestic project
- Appointment and document route
On a multi-contractor domestic job, client duties normally pass to the principal contractor or contractor in control, unless the principal designer accepts them by written agreement. If the householder makes no principal appointments, regulation 7 places principal-designer duties on the designer in control and principal-contractor duties on the contractor in control.
- Do not confuse with
Do not call a business landlord a domestic client.
Row 4
- Situation
Notification threshold reached
- Appointment and document route
For a commercial project the client notifies HSE via F10 in GB or HSENI via NI10 in NI. On a domestic project, regulation 7 transfers the regulation 6 notification duty to the sole contractor, principal contractor or principal designer under a written client-duty agreement. Keep appointment and notification tests separate.
- Do not confuse with
Notification is not permission to start and is not the appointment trigger.
Read the complete comparison table
| Row | Situation | Appointment and document route | Do not confuse with |
|---|---|---|---|
| 1 | One contractor expected | No principal designer or principal contractor appointment solely for this project; sole contractor prepares a construction phase plan before work. | Notification may still apply if its separate threshold is reached. |
| 2 | More than one contractor expected or reasonably foreseeable | Commercial client appoints both principal roles in writing as soon as practicable and before construction; principal contractor plans the phase and the health and safety file is prepared. For domestic clients, use the regulation 7 defaults below. | Trades need not overlap on site. |
| 3 | Domestic project | On a multi-contractor domestic job, client duties normally pass to the principal contractor or contractor in control, unless the principal designer accepts them by written agreement. If the householder makes no principal appointments, regulation 7 places principal-designer duties on the designer in control and principal-contractor duties on the contractor in control. | Do not call a business landlord a domestic client. |
| 4 | Notification threshold reached | For a commercial project the client notifies HSE via F10 in GB or HSENI via NI10 in NI. On a domestic project, regulation 7 transfers the regulation 6 notification duty to the sole contractor, principal contractor or principal designer under a written client-duty agreement. Keep appointment and notification tests separate. | Notification is not permission to start and is not the appointment trigger. |
CDM terms used in project decisions
Table ID: appointed-relevent-parties-cdm-terms
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Term
Construction project
- Operational meaning
The whole programme of defined construction work, including preparation and any successive trades.
- Common error
Counting each purchase order as a separate project without checking the reality.
Row 2
- Term
Pre-construction phase
- Operational meaning
Design and preparatory period; it can continue after site work begins.
- Common error
Ending design coordination at first site mobilisation.
Row 3
- Term
Principal designer
- Operational meaning
Designer with control over pre-construction phase on a multi-contractor project.
- Common error
Assuming a job title or course certificate automatically creates the role.
Row 4
- Term
Principal contractor
- Operational meaning
Contractor in control of construction phase on a multi-contractor project.
- Common error
Assuming the largest trade is appointed without writing or control.
Row 5
- Term
Construction phase plan
- Operational meaning
Written, proportionate plan for every construction project before that phase begins.
- Common error
Treating a generic RAMS bundle as the project coordination plan.
Row 6
- Term
Health and safety file
- Operational meaning
Future-work information produced for a multi-contractor project and handed to the client.
- Common error
Confusing it with the daily site log or every product manual.
Read the complete comparison table
| Row | Term | Operational meaning | Common error |
|---|---|---|---|
| 1 | Construction project | The whole programme of defined construction work, including preparation and any successive trades. | Counting each purchase order as a separate project without checking the reality. |
| 2 | Pre-construction phase | Design and preparatory period; it can continue after site work begins. | Ending design coordination at first site mobilisation. |
| 3 | Principal designer | Designer with control over pre-construction phase on a multi-contractor project. | Assuming a job title or course certificate automatically creates the role. |
| 4 | Principal contractor | Contractor in control of construction phase on a multi-contractor project. | Assuming the largest trade is appointed without writing or control. |
| 5 | Construction phase plan | Written, proportionate plan for every construction project before that phase begins. | Treating a generic RAMS bundle as the project coordination plan. |
| 6 | Health and safety file | Future-work information produced for a multi-contractor project and handed to the client. | Confusing it with the daily site log or every product manual. |
Appointment timing and evidence
Table ID: appointed-relevent-parties-cdm-timing
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Gate
Project concept and scope
- Client action
Forecast all design and construction parties and interfaces.
- Record
Scope, location and contractor forecast.
Row 2
- Gate
Before design decisions harden
- Client action
Appoint principal designer where multi-contractor work is foreseeable.
- Record
Written role, authority, design scope and acceptance.
Row 3
- Gate
Before construction phase
- Client action
Appoint principal contractor early enough to plan and produce the construction phase plan.
- Record
Written role, start date, capability and plan review.
Row 4
- Gate
During change
- Client action
Check role continuity, new trades, design changes and information transfer.
- Record
Updated appointments, plan, design and file actions.
Read the complete comparison table
| Row | Gate | Client action | Record |
|---|---|---|---|
| 1 | Project concept and scope | Forecast all design and construction parties and interfaces. | Scope, location and contractor forecast. |
| 2 | Before design decisions harden | Appoint principal designer where multi-contractor work is foreseeable. | Written role, authority, design scope and acceptance. |
| 3 | Before construction phase | Appoint principal contractor early enough to plan and produce the construction phase plan. | Written role, start date, capability and plan review. |
| 4 | During change | Check role continuity, new trades, design changes and information transfer. | Updated appointments, plan, design and file actions. |
Duties across the project
Table ID: appointed-relevent-parties-cdm-dutyholders
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Dutyholder
Commercial client
- Primary decision
Arrange project, resources, information, welfare and required appointments; check principal roles are carried out.
- Evidence of performance
Project brief, information register and review gates.
Row 2
- Dutyholder
Domestic client
- Primary decision
Client duties normally transfer under the regulations; choose capable people and provide known property information.
- Evidence of performance
Actual controlling contractor/designer identified.
Row 3
- Dutyholder
Principal designer
- Primary decision
Plan, manage, monitor and coordinate the pre-construction phase; work with designers and principal contractor.
- Evidence of performance
Risk decisions, coordinated information and file.
Row 4
- Dutyholder
Principal contractor
- Primary decision
Plan, manage, monitor and coordinate construction; plan, welfare, induction, access and worker engagement.
- Evidence of performance
Current plan, site controls, coordination and consultation.
Row 5
- Dutyholder
Designer
- Primary decision
Eliminate, reduce or control foreseeable construction, use and maintenance risk; share residual information.
- Evidence of performance
Design revisions and significant residual risk notes.
Row 6
- Dutyholder
Contractor
- Primary decision
Plan, manage and monitor own work; cooperate and coordinate with project team.
- Evidence of performance
Task arrangements, supervision and interface briefings.
Row 7
- Dutyholder
Worker
- Primary decision
Cooperate, take care and report dangers; be consulted about work affecting them.
- Evidence of performance
Induction, voice and report response.
Read the complete comparison table
| Row | Dutyholder | Primary decision | Evidence of performance |
|---|---|---|---|
| 1 | Commercial client | Arrange project, resources, information, welfare and required appointments; check principal roles are carried out. | Project brief, information register and review gates. |
| 2 | Domestic client | Client duties normally transfer under the regulations; choose capable people and provide known property information. | Actual controlling contractor/designer identified. |
| 3 | Principal designer | Plan, manage, monitor and coordinate the pre-construction phase; work with designers and principal contractor. | Risk decisions, coordinated information and file. |
| 4 | Principal contractor | Plan, manage, monitor and coordinate construction; plan, welfare, induction, access and worker engagement. | Current plan, site controls, coordination and consultation. |
| 5 | Designer | Eliminate, reduce or control foreseeable construction, use and maintenance risk; share residual information. | Design revisions and significant residual risk notes. |
| 6 | Contractor | Plan, manage and monitor own work; cooperate and coordinate with project team. | Task arrangements, supervision and interface briefings. |
| 7 | Worker | Cooperate, take care and report dangers; be consulted about work affecting them. | Induction, voice and report response. |
Project-specific appointment check
Table ID: appointed-relevent-parties-cdm-capability
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Test
Role and control
- Question
Is the principal designer a designer controlling pre-construction work; is the principal contractor a contractor controlling site work?
- Useful evidence
Role map and delegated authority.
Row 2
- Test
Skills, knowledge and experience
- Question
Can named people address this project type and its foreseeable risks?
- Useful evidence
Relevant previous work and team plan.
Row 3
- Test
Organisational capability
- Question
Can the organisation resource and coordinate the role across the project duration?
- Useful evidence
People, supervision, programme and escalation route.
Row 4
- Test
Interfaces
- Question
Can both principals share changes and address design/works interfaces?
- Useful evidence
Meeting and information handover method.
Row 5
- Test
Written terms
- Question
Are scope, date, authority and dutyholder acceptance clear?
- Useful evidence
Signed appointment and change control.
Read the complete comparison table
| Row | Test | Question | Useful evidence |
|---|---|---|---|
| 1 | Role and control | Is the principal designer a designer controlling pre-construction work; is the principal contractor a contractor controlling site work? | Role map and delegated authority. |
| 2 | Skills, knowledge and experience | Can named people address this project type and its foreseeable risks? | Relevant previous work and team plan. |
| 3 | Organisational capability | Can the organisation resource and coordinate the role across the project duration? | People, supervision, programme and escalation route. |
| 4 | Interfaces | Can both principals share changes and address design/works interfaces? | Meeting and information handover method. |
| 5 | Written terms | Are scope, date, authority and dutyholder acceptance clear? | Signed appointment and change control. |
Principal designer and principal contractor interface
Table ID: appointed-relevent-parties-cdm-interface
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Moment
Concept and preparation
- Principal designer lead
Coordinate designers, significant risks and information gaps.
- Principal contractor lead
Contribute buildability, sequencing and resources if appointed.
Row 2
- Moment
Before mobilisation
- Principal designer lead
Pass relevant design and site information promptly.
- Principal contractor lead
Prepare plan, welfare, induction, access and contractor coordination.
Row 3
- Moment
Construction design change
- Principal designer lead
Coordinate design risk and residual information while appointed.
- Principal contractor lead
Hold affected work, revise plan and brief contractors.
Row 4
- Moment
Principal designer leaves early
- Principal designer lead
Hand health and safety file and outstanding design issues to principal contractor.
- Principal contractor lead
Maintain and update file and construction controls.
Row 5
- Moment
Completion
- Principal designer lead
Provide current file to client if still appointed.
- Principal contractor lead
Provide as-built and residual information for file and hand-back.
Read the complete comparison table
| Row | Moment | Principal designer lead | Principal contractor lead |
|---|---|---|---|
| 1 | Concept and preparation | Coordinate designers, significant risks and information gaps. | Contribute buildability, sequencing and resources if appointed. |
| 2 | Before mobilisation | Pass relevant design and site information promptly. | Prepare plan, welfare, induction, access and contractor coordination. |
| 3 | Construction design change | Coordinate design risk and residual information while appointed. | Hold affected work, revise plan and brief contractors. |
| 4 | Principal designer leaves early | Hand health and safety file and outstanding design issues to principal contractor. | Maintain and update file and construction controls. |
| 5 | Completion | Provide current file to client if still appointed. | Provide as-built and residual information for file and hand-back. |
Core CDM information and handover
Table ID: appointed-relevent-parties-cdm-documents
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Information
Pre-construction information
- Owner and timing
Client provides relevant information as soon as practicable; principal designer helps assemble and share it.
- Practical quality test
Includes known site, services, existing structure and hazards; gaps are named.
Row 2
- Information
Construction phase plan
- Owner and timing
Principal contractor on multi-contractor project, sole contractor otherwise; before construction begins.
- Practical quality test
Current arrangements, site rules and project-specific high-risk work.
Row 3
- Information
Health and safety file
- Owner and timing
Principal designer prepares on multi-contractor project; principal contractor maintains it if PD leaves; client receives and retains it.
- Practical quality test
Only useful future-work information, updated for actual build and accessible on later work.
Row 4
- Information
Regulator notification
- Owner and timing
If threshold met, commercial client submits GB F10 or NI NI10. For a domestic client, regulation 7 passes notification to the sole contractor, principal contractor or principal designer under a written client-duty agreement.
- Practical quality test
Calculation, submission and update; separate from appointment and plan.
Read the complete comparison table
| Row | Information | Owner and timing | Practical quality test |
|---|---|---|---|
| 1 | Pre-construction information | Client provides relevant information as soon as practicable; principal designer helps assemble and share it. | Includes known site, services, existing structure and hazards; gaps are named. |
| 2 | Construction phase plan | Principal contractor on multi-contractor project, sole contractor otherwise; before construction begins. | Current arrangements, site rules and project-specific high-risk work. |
| 3 | Health and safety file | Principal designer prepares on multi-contractor project; principal contractor maintains it if PD leaves; client receives and retains it. | Only useful future-work information, updated for actual build and accessible on later work. |
| 4 | Regulator notification | If threshold met, commercial client submits GB F10 or NI NI10. For a domestic client, regulation 7 passes notification to the sole contractor, principal contractor or principal designer under a written client-duty agreement. | Calculation, submission and update; separate from appointment and plan. |
CDM project stage gates
Table ID: appointed-relevent-parties-cdm-stage-gates
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Stage
Before procurement
- Check and action
Define construction scope, location, client, expected trades and site information.
- Hold or escalation
Unclear project or contractor forecast: obtain project and legal advice.
Row 2
- Stage
Before design freeze
- Check and action
Appoint PD if needed; coordinate design risks and residual information.
- Hold or escalation
No capable lead or critical unknown: hold decision.
Row 3
- Stage
Before site start
- Check and action
Appoint PC if needed; verify plan, welfare, access and arrangements.
- Hold or escalation
No plan or uncontrolled public interface: do not start.
Row 4
- Stage
During construction
- Check and action
Coordinate trades, consult workers, update design and plan after change.
- Hold or escalation
Unknown services, unstable structure or missing design approval: stop affected work.
Row 5
- Stage
At completion
- Check and action
Verify safe hand-back and client receipt of required health and safety file.
- Hold or escalation
Unresolved critical defect or missing future-work information: retain an agreed hold.
Read the complete comparison table
| Row | Stage | Check and action | Hold or escalation |
|---|---|---|---|
| 1 | Before procurement | Define construction scope, location, client, expected trades and site information. | Unclear project or contractor forecast: obtain project and legal advice. |
| 2 | Before design freeze | Appoint PD if needed; coordinate design risks and residual information. | No capable lead or critical unknown: hold decision. |
| 3 | Before site start | Appoint PC if needed; verify plan, welfare, access and arrangements. | No plan or uncontrolled public interface: do not start. |
| 4 | During construction | Coordinate trades, consult workers, update design and plan after change. | Unknown services, unstable structure or missing design approval: stop affected work. |
| 5 | At completion | Verify safe hand-back and client receipt of required health and safety file. | Unresolved critical defect or missing future-work information: retain an agreed hold. |
Source comparison
Table ID: appointed-relevent-parties-cdm-ericpd-visual-controls
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Column 1
Eliminate
- Column 2
Design plant maintenance so roof-edge access is avoided.
- Column 3
Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
Row 2
- Column 1
Reduce
- Column 2
Assess ground-level or protected-location servicing.
- Column 3
Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
Row 3
- Column 1
Isolate
- Column 2
Provide suitable permanent edge protection and safe access.
- Column 3
Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
Row 4
- Column 1
Control
- Column 2
Coordinate the construction plan, permit and briefing.
- Column 3
Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
Row 5
- Column 1
PPE
- Column 2
Use assessed residual fall protection with a rescue route.
- Column 3
Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
Row 6
- Column 1
Discipline
- Column 2
Verify appointments, installed protection and changes before access.
- Column 3
Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
Read the complete comparison table
| Row | Column 1 | Column 2 | Column 3 |
|---|---|---|---|
| 1 | Eliminate | Design plant maintenance so roof-edge access is avoided. | Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients |
| 2 | Reduce | Assess ground-level or protected-location servicing. | Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients |
| 3 | Isolate | Provide suitable permanent edge protection and safe access. | Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients |
| 4 | Control | Coordinate the construction plan, permit and briefing. | Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients |
| 5 | PPE | Use assessed residual fall protection with a rescue route. | Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients |
| 6 | Discipline | Verify appointments, installed protection and changes before access. | Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients |
GB and NI CDM legal routes
Table ID: appointed-relevent-parties-cdm-jurisdiction
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Decision
Binding regulation
- Great britain
Construction (Design and Management) Regulations 2015.
- Northern ireland
Construction (Design and Management) Regulations (NI) 2016. GB source NI source
Row 2
- Decision
Written principal appointments
- Great britain
Regulation 5: client, multi-contractor trigger, as soon as practicable and before construction.
- Northern ireland
Regulation 5: same trigger and written timing requirement in NI instrument. GB source NI source
Row 3
- Decision
Notification
- Great britain
Regulation 6, HSE F10 if threshold met; commercial client notifies, with domestic regulation 7 transfer.
- Northern ireland
Regulation 6, HSENI NI10 if threshold met; commercial client notifies, with domestic regulation 7 transfer. GB source NI source
Row 4
- Decision
Domestic client route
- Great britain
Regulation 7 transfer/default roles.
- Northern ireland
Regulation 7 transfer/default roles under NI law. GB source NI source
Row 5
- Decision
Project documents
- Great britain
Pre-construction information, plan and multi-contractor file under relevant provisions.
- Northern ireland
Corresponding duties in NI 2016; verify NI schedules. GB source NI source
Read the complete comparison table
| Row | Decision | Great britain | Northern ireland |
|---|---|---|---|
| 1 | Binding regulation | Construction (Design and Management) Regulations 2015. | Construction (Design and Management) Regulations (NI) 2016. GB source NI source |
| 2 | Written principal appointments | Regulation 5: client, multi-contractor trigger, as soon as practicable and before construction. | Regulation 5: same trigger and written timing requirement in NI instrument. GB source NI source |
| 3 | Notification | Regulation 6, HSE F10 if threshold met; commercial client notifies, with domestic regulation 7 transfer. | Regulation 6, HSENI NI10 if threshold met; commercial client notifies, with domestic regulation 7 transfer. GB source NI source |
| 4 | Domestic client route | Regulation 7 transfer/default roles. | Regulation 7 transfer/default roles under NI law. GB source NI source |
| 5 | Project documents | Pre-construction information, plan and multi-contractor file under relevant provisions. | Corresponding duties in NI 2016; verify NI schedules. GB source NI source |
CDM governance risk register examples
Table ID: appointed-relevent-parties-cdm-risk-register
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Risk
Principal role appointed late
- Control
Forecast trades early and require written appointment before construction.
- Evidence and trigger
Gate approval and dated role acceptance.
Row 2
- Risk
Unknown existing structure or services
- Control
Collect and share relevant information; survey or redesign before intrusive work.
- Evidence and trigger
Information register; hold after discovery.
Row 3
- Risk
Design and site sequence conflict
- Control
PD and PC coordinate changes and hold affected work.
- Evidence and trigger
Design issue, revised plan and briefing.
Row 4
- Risk
Welfare or access missing
- Control
Verify facilities and segregation before mobilisation.
- Evidence and trigger
Site setup check and action closeout.
Row 5
- Risk
Health and safety file incomplete
- Control
Assign inputs early and review at milestones.
- Evidence and trigger
File index, as-built inputs and client receipt.
Read the complete comparison table
| Row | Risk | Control | Evidence and trigger |
|---|---|---|---|
| 1 | Principal role appointed late | Forecast trades early and require written appointment before construction. | Gate approval and dated role acceptance. |
| 2 | Unknown existing structure or services | Collect and share relevant information; survey or redesign before intrusive work. | Information register; hold after discovery. |
| 3 | Design and site sequence conflict | PD and PC coordinate changes and hold affected work. | Design issue, revised plan and briefing. |
| 4 | Welfare or access missing | Verify facilities and segregation before mobilisation. | Site setup check and action closeout. |
| 5 | Health and safety file incomplete | Assign inputs early and review at milestones. | File index, as-built inputs and client receipt. |
BuildOut Ltd project gates
Table ID: appointed-relevent-parties-cdm-buildout
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Gate
Scope
- Named decision
Client representative confirms construction work, GB or NI site and forecast trades.
- Record
Project brief.
Row 2
- Gate
Appointment
- Named decision
Client names both principals in writing when multi-contractor.
- Record
Accepted appointments and capability review.
Row 3
- Gate
Safe start
- Named decision
Principal contractor confirms current plan, welfare, access and site coordination.
- Record
Start authority and plan version.
Row 4
- Gate
Change
- Named decision
Principal designer and contractor resolve design and method changes.
- Record
Hold, revision and briefings.
Row 5
- Gate
Hand-back
- Named decision
Client receives safe site and required file.
- Record
Completion and file receipt.
Read the complete comparison table
| Row | Gate | Named decision | Record |
|---|---|---|---|
| 1 | Scope | Client representative confirms construction work, GB or NI site and forecast trades. | Project brief. |
| 2 | Appointment | Client names both principals in writing when multi-contractor. | Accepted appointments and capability review. |
| 3 | Safe start | Principal contractor confirms current plan, welfare, access and site coordination. | Start authority and plan version. |
| 4 | Change | Principal designer and contractor resolve design and method changes. | Hold, revision and briefings. |
| 5 | Hand-back | Client receives safe site and required file. | Completion and file receipt. |
Role practice, observed competence and reassessment
Table ID: appointed-relevent-parties-cdm-training-evidence
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Role and learning
Clients: commission the right roles
- Practice on the actual task
Decide project scope, contractor count, written appointments and suitable arrangements before work.
- Competence evidence and record
Project case and documented competent appointment decision.
- Assessor and reassessment trigger
Client lead rechecks after scope or team change.
Row 2
- Role and learning
Principal designers: coordinate design risk
- Practice on the actual task
Practise collecting pre-construction information and resolving significant design interfaces.
- Competence evidence and record
Reviewed design-risk record and handover to principal contractor.
- Assessor and reassessment trigger
Competent client checks after design or appointment change.
Row 3
- Role and learning
Principal contractors: coordinate construction
- Practice on the actual task
Practise phase planning, inductions, welfare, contractor interface and hand-back.
- Competence evidence and record
Observed site review, plan and closed action record.
- Assessor and reassessment trigger
Client checks after phase, contractor or incident change.
Row 4
- Role and learning
Designers and contractors: deliver own duties
- Practice on the actual task
Identify foreseeable risks, share information and follow the actual phase plan.
- Competence evidence and record
Task/plan exercise and demonstrated interface communication.
- Assessor and reassessment trigger
Principal dutyholder checks after design or method change.
Row 5
- Role and learning
Workers and supervisors: use and report
- Practice on the actual task
Demonstrate induction, welfare check, safe task method and concern escalation.
- Competence evidence and record
Observed work and reported/closed defect.
- Assessor and reassessment trigger
Site supervisor checks after new phase or control failure.
Read the complete comparison table
| Row | Role and learning | Practice on the actual task | Competence evidence and record | Assessor and reassessment trigger |
|---|---|---|---|---|
| 1 | Clients: commission the right roles | Decide project scope, contractor count, written appointments and suitable arrangements before work. | Project case and documented competent appointment decision. | Client lead rechecks after scope or team change. |
| 2 | Principal designers: coordinate design risk | Practise collecting pre-construction information and resolving significant design interfaces. | Reviewed design-risk record and handover to principal contractor. | Competent client checks after design or appointment change. |
| 3 | Principal contractors: coordinate construction | Practise phase planning, inductions, welfare, contractor interface and hand-back. | Observed site review, plan and closed action record. | Client checks after phase, contractor or incident change. |
| 4 | Designers and contractors: deliver own duties | Identify foreseeable risks, share information and follow the actual phase plan. | Task/plan exercise and demonstrated interface communication. | Principal dutyholder checks after design or method change. |
| 5 | Workers and supervisors: use and report | Demonstrate induction, welfare check, safe task method and concern escalation. | Observed work and reported/closed defect. | Site supervisor checks after new phase or control failure. |
Related SHARE Knowledge Hub pages
Table ID: appointed-relevent-parties-cdm-related-share-knowledge-hub-pages
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Related page
CDM
- Why it is useful
Wider overview of CDM duties and construction project management.
Row 2
- Related page
Construction phase plan
- Why it is useful
Explains the plan needed before construction work starts.
Row 3
- Related page
Contractor safety
- Why it is useful
Useful for contractor selection, monitoring and competence evidence.
Row 4
- Related page
Health, welfare and work environment
- Why it is useful
Supports welfare and workplace condition duties on construction projects.
Row 5
- Related page
Working at height
- Why it is useful
Common construction hazard that should be designed and planned under CDM.
Row 6
- Related page
Construction dust
- Why it is useful
Common construction health risk that relies on design, planning and contractor control.
Read the complete comparison table
| Row | Related page | Why it is useful |
|---|---|---|
| 1 | CDM | Wider overview of CDM duties and construction project management. |
| 2 | Construction phase plan | Explains the plan needed before construction work starts. |
| 3 | Contractor safety | Useful for contractor selection, monitoring and competence evidence. |
| 4 | Health, welfare and work environment | Supports welfare and workplace condition duties on construction projects. |
| 5 | Working at height | Common construction hazard that should be designed and planned under CDM. |
| 6 | Construction dust | Common construction health risk that relies on design, planning and contractor control. |
Source tables and records 2
CDM appointment source register
Table ID: appointed-relevent-parties-cdm-official-source-register
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Authority
UK legislation
- Linked source
Construction (Design and Management) Regulations 2015 (2015, as amended)
- Jurisdiction
Great Britain
- Claim supported
Binding GB client, appointment and project duties. Not Northern Ireland law.
Row 2
- Authority
UK legislation
- Linked source
Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended)
- Jurisdiction
Northern Ireland
- Claim supported
Binding NI client, appointment and project duties. Use NI schedules and NI10, not GB F10.
Row 3
- Authority
HSE
- Linked source
HSE CDM 2015 legal summary
- Jurisdiction
Great Britain
- Claim supported
Confirms GB extent and structure. HSE page is not the NI legal instrument.
Row 4
- Authority
HSE
- Linked source
HSE CDM dutyholder summary
- Jurisdiction
Great Britain
- Claim supported
Commercial and domestic clients, designers, principal roles, contractors and workers. Read with the legislation and project facts.
Row 5
- Authority
HSE
- Linked source
HSE commercial clients
- Jurisdiction
Great Britain
- Claim supported
Client arrangements, appointments, information, welfare and oversight. An adviser does not automatically take over the client duty.
Row 6
- Authority
HSE
- Linked source
HSE domestic clients
- Jurisdiction
Great Britain
- Claim supported
Domestic-client transfer of duties and written agreement option. A business landlord is a commercial client.
Row 7
- Authority
HSE
- Linked source
HSE principal designers
- Jurisdiction
Great Britain
- Claim supported
Pre-construction coordination and file duties. Principal designer must be a designer with control of that phase.
Row 8
- Authority
HSE
- Linked source
HSE principal contractors
- Jurisdiction
Great Britain
- Claim supported
Construction phase coordination, plan, welfare and worker engagement. Principal contractor role is not the same as every subcontractor.
Row 9
- Authority
HSE
- Linked source
HSE designers
- Jurisdiction
Great Britain
- Claim supported
Eliminate, reduce and communicate foreseeable design risks. Design duty can apply to people who specify or alter work, not only architects.
Row 10
- Authority
HSE
- Linked source
HSE contractors
- Jurisdiction
Great Britain
- Claim supported
Plan, manage and monitor own work and coordinate with others. Sole contractor prepares the construction phase plan.
Row 11
- Authority
HSE
- Linked source
HSE construction workers
- Jurisdiction
Great Britain
- Claim supported
Worker cooperation, reporting and consultation. Worker duties do not remove employer or contractor duties.
Row 12
- Authority
HSE
- Linked source
HSE planning for construction work
- Jurisdiction
Great Britain
- Claim supported
Early principal-contractor appointment and construction phase plan. Plan is required for every project, not only notifiable ones.
Row 13
- Authority
HSE
- Linked source
HSE F10 construction notification
- Jurisdiction
Great Britain
- Claim supported
GB notification route and sole-contractor form caveat. Notification threshold does not trigger principal appointments.
Row 14
- Authority
HSE
- Linked source
HSE CDM frequently asked questions
- Jurisdiction
Great Britain
- Claim supported
Threshold, project scope and multiple dutyholder roles. Check project facts rather than using project value as a trigger.
Row 15
- Authority
HSE
- Linked source
HSE construction welfare overview
- Jurisdiction
Great Britain
- Claim supported
Welfare planning and Schedule 2 GB route. Do not rely on old CIS59 CDM 2007 duties.
Row 16
- Authority
HSE
- Linked source
HSE L153 Managing health and safety in construction
- Jurisdiction
Great Britain guidance
- Claim supported
Detailed HSE guidance on CDM 2015 and document handover. Guidance on Regulations, not an Approved Code of Practice.
Row 17
- Authority
HSENI
- Linked source
HSENI CDM 2016 overview
- Jurisdiction
Northern Ireland
- Claim supported
NI role, all-project and multi-contractor duties. Use alongside NI 2016 Regulations.
Row 18
- Authority
HSENI
- Linked source
HSENI new construction project notification
- Jurisdiction
Northern Ireland
- Claim supported
NI notification route. NI10 is distinct from the GB F10 form.
Row 19
- Authority
HSE
- Linked source
HSE INDG368 Using contractors (2012 revision)
- Jurisdiction
Great Britain general guidance
- Claim supported
Proportionate contractor selection and coordination. Predates CDM 2015; not authority for CDM role allocation.
Row 20
- Authority
HSE
- Linked source
HSE HSG150 Health and safety in construction (Third edition 2006)
- Jurisdiction
Great Britain practical guidance
- Claim supported
Historical task-risk and site-control context. Predates CDM 2015; do not use for current appointment law.
Row 21
- Authority
HSE
- Linked source
HSE CIS59 construction welfare facilities (CDM 2007-era leaflet)
- Jurisdiction
Great Britain historical guidance
- Claim supported
Practical welfare planning context. Legal references to CDM 2007 are superseded.
Read the complete comparison table
| Row | Authority | Linked source | Jurisdiction | Claim supported |
|---|---|---|---|---|
| 1 | UK legislation | Construction (Design and Management) Regulations 2015 (2015, as amended) | Great Britain | Binding GB client, appointment and project duties. Not Northern Ireland law. |
| 2 | UK legislation | Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) | Northern Ireland | Binding NI client, appointment and project duties. Use NI schedules and NI10, not GB F10. |
| 3 | HSE | HSE CDM 2015 legal summary | Great Britain | Confirms GB extent and structure. HSE page is not the NI legal instrument. |
| 4 | HSE | HSE CDM dutyholder summary | Great Britain | Commercial and domestic clients, designers, principal roles, contractors and workers. Read with the legislation and project facts. |
| 5 | HSE | HSE commercial clients | Great Britain | Client arrangements, appointments, information, welfare and oversight. An adviser does not automatically take over the client duty. |
| 6 | HSE | HSE domestic clients | Great Britain | Domestic-client transfer of duties and written agreement option. A business landlord is a commercial client. |
| 7 | HSE | HSE principal designers | Great Britain | Pre-construction coordination and file duties. Principal designer must be a designer with control of that phase. |
| 8 | HSE | HSE principal contractors | Great Britain | Construction phase coordination, plan, welfare and worker engagement. Principal contractor role is not the same as every subcontractor. |
| 9 | HSE | HSE designers | Great Britain | Eliminate, reduce and communicate foreseeable design risks. Design duty can apply to people who specify or alter work, not only architects. |
| 10 | HSE | HSE contractors | Great Britain | Plan, manage and monitor own work and coordinate with others. Sole contractor prepares the construction phase plan. |
| 11 | HSE | HSE construction workers | Great Britain | Worker cooperation, reporting and consultation. Worker duties do not remove employer or contractor duties. |
| 12 | HSE | HSE planning for construction work | Great Britain | Early principal-contractor appointment and construction phase plan. Plan is required for every project, not only notifiable ones. |
| 13 | HSE | HSE F10 construction notification | Great Britain | GB notification route and sole-contractor form caveat. Notification threshold does not trigger principal appointments. |
| 14 | HSE | HSE CDM frequently asked questions | Great Britain | Threshold, project scope and multiple dutyholder roles. Check project facts rather than using project value as a trigger. |
| 15 | HSE | HSE construction welfare overview | Great Britain | Welfare planning and Schedule 2 GB route. Do not rely on old CIS59 CDM 2007 duties. |
| 16 | HSE | HSE L153 Managing health and safety in construction | Great Britain guidance | Detailed HSE guidance on CDM 2015 and document handover. Guidance on Regulations, not an Approved Code of Practice. |
| 17 | HSENI | HSENI CDM 2016 overview | Northern Ireland | NI role, all-project and multi-contractor duties. Use alongside NI 2016 Regulations. |
| 18 | HSENI | HSENI new construction project notification | Northern Ireland | NI notification route. NI10 is distinct from the GB F10 form. |
| 19 | HSE | HSE INDG368 Using contractors (2012 revision) | Great Britain general guidance | Proportionate contractor selection and coordination. Predates CDM 2015; not authority for CDM role allocation. |
| 20 | HSE | HSE HSG150 Health and safety in construction (Third edition 2006) | Great Britain practical guidance | Historical task-risk and site-control context. Predates CDM 2015; do not use for current appointment law. |
| 21 | HSE | HSE CIS59 construction welfare facilities (CDM 2007-era leaflet) | Great Britain historical guidance | Practical welfare planning context. Legal references to CDM 2007 are superseded. |
CDM appointment acronyms
Table ID: appointed-relevent-parties-cdm-acronyms
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Term
CDM
- Meaning and boundary
Construction (Design and Management); GB 2015 and NI 2016 are separate regulations.
Row 2
- Term
PD / PC
- Meaning and boundary
Principal designer / principal contractor, required on multi-contractor projects.
Row 3
- Term
PCI
- Meaning and boundary
Pre-construction information relevant to the project and shared early.
Row 4
- Term
CPP
- Meaning and boundary
Construction phase plan, required before construction for every project.
Row 5
- Term
F10 / NI10
- Meaning and boundary
GB HSE / NI HSENI notification routes when size test is met.
Row 6
- Term
RAMS
- Meaning and boundary
Risk assessments and method statements; useful task documents, not a substitute for CPP or principal appointment.
Read the complete comparison table
| Row | Term | Meaning and boundary |
|---|---|---|
| 1 | CDM | Construction (Design and Management); GB 2015 and NI 2016 are separate regulations. |
| 2 | PD / PC | Principal designer / principal contractor, required on multi-contractor projects. |
| 3 | PCI | Pre-construction information relevant to the project and shared early. |
| 4 | CPP | Construction phase plan, required before construction for every project. |
| 5 | F10 / NI10 | GB HSE / NI HSENI notification routes when size test is met. |
| 6 | RAMS | Risk assessments and method statements; useful task documents, not a substitute for CPP or principal appointment. |
Suggested CDM project records
Table ID: appointed-relevent-parties-cdm-tools
Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html
Row 1
- Record
Contractor forecast and role map
- Use
Determine whether principal roles are required, including later trades.
- Owner and boundary
Client; review on change.
Row 2
- Record
Written appointment and capability check
- Use
Define role, authority, scope, timing and project-specific suitability.
- Owner and boundary
Client; not a generic certificate collection.
Row 3
- Record
PCI and design issue register
- Use
Share known site, existing structure and unresolved risks.
- Owner and boundary
Client and PD; keep current.
Row 4
- Record
CPP and coordination log
- Use
Manage site rules, high-risk work, welfare and interfaces.
- Owner and boundary
PC or sole contractor; update during work.
Row 5
- Record
Health and safety file index
- Use
Capture relevant future-work information and client receipt.
- Owner and boundary
PD/PC as applicable; multi-contractor project.
Read the complete comparison table
| Row | Record | Use | Owner and boundary |
|---|---|---|---|
| 1 | Contractor forecast and role map | Determine whether principal roles are required, including later trades. | Client; review on change. |
| 2 | Written appointment and capability check | Define role, authority, scope, timing and project-specific suitability. | Client; not a generic certificate collection. |
| 3 | PCI and design issue register | Share known site, existing structure and unresolved risks. | Client and PD; keep current. |
| 4 | CPP and coordination log | Manage site rules, high-risk work, welfare and interfaces. | PC or sole contractor; update during work. |
| 5 | Health and safety file index | Capture relevant future-work information and client receipt. | PD/PC as applicable; multi-contractor project. |
CDM in plain English
Table ID: cdm-cdm-in-plain-english
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Area
Lifecycle control
- What it means
Manage risk from design through handover.
- Practical output
Project CDM plan and review points.
Row 2
- Area
Dutyholders
- What it means
Named roles with specific responsibilities.
- Practical output
Appointments and responsibility matrix.
Row 3
- Area
Information flow
- What it means
Give the right people the right risk information.
- Practical output
Pre-construction information and design risk notes.
Row 4
- Area
Planning
- What it means
Organise work before it starts.
- Practical output
Construction phase plan.
Row 5
- Area
Coordination
- What it means
Make trades and designers work together safely.
- Practical output
Meetings, interfaces and site rules.
Row 6
- Area
Legacy information
- What it means
Help future work be safer.
- Practical output
Health and safety file.
Read the complete comparison table
| Row | Area | What it means | Practical output |
|---|---|---|---|
| 1 | Lifecycle control | Manage risk from design through handover. | Project CDM plan and review points. |
| 2 | Dutyholders | Named roles with specific responsibilities. | Appointments and responsibility matrix. |
| 3 | Information flow | Give the right people the right risk information. | Pre-construction information and design risk notes. |
| 4 | Planning | Organise work before it starts. | Construction phase plan. |
| 5 | Coordination | Make trades and designers work together safely. | Meetings, interfaces and site rules. |
| 6 | Legacy information | Help future work be safer. | Health and safety file. |
CDM scope examples
Table ID: cdm-cdm-scope-examples
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Work type
New build
- Likely cdm relevance
Clearly construction work.
- Planning focus
Appointments, design risk, CPP and welfare.
Row 2
- Work type
Refurbishment
- Likely cdm relevance
Usually construction work.
- Planning focus
Asbestos, services, access, fire and segregation.
Row 3
- Work type
Maintenance on a structure
- Likely cdm relevance
Can be construction work depending on activity.
- Planning focus
Task risk and existing hazards.
Row 4
- Work type
Demolition or dismantling
- Likely cdm relevance
Construction work with high-risk sequencing.
- Planning focus
Method, exclusion zones and temporary works.
Row 5
- Work type
Service installation
- Likely cdm relevance
Included where fixed to a structure.
- Planning focus
Isolation, coordination and commissioning.
Row 6
- Work type
High-pressure cleaning or abrasive cleaning
- Likely cdm relevance
Can be included in CDM where it meets the definition.
- Planning focus
Exposure, access and containment.
Read the complete comparison table
| Row | Work type | Likely cdm relevance | Planning focus |
|---|---|---|---|
| 1 | New build | Clearly construction work. | Appointments, design risk, CPP and welfare. |
| 2 | Refurbishment | Usually construction work. | Asbestos, services, access, fire and segregation. |
| 3 | Maintenance on a structure | Can be construction work depending on activity. | Task risk and existing hazards. |
| 4 | Demolition or dismantling | Construction work with high-risk sequencing. | Method, exclusion zones and temporary works. |
| 5 | Service installation | Included where fixed to a structure. | Isolation, coordination and commissioning. |
| 6 | High-pressure cleaning or abrasive cleaning | Can be included in CDM where it meets the definition. | Exposure, access and containment. |
Prevention principles in CDM practice
Table ID: cdm-prevention-principles-in-cdm-practice
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Principle
Avoid risks
- Cdm application
Remove hazards through design or method.
- Example
Prefabricate at ground level.
Row 2
- Principle
Evaluate unavoidable risks
- Cdm application
Assess remaining risks before work starts.
- Example
Temporary works and services assessment.
Row 3
- Principle
Combat risks at source
- Cdm application
Control the source rather than the worker.
- Example
Fixed edge protection, not harness-only reliance.
Row 4
- Principle
Adapt work to people
- Cdm application
Design access, handling and maintenance around human capability.
- Example
Plant with safe access and clearances.
Row 5
- Principle
Replace dangerous with less dangerous
- Cdm application
Choose safer materials or methods.
- Example
Low-dust cutting method.
Row 6
- Principle
Prioritise collective measures
- Cdm application
Protect everyone before relying on PPE.
- Example
Guardrails before fall arrest.
Row 7
- Principle
Give instructions
- Cdm application
Communicate residual significant risks clearly.
- Example
Design risk notes and briefings.
Read the complete comparison table
| Row | Principle | Cdm application | Example |
|---|---|---|---|
| 1 | Avoid risks | Remove hazards through design or method. | Prefabricate at ground level. |
| 2 | Evaluate unavoidable risks | Assess remaining risks before work starts. | Temporary works and services assessment. |
| 3 | Combat risks at source | Control the source rather than the worker. | Fixed edge protection, not harness-only reliance. |
| 4 | Adapt work to people | Design access, handling and maintenance around human capability. | Plant with safe access and clearances. |
| 5 | Replace dangerous with less dangerous | Choose safer materials or methods. | Low-dust cutting method. |
| 6 | Prioritise collective measures | Protect everyone before relying on PPE. | Guardrails before fall arrest. |
| 7 | Give instructions | Communicate residual significant risks clearly. | Design risk notes and briefings. |
CDM dutyholder summary
Table ID: cdm-cdm-dutyholder-summary
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Dutyholder
Client
- Main role
Make suitable arrangements, appoint dutyholders and provide information.
- Evidence
Client brief, appointments and PCI.
Row 2
- Dutyholder
Designer
- Main role
Eliminate, reduce or control foreseeable risks through design.
- Evidence
Design risk register and information.
Row 3
- Dutyholder
Principal designer
- Main role
Coordinate pre-construction health and safety.
- Evidence
Design coordination and H&S file development.
Row 4
- Dutyholder
Principal contractor
- Main role
Coordinate the construction phase.
- Evidence
CPP, site rules, inductions and coordination.
Row 5
- Dutyholder
Contractor
- Main role
Plan, manage and monitor their work.
- Evidence
RAMS, briefings and supervision.
Row 6
- Dutyholder
Worker
- Main role
Cooperate, follow site rules and report danger.
- Evidence
Induction and consultation.
Read the complete comparison table
| Row | Dutyholder | Main role | Evidence |
|---|---|---|---|
| 1 | Client | Make suitable arrangements, appoint dutyholders and provide information. | Client brief, appointments and PCI. |
| 2 | Designer | Eliminate, reduce or control foreseeable risks through design. | Design risk register and information. |
| 3 | Principal designer | Coordinate pre-construction health and safety. | Design coordination and H&S file development. |
| 4 | Principal contractor | Coordinate the construction phase. | CPP, site rules, inductions and coordination. |
| 5 | Contractor | Plan, manage and monitor their work. | RAMS, briefings and supervision. |
| 6 | Worker | Cooperate, follow site rules and report danger. | Induction and consultation. |
Key CDM documents
Table ID: cdm-key-cdm-documents
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Document
Pre-construction information
- Purpose
Tell designers and contractors about relevant hazards and constraints.
- Quality test
Would it help price and plan the job safely?
Row 2
- Document
Construction phase plan
- Purpose
Explain how construction health and safety will be managed.
- Quality test
Is it specific to the project and updated?
Row 3
- Document
F10 notification
- Purpose
Notify the enforcing authority where thresholds are met.
- Quality test
Is it submitted and updated when details change?
Row 4
- Document
Health and safety file
- Purpose
Provide information needed for future maintenance or work.
- Quality test
Would a future contractor find it useful?
Row 5
- Document
Design risk register
- Purpose
Track significant design risks and decisions.
- Quality test
Does it show eliminated and residual risks?
Row 6
- Document
Site rules and logistics plan
- Purpose
Control behaviour, access, traffic, welfare and emergencies.
- Quality test
Are workers briefed and supervisors checking?
Read the complete comparison table
| Row | Document | Purpose | Quality test |
|---|---|---|---|
| 1 | Pre-construction information | Tell designers and contractors about relevant hazards and constraints. | Would it help price and plan the job safely? |
| 2 | Construction phase plan | Explain how construction health and safety will be managed. | Is it specific to the project and updated? |
| 3 | F10 notification | Notify the enforcing authority where thresholds are met. | Is it submitted and updated when details change? |
| 4 | Health and safety file | Provide information needed for future maintenance or work. | Would a future contractor find it useful? |
| 5 | Design risk register | Track significant design risks and decisions. | Does it show eliminated and residual risks? |
| 6 | Site rules and logistics plan | Control behaviour, access, traffic, welfare and emergencies. | Are workers briefed and supervisors checking? |
Notification decision
Table ID: cdm-notification-check
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Column-1
30-working-day/20-worker test
- Column-2
More than 30 working days and more than 20 people on site at any time.
- Column-3
More than 30 working days and more than 20 workers simultaneously, per NI Regulation 6.
Row 2
- Column-1
Person-day test
- Column-2
More than 500 person-days.
- Column-3
More than 500 person-days.
Row 3
- Column-1
Regulator and record
- Column-2
HSE F10 or relevant GB enforcing route; client records submission and updates.
- Column-3
HSENI NI notification route; client records submission and updates.
Row 4
- Column-1
Under threshold
- Column-2
CDM duties, appointments and construction phase plan can still apply.
- Column-3
CDM duties, appointments and written construction phase plan can still apply.
Read the complete comparison table
| Row | Column-1 | Column-2 | Column-3 |
|---|---|---|---|
| 1 | 30-working-day/20-worker test | More than 30 working days and more than 20 people on site at any time. | More than 30 working days and more than 20 workers simultaneously, per NI Regulation 6. |
| 2 | Person-day test | More than 500 person-days. | More than 500 person-days. |
| 3 | Regulator and record | HSE F10 or relevant GB enforcing route; client records submission and updates. | HSENI NI notification route; client records submission and updates. |
| 4 | Under threshold | CDM duties, appointments and construction phase plan can still apply. | CDM duties, appointments and written construction phase plan can still apply. |
Pre-construction outputs
Table ID: cdm-pre-construction-outputs
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Output
Client brief
- What it should contain
Project purpose, constraints, standards and key risks.
- Owner
Client.
Row 2
- Output
Pre-construction information
- What it should contain
Existing hazards, surveys, services, asbestos and site information.
- Owner
Client with PD support.
Row 3
- Output
Design risk register
- What it should contain
Significant risks eliminated, reduced or communicated.
- Owner
Designers and PD.
Row 4
- Output
Appointments
- What it should contain
Written PD and PC appointments where required.
- Owner
Client.
Row 5
- Output
Programme
- What it should contain
Time allowed for planning, design and safe construction.
- Owner
Client and project team.
Row 6
- Output
Competence checks
- What it should contain
Skills, knowledge, experience and organisational capability.
- Owner
Client and dutyholders.
Read the complete comparison table
| Row | Output | What it should contain | Owner |
|---|---|---|---|
| 1 | Client brief | Project purpose, constraints, standards and key risks. | Client. |
| 2 | Pre-construction information | Existing hazards, surveys, services, asbestos and site information. | Client with PD support. |
| 3 | Design risk register | Significant risks eliminated, reduced or communicated. | Designers and PD. |
| 4 | Appointments | Written PD and PC appointments where required. | Client. |
| 5 | Programme | Time allowed for planning, design and safe construction. | Client and project team. |
| 6 | Competence checks | Skills, knowledge, experience and organisational capability. | Client and dutyholders. |
Construction phase controls
Table ID: cdm-construction-phase-controls
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Control
Construction phase plan
- Why it matters
Sets out site-specific arrangements.
- Evidence
Current CPP.
Row 2
- Control
Induction and briefings
- Why it matters
Workers understand site risks and rules.
- Evidence
Attendance and briefing records.
Row 3
- Control
Contractor coordination
- Why it matters
Prevents interface failures.
- Evidence
Coordination meetings.
Row 4
- Control
Site inspections
- Why it matters
Checks controls remain effective.
- Evidence
Inspection and action records.
Row 5
- Control
Permit systems
- Why it matters
Controls high-risk work such as hot work or excavations.
- Evidence
Permits and hand-back checks.
Row 6
- Control
Change control
- Why it matters
Prevents new hazards being missed.
- Evidence
Design and method change log.
Read the complete comparison table
| Row | Control | Why it matters | Evidence |
|---|---|---|---|
| 1 | Construction phase plan | Sets out site-specific arrangements. | Current CPP. |
| 2 | Induction and briefings | Workers understand site risks and rules. | Attendance and briefing records. |
| 3 | Contractor coordination | Prevents interface failures. | Coordination meetings. |
| 4 | Site inspections | Checks controls remain effective. | Inspection and action records. |
| 5 | Permit systems | Controls high-risk work such as hot work or excavations. | Permits and hand-back checks. |
| 6 | Change control | Prevents new hazards being missed. | Design and method change log. |
Welfare checks
Table ID: cdm-welfare-checks
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Facility
Toilets
- Why it matters
Basic hygiene and dignity.
- Evidence
Welfare inspection.
Row 2
- Facility
Washing
- Why it matters
Controls skin and substance exposure.
- Evidence
Hot/warm water and supplies.
Row 3
- Facility
Drinking water
- Why it matters
Hydration and health.
- Evidence
Water availability.
Row 4
- Facility
Rest area
- Why it matters
Breaks, fatigue and shelter.
- Evidence
Suitable rest facilities.
Row 5
- Facility
Changing/drying
- Why it matters
Contaminated or wet clothing management.
- Evidence
Changing facilities.
Row 6
- Facility
Maintenance
- Why it matters
Facilities remain usable.
- Evidence
Cleaning and defect records.
Read the complete comparison table
| Row | Facility | Why it matters | Evidence |
|---|---|---|---|
| 1 | Toilets | Basic hygiene and dignity. | Welfare inspection. |
| 2 | Washing | Controls skin and substance exposure. | Hot/warm water and supplies. |
| 3 | Drinking water | Hydration and health. | Water availability. |
| 4 | Rest area | Breaks, fatigue and shelter. | Suitable rest facilities. |
| 5 | Changing/drying | Contaminated or wet clothing management. | Changing facilities. |
| 6 | Maintenance | Facilities remain usable. | Cleaning and defect records. |
Handover information
Table ID: cdm-handover-information
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Information
Residual risks
- Why future users need it
Future work needs to know what remains.
- Example
Fragile roof area or unusual loading.
Row 2
- Information
Maintenance access
- Why future users need it
Safe access needs to be planned.
- Example
Access routes and anchor details.
Row 3
- Information
Asbestos information
- Why future users need it
Prevents uncontrolled disturbance.
- Example
Survey and register details.
Row 4
- Information
Services
- Why future users need it
Prevents strikes during future work.
- Example
As-built drawings and service routes.
Row 5
- Information
Plant and systems
- Why future users need it
Supports safe maintenance.
- Example
Manuals, isolation and testing details.
Row 6
- Information
Lessons learned
- Why future users need it
Improves the next project.
- Example
Project review and action log.
Read the complete comparison table
| Row | Information | Why future users need it | Example |
|---|---|---|---|
| 1 | Residual risks | Future work needs to know what remains. | Fragile roof area or unusual loading. |
| 2 | Maintenance access | Safe access needs to be planned. | Access routes and anchor details. |
| 3 | Asbestos information | Prevents uncontrolled disturbance. | Survey and register details. |
| 4 | Services | Prevents strikes during future work. | As-built drawings and service routes. |
| 5 | Plant and systems | Supports safe maintenance. | Manuals, isolation and testing details. |
| 6 | Lessons learned | Improves the next project. | Project review and action log. |
CDM assurance levels
Table ID: cdm-cdm-assurance-levels
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Level
First line
- Who does it
Site manager, supervisor or trade lead.
- What they check
Controls, welfare, inductions, permits and safe work.
Row 2
- Level
Second line
- Who does it
Client representative, principal designer, principal contractor or H&S adviser.
- What they check
Appointments, PCI, CPP, coordination and inspections.
Row 3
- Level
Third line
- Who does it
Independent auditor, consultant or senior client assurance.
- What they check
System effectiveness, evidence quality and legal gaps.
Row 4
- Level
Close-out
- Who does it
Project team and client.
- What they check
H&S file, lessons learned and future actions.
Read the complete comparison table
| Row | Level | Who does it | What they check |
|---|---|---|---|
| 1 | First line | Site manager, supervisor or trade lead. | Controls, welfare, inductions, permits and safe work. |
| 2 | Second line | Client representative, principal designer, principal contractor or H&S adviser. | Appointments, PCI, CPP, coordination and inspections. |
| 3 | Third line | Independent auditor, consultant or senior client assurance. | System effectiveness, evidence quality and legal gaps. |
| 4 | Close-out | Project team and client. | H&S file, lessons learned and future actions. |
CDM duties by work location
Table ID: cdm-jurisdiction-map
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Column-1
Main instrument
- Column-2
Construction (Design and Management) Regulations 2015.
- Column-3
Construction (Design and Management) Regulations (Northern Ireland) 2016.
Row 2
- Column-1
Small or single-contractor work
- Column-2
CDM still applies; a construction phase plan is required.
- Column-3
CDM still applies; HSENI expects a written construction phase health and safety plan.
Row 3
- Column-1
Multiple contractors
- Column-2
Appoint principal designer and principal contractor; maintain health and safety file.
- Column-3
Appoint principal designer and principal contractor; maintain health and safety file.
Row 4
- Column-1
Notification
- Column-2
HSE/appropriate GB authority via F10 where threshold met.
- Column-3
Client notifies HSENI via NI route where threshold met.
Row 5
- Column-1
Building-control interface
- Column-2
England Building Regulations roles may additionally apply in England.
- Column-3
Check NI building-control requirements separately.
Read the complete comparison table
| Row | Column-1 | Column-2 | Column-3 |
|---|---|---|---|
| 1 | Main instrument | Construction (Design and Management) Regulations 2015. | Construction (Design and Management) Regulations (Northern Ireland) 2016. |
| 2 | Small or single-contractor work | CDM still applies; a construction phase plan is required. | CDM still applies; HSENI expects a written construction phase health and safety plan. |
| 3 | Multiple contractors | Appoint principal designer and principal contractor; maintain health and safety file. | Appoint principal designer and principal contractor; maintain health and safety file. |
| 4 | Notification | HSE/appropriate GB authority via F10 where threshold met. | Client notifies HSENI via NI route where threshold met. |
| 5 | Building-control interface | England Building Regulations roles may additionally apply in England. | Check NI building-control requirements separately. |
BuildOut CDM management approach
Table ID: cdm-buildout-cdm-management-approach
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Activity
Assess
- How buildout manages it
Screens project scope, dutyholder role, notification, high-risk work and information needs.
- Evidence
CDM project register.
Row 2
- Activity
Analyse
- How buildout manages it
Reviews design risk, site constraints, services, asbestos, welfare and contractor interfaces.
- Evidence
PCI review and risk workshop.
Row 3
- Activity
Train
- How buildout manages it
Trains project managers, site managers, designers and supervisors on CDM duties.
- Evidence
Training matrix and briefings.
Row 4
- Activity
Implement
- How buildout manages it
Uses appointments, CPP, welfare plan, site rules, permits and contractor coordination.
- Evidence
Project file and site records.
Row 5
- Activity
Check
- How buildout manages it
Uses inspections, document reviews, worker feedback and audits.
- Evidence
Assurance dashboard and action tracker.
Row 6
- Activity
Learn
- How buildout manages it
Reviews incidents, near misses, design changes and project close-out.
- Evidence
Lessons learned record.
Row 7
- Activity
Improve
- How buildout manages it
Updates templates, procurement standards, designer prompts and contractor controls.
- Evidence
Management review and revised procedures.
Read the complete comparison table
| Row | Activity | How buildout manages it | Evidence |
|---|---|---|---|
| 1 | Assess | Screens project scope, dutyholder role, notification, high-risk work and information needs. | CDM project register. |
| 2 | Analyse | Reviews design risk, site constraints, services, asbestos, welfare and contractor interfaces. | PCI review and risk workshop. |
| 3 | Train | Trains project managers, site managers, designers and supervisors on CDM duties. | Training matrix and briefings. |
| 4 | Implement | Uses appointments, CPP, welfare plan, site rules, permits and contractor coordination. | Project file and site records. |
| 5 | Check | Uses inspections, document reviews, worker feedback and audits. | Assurance dashboard and action tracker. |
| 6 | Learn | Reviews incidents, near misses, design changes and project close-out. | Lessons learned record. |
| 7 | Improve | Updates templates, procurement standards, designer prompts and contractor controls. | Management review and revised procedures. |
Role-level learning and competence evidence
Table ID: cdm-competence-decisions
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Column-1
Client: project brief, resources and appointments.
- Column-2
CDM specialist challenges a programme that omits pre-construction information, welfare and an early appointment.
- Column-3
Dated brief and appointment record; revisit after scope or team change.
Row 2
- Column-1
Designer/principal designer: foreseeable risk and coordination.
- Column-2
Competent reviewer traces one design hazard from elimination choice to residual information handed to the builder.
- Column-3
Design decision and coordination record; revisit after design change.
Row 3
- Column-1
Principal contractor/contractor: construction plan and site controls.
- Column-2
Site lead demonstrates sequence, induction, welfare, interfaces, permits and stop response at the actual site.
- Column-3
Plan version, site observation and action close-out; revisit after new activity or contractor.
Row 4
- Column-1
Worker/supervisor: task briefing and unsafe-condition report.
- Column-2
Supervisor checks understanding through a live task walk-through, including who to tell and when to stop.
- Column-3
Induction and task observation; refresh after change or incident.
Row 5
- Column-1
Project administrator: jurisdiction and threshold.
- Column-2
Competent client representative applies GB/NI form, threshold and update route to a forecast exercise.
- Column-3
Calculation and submission record; review when workforce or programme changes.
Read the complete comparison table
| Row | Column-1 | Column-2 | Column-3 |
|---|---|---|---|
| 1 | Client: project brief, resources and appointments. | CDM specialist challenges a programme that omits pre-construction information, welfare and an early appointment. | Dated brief and appointment record; revisit after scope or team change. |
| 2 | Designer/principal designer: foreseeable risk and coordination. | Competent reviewer traces one design hazard from elimination choice to residual information handed to the builder. | Design decision and coordination record; revisit after design change. |
| 3 | Principal contractor/contractor: construction plan and site controls. | Site lead demonstrates sequence, induction, welfare, interfaces, permits and stop response at the actual site. | Plan version, site observation and action close-out; revisit after new activity or contractor. |
| 4 | Worker/supervisor: task briefing and unsafe-condition report. | Supervisor checks understanding through a live task walk-through, including who to tell and when to stop. | Induction and task observation; refresh after change or incident. |
| 5 | Project administrator: jurisdiction and threshold. | Competent client representative applies GB/NI form, threshold and update route to a forecast exercise. | Calculation and submission record; review when workforce or programme changes. |
Source tables and records 3
Study application
Table ID: cdm-study-application
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Learning context
IOSH Construction Certificate
- What to know
CDM dutyholders, CPP, PCI, welfare, F10 and construction control.
- Scenario application
Refurbishment project starts without asbestos information.
Row 2
- Learning context
IOSH National General Certificate
- What to know
Contractor management and construction risk.
- Scenario application
Client appoints contractor without checking arrangements.
Row 3
- Learning context
IOSH Diploma
- What to know
Lifecycle risk, assurance and organisational control.
- Scenario application
Audit of design-risk management across projects.
Row 4
- Learning context
Professional CPD
- What to know
Practical CDM governance and evidence.
- Scenario application
Project close-out shows poor H&S file quality.
Read the complete comparison table
| Row | Learning context | What to know | Scenario application |
|---|---|---|---|
| 1 | IOSH Construction Certificate | CDM dutyholders, CPP, PCI, welfare, F10 and construction control. | Refurbishment project starts without asbestos information. |
| 2 | IOSH National General Certificate | Contractor management and construction risk. | Client appoints contractor without checking arrangements. |
| 3 | IOSH Diploma | Lifecycle risk, assurance and organisational control. | Audit of design-risk management across projects. |
| 4 | Professional CPD | Practical CDM governance and evidence. | Project close-out shows poor H&S file quality. |
Warning signs and consequences
Table ID: cdm-warning-signs-and-consequences
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Warning sign
Late appointments
- How harm can develop
Design and planning risk is missed.
- Improvement action
Appoint dutyholders early and in writing.
Row 2
- Warning sign
Generic CPP
- How harm can develop
Real site risks are not controlled.
- Improvement action
Rewrite around actual work.
Row 3
- Warning sign
Missing PCI
- How harm can develop
Asbestos, services or structural hazards are discovered late.
- Improvement action
Collect and review information before work.
Row 4
- Warning sign
Poor welfare
- How harm can develop
Health, hygiene and morale suffer.
- Improvement action
Provide facilities before start.
Row 5
- Warning sign
Weak coordination
- How harm can develop
Trades interfere with each other.
- Improvement action
Improve sequencing and meetings.
Row 6
- Warning sign
No H&S file
- How harm can develop
Future work is less safe.
- Improvement action
Plan file ownership and close-out.
Read the complete comparison table
| Row | Warning sign | How harm can develop | Improvement action |
|---|---|---|---|
| 1 | Late appointments | Design and planning risk is missed. | Appoint dutyholders early and in writing. |
| 2 | Generic CPP | Real site risks are not controlled. | Rewrite around actual work. |
| 3 | Missing PCI | Asbestos, services or structural hazards are discovered late. | Collect and review information before work. |
| 4 | Poor welfare | Health, hygiene and morale suffer. | Provide facilities before start. |
| 5 | Weak coordination | Trades interfere with each other. | Improve sequencing and meetings. |
| 6 | No H&S file | Future work is less safe. | Plan file ownership and close-out. |
Official links and their use
Table ID: cdm-official-links
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Column-1
HSE CDM 2015
- Column-2
Great Britain regulator
- Column-3
GB statutory framework and roles
Row 2
- Column-1
HSE CDM FAQ
- Column-2
Great Britain regulator
- Column-3
Threshold, domestic duties, appointments and notification
Row 3
- Column-1
HSE dutyholder responsibilities
- Column-2
Great Britain regulator
- Column-3
Client, designer and contractor decision points
Row 4
- Column-1
HSE designers
- Column-2
Great Britain regulator
- Column-3
Design risk and residual information
Row 5
- Column-1
HSE construction phase plan
- Column-2
Great Britain regulator
- Column-3
Plan required for construction phase, including small projects
Row 6
- Column-1
HSE F10
- Column-2
Great Britain notification route
- Column-3
GB notifiable projects
Row 7
- Column-1
CDM 2015 legal text
- Column-2
Great Britain legislation
- Column-3
Exact GB regulations including notification and appointments
Row 8
- Column-1
HSENI CDM (NI) 2016
- Column-2
Northern Ireland regulator
- Column-3
NI duties and notification thresholds
Row 9
- Column-1
CDM (NI) 2016 legal text
- Column-2
Northern Ireland legislation
- Column-3
Exact NI Regulation 6 working-day test and domestic-client route
Row 10
- Column-1
HSENI NI10 construction notification
- Column-2
Northern Ireland regulator; non-accessible form
- Column-3
NI notification route; use accessible HSENI support if needed
Row 11
- Column-1
GOV.UK building work requirements
- Column-2
England building-control guidance
- Column-3
Separate Building Regulations dutyholders
Row 12
- Column-1
HSE Managing for health and safety (HSG65)
- Column-2
HSE management guidance for Great Britain; check current edition
- Column-3
Management-system scope only
Read the complete comparison table
| Row | Column-1 | Column-2 | Column-3 |
|---|---|---|---|
| 1 | HSE CDM 2015 | Great Britain regulator | GB statutory framework and roles |
| 2 | HSE CDM FAQ | Great Britain regulator | Threshold, domestic duties, appointments and notification |
| 3 | HSE dutyholder responsibilities | Great Britain regulator | Client, designer and contractor decision points |
| 4 | HSE designers | Great Britain regulator | Design risk and residual information |
| 5 | HSE construction phase plan | Great Britain regulator | Plan required for construction phase, including small projects |
| 6 | HSE F10 | Great Britain notification route | GB notifiable projects |
| 7 | CDM 2015 legal text | Great Britain legislation | Exact GB regulations including notification and appointments |
| 8 | HSENI CDM (NI) 2016 | Northern Ireland regulator | NI duties and notification thresholds |
| 9 | CDM (NI) 2016 legal text | Northern Ireland legislation | Exact NI Regulation 6 working-day test and domestic-client route |
| 10 | HSENI NI10 construction notification | Northern Ireland regulator; non-accessible form | NI notification route; use accessible HSENI support if needed |
| 11 | GOV.UK building work requirements | England building-control guidance | Separate Building Regulations dutyholders |
| 12 | HSE Managing for health and safety (HSG65) | HSE management guidance for Great Britain; check current edition | Management-system scope only |
Acronyms and terms
Table ID: cdm-acronyms-and-terms
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Acronym or term
CDM
- Meaning
Construction Design and Management
- Why it matters
Main construction health and safety framework.
Row 2
- Acronym or term
PCI
- Meaning
Pre-Construction Information
- Why it matters
Key information for planning and designing safely.
Row 3
- Acronym or term
CPP
- Meaning
Construction Phase Plan
- Why it matters
Plan for managing construction health and safety.
Row 4
- Acronym or term
PD
- Meaning
Principal Designer
- Why it matters
Coordinates pre-construction health and safety on multi-contractor projects.
Row 5
- Acronym or term
PC
- Meaning
Principal Contractor
- Why it matters
Coordinates the construction phase on multi-contractor projects.
Row 6
- Acronym or term
F10
- Meaning
Notification of Construction Project
- Why it matters
Online notification route for notifiable projects in Great Britain.
Row 7
- Acronym or term
H&S file
- Meaning
Health and Safety File
- Why it matters
Handover file for future safe work.
Row 8
- Acronym or term
RAMS
- Meaning
Risk Assessment and Method Statement
- Why it matters
Contractor task planning documents.
Row 9
- Acronym or term
SKE
- Meaning
Skills, Knowledge and Experience
- Why it matters
Competence concept for dutyholder capability.
Read the complete comparison table
| Row | Acronym or term | Meaning | Why it matters |
|---|---|---|---|
| 1 | CDM | Construction Design and Management | Main construction health and safety framework. |
| 2 | PCI | Pre-Construction Information | Key information for planning and designing safely. |
| 3 | CPP | Construction Phase Plan | Plan for managing construction health and safety. |
| 4 | PD | Principal Designer | Coordinates pre-construction health and safety on multi-contractor projects. |
| 5 | PC | Principal Contractor | Coordinates the construction phase on multi-contractor projects. |
| 6 | F10 | Notification of Construction Project | Online notification route for notifiable projects in Great Britain. |
| 7 | H&S file | Health and Safety File | Handover file for future safe work. |
| 8 | RAMS | Risk Assessment and Method Statement | Contractor task planning documents. |
| 9 | SKE | Skills, Knowledge and Experience | Competence concept for dutyholder capability. |
Individual editable BuildOut documents
Table ID: cdm-buildout-documents
Source: https://www.sharehub.ltd/knowledge-hub/cdm.html
Row 1
- Document
CDM project mobilisation and coordination procedureBOUK-PRO-CDM · Completed fictional example · v1.0
- Purpose
Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover.
- Editable download
Download DOCXRead preview
Row 2
- Document
Project CDM applicability and dutyholder checklistBOUK-CHK-CDM-01 · Blank editable master · v1.0
- Purpose
Check project definition, client type, contractor count, appointments and notification threshold.
- Editable download
Download DOCXRead preview
Row 3
- Document
Pre-construction information and gap registerBOUK-REG-CDM-01 · Blank register with separate fictional worked entries · v1.0
- Purpose
Track asbestos, services, design, client and existing-structure information gaps.
- Editable download
Download XLSXRead preview
Row 4
- Document
Construction phase planBOUK-PLN-CDM-01 · Completed fictional example · v1.0
- Purpose
Set project health and safety arrangements, site rules and specific high-risk measures before construction starts.
- Editable download
Download DOCXRead preview
Row 5
- Document
F10 notification decision and submission recordBOUK-FRM-CDM-01 · Blank editable master · v1.0
- Purpose
Record threshold assessment, responsible dutyholder and update/submission evidence when required.
- Editable download
Download DOCXRead preview
Row 6
- Document
Coordination meeting and interface action recordBOUK-FRM-CDM-02 · Blank editable master · v1.0
- Purpose
Record trade sequencing, shared risks, access and responsibilities.
- Editable download
Download DOCXRead preview
Row 7
- Document
Health and safety file and handover checklistBOUK-CHK-CDM-02 · Blank editable master · v1.0
- Purpose
Gather proportionate residual-risk information and agree file responsibilities and delivery.
- Editable download
Download DOCXRead preview
Row 8
- Document
Design review and residual-risk communication procedureBOUK-PRO-DES · Completed fictional example · v1.0
- Purpose
Record design decisions, interfaces, change control and safety-critical information.
- Editable download
Download DOCXRead preview
Row 9
- Document
Design hazard and residual-risk registerBOUK-REG-DES-01 · Blank register with separate fictional worked entries · v1.0
- Purpose
Track design elimination/reduction decisions and residual risks requiring communication.
- Editable download
Download XLSXRead preview
Row 10
- Document
Design risk review and change approval recordBOUK-FRM-DES-01 · Blank editable master · v1.0
- Purpose
Review buildability, temporary stability, use and maintenance interfaces.
- Editable download
Download DOCXRead preview
Row 11
- Document
Designer capability and appointment checklistBOUK-CHK-DES-01 · Blank editable master · v1.0
- Purpose
Confirm role, skills, knowledge, experience and organisational capability.
- Editable download
Download DOCXRead preview
Row 12
- Document
Safety-critical design information transmittalBOUK-FRM-DES-02 · Blank editable master · v1.0
- Purpose
Record issue and acknowledgement of significant residual risks.
- Editable download
Download DOCXRead preview
Row 13
- Document
Building-control and higher-risk-building interface screenBOUK-CHK-DES-02 · Blank editable master · v1.0
- Purpose
Determine whether additional building-safety appointments, controls and approvals require specialist review.
- Editable download
Download DOCXRead preview
Read the complete comparison table
| Row | Document | Purpose | Editable download |
|---|---|---|---|
| 1 | CDM project mobilisation and coordination procedureBOUK-PRO-CDM · Completed fictional example · v1.0 | Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover. | Download DOCXRead preview |
| 2 | Project CDM applicability and dutyholder checklistBOUK-CHK-CDM-01 · Blank editable master · v1.0 | Check project definition, client type, contractor count, appointments and notification threshold. | Download DOCXRead preview |
| 3 | Pre-construction information and gap registerBOUK-REG-CDM-01 · Blank register with separate fictional worked entries · v1.0 | Track asbestos, services, design, client and existing-structure information gaps. | Download XLSXRead preview |
| 4 | Construction phase planBOUK-PLN-CDM-01 · Completed fictional example · v1.0 | Set project health and safety arrangements, site rules and specific high-risk measures before construction starts. | Download DOCXRead preview |
| 5 | F10 notification decision and submission recordBOUK-FRM-CDM-01 · Blank editable master · v1.0 | Record threshold assessment, responsible dutyholder and update/submission evidence when required. | Download DOCXRead preview |
| 6 | Coordination meeting and interface action recordBOUK-FRM-CDM-02 · Blank editable master · v1.0 | Record trade sequencing, shared risks, access and responsibilities. | Download DOCXRead preview |
| 7 | Health and safety file and handover checklistBOUK-CHK-CDM-02 · Blank editable master · v1.0 | Gather proportionate residual-risk information and agree file responsibilities and delivery. | Download DOCXRead preview |
| 8 | Design review and residual-risk communication procedureBOUK-PRO-DES · Completed fictional example · v1.0 | Record design decisions, interfaces, change control and safety-critical information. | Download DOCXRead preview |
| 9 | Design hazard and residual-risk registerBOUK-REG-DES-01 · Blank register with separate fictional worked entries · v1.0 | Track design elimination/reduction decisions and residual risks requiring communication. | Download XLSXRead preview |
| 10 | Design risk review and change approval recordBOUK-FRM-DES-01 · Blank editable master · v1.0 | Review buildability, temporary stability, use and maintenance interfaces. | Download DOCXRead preview |
| 11 | Designer capability and appointment checklistBOUK-CHK-DES-01 · Blank editable master · v1.0 | Confirm role, skills, knowledge, experience and organisational capability. | Download DOCXRead preview |
| 12 | Safety-critical design information transmittalBOUK-FRM-DES-02 · Blank editable master · v1.0 | Record issue and acknowledgement of significant residual risks. | Download DOCXRead preview |
| 13 | Building-control and higher-risk-building interface screenBOUK-CHK-DES-02 · Blank editable master · v1.0 | Determine whether additional building-safety appointments, controls and approvals require specialist review. | Download DOCXRead preview |
CPP in plain English
Table ID: construction-phase-plan-cpp-in-plain-english
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Element
Project plan
- What it means
Sets out how the construction phase will be managed.
- What it should not become
A generic company policy folder.
Row 2
- Element
Risk control document
- What it means
Explains site-specific hazards and arrangements.
- What it should not become
A collection of disconnected RAMS.
Row 3
- Element
Communication tool
- What it means
Helps workers and contractors understand site rules.
- What it should not become
A document no one on site has read.
Row 4
- Element
Live document
- What it means
Changes when the project changes.
- What it should not become
A tender-stage file frozen after day one.
Row 5
- Element
Evidence source
- What it means
Shows planning, coordination and review.
- What it should not become
Paperwork with no field implementation.
Read the complete comparison table
| Row | Element | What it means | What it should not become |
|---|---|---|---|
| 1 | Project plan | Sets out how the construction phase will be managed. | A generic company policy folder. |
| 2 | Risk control document | Explains site-specific hazards and arrangements. | A collection of disconnected RAMS. |
| 3 | Communication tool | Helps workers and contractors understand site rules. | A document no one on site has read. |
| 4 | Live document | Changes when the project changes. | A tender-stage file frozen after day one. |
| 5 | Evidence source | Shows planning, coordination and review. | Paperwork with no field implementation. |
Dutyholder responsibilities
Table ID: construction-phase-plan-dutyholder-responsibilities
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Dutyholder
Client
- Cpp role
Ensures suitable arrangements and adequate time/resources.
- Evidence
Appointment records, project brief and checks.
Row 2
- Dutyholder
Principal designer
- Cpp role
Provides pre-construction and design risk information.
- Evidence
Design risk information and coordination records.
Row 3
- Dutyholder
Principal contractor
- Cpp role
Prepares, implements, reviews and revises the CPP.
- Evidence
Approved CPP, revisions, site rules and inspections.
Row 4
- Dutyholder
Contractor
- Cpp role
Prepares CPP on single-contractor projects and follows it on all projects.
- Evidence
RAMS, briefings, worker consultation and supervision.
Row 5
- Dutyholder
Workers
- Cpp role
Follow site rules and report hazards.
- Evidence
Induction, briefings and reporting records.
Read the complete comparison table
| Row | Dutyholder | Cpp role | Evidence |
|---|---|---|---|
| 1 | Client | Ensures suitable arrangements and adequate time/resources. | Appointment records, project brief and checks. |
| 2 | Principal designer | Provides pre-construction and design risk information. | Design risk information and coordination records. |
| 3 | Principal contractor | Prepares, implements, reviews and revises the CPP. | Approved CPP, revisions, site rules and inspections. |
| 4 | Contractor | Prepares CPP on single-contractor projects and follows it on all projects. | RAMS, briefings, worker consultation and supervision. |
| 5 | Workers | Follow site rules and report hazards. | Induction, briefings and reporting records. |
Planning a concrete cut beside occupied offices
Table ID: construction-phase-plan-hierarchy
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Column-1
Eliminate / eliminate
- Column-2
Redesign service route to avoid cutting where feasible.
- Column-3
Designer records decision; hold intrusive work pending survey.
Row 2
- Column-1
Substitute / reduce
- Column-2
Use prefabricated or lower-dust method after compatibility check.
- Column-3
Principal contractor approves method and interface; hold cutting if compatibility or dust control fails.
Row 3
- Column-1
Engineering / isolate and control
- Column-2
Matched dust capture and a physical occupied-area boundary.
- Column-3
Site manager tests capture and segregation; stop on escape.
Row 4
- Column-1
Administrative / discipline
- Column-2
Permit, access schedule, briefing and inspection.
- Column-3
Supervisor checks before each phase; pause on failed coordination.
Row 5
- Column-1
PPE / PPE
- Column-2
Task RPE for residual exposure, not substitute for source capture.
- Column-3
Competent lead checks fit; no work if required PPE fails.
Read the complete comparison table
| Row | Column-1 | Column-2 | Column-3 |
|---|---|---|---|
| 1 | Eliminate / eliminate | Redesign service route to avoid cutting where feasible. | Designer records decision; hold intrusive work pending survey. |
| 2 | Substitute / reduce | Use prefabricated or lower-dust method after compatibility check. | Principal contractor approves method and interface; hold cutting if compatibility or dust control fails. |
| 3 | Engineering / isolate and control | Matched dust capture and a physical occupied-area boundary. | Site manager tests capture and segregation; stop on escape. |
| 4 | Administrative / discipline | Permit, access schedule, briefing and inspection. | Supervisor checks before each phase; pause on failed coordination. |
| 5 | PPE / PPE | Task RPE for residual exposure, not substitute for source capture. | Competent lead checks fit; no work if required PPE fails. |
Examples of high-risk work to consider
Table ID: construction-phase-plan-examples-of-high-risk-work-to-consider
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Work type
Burial, engulfment or serious falls
- Why it matters
Can cause fatal injury quickly.
- Cpp response
Excavation support, edge protection, fall prevention and rescue.
Row 2
- Work type
Chemical or biological substances
- Why it matters
May cause acute or chronic health harm.
- Cpp response
COSHH controls, hygiene, RPE and health monitoring where relevant.
Row 3
- Work type
Work near high-voltage power lines
- Why it matters
Electrical contact can be fatal.
- Cpp response
Exclusion zones, isolation, permits and utility liaison.
Row 4
- Work type
Risk of drowning
- Why it matters
Water work or flood-prone areas need rescue planning.
- Cpp response
Water safety plan and emergency arrangements.
Row 5
- Work type
Wells, underground earthworks and tunnels
- Why it matters
Ground, atmosphere and access risks.
- Cpp response
Temporary works, ventilation, permits and rescue.
Row 6
- Work type
Heavy prefabricated components
- Why it matters
Lifting and stability risks.
- Cpp response
Lift plans, temporary stability and exclusion zones.
Read the complete comparison table
| Row | Work type | Why it matters | Cpp response |
|---|---|---|---|
| 1 | Burial, engulfment or serious falls | Can cause fatal injury quickly. | Excavation support, edge protection, fall prevention and rescue. |
| 2 | Chemical or biological substances | May cause acute or chronic health harm. | COSHH controls, hygiene, RPE and health monitoring where relevant. |
| 3 | Work near high-voltage power lines | Electrical contact can be fatal. | Exclusion zones, isolation, permits and utility liaison. |
| 4 | Risk of drowning | Water work or flood-prone areas need rescue planning. | Water safety plan and emergency arrangements. |
| 5 | Wells, underground earthworks and tunnels | Ground, atmosphere and access risks. | Temporary works, ventilation, permits and rescue. |
| 6 | Heavy prefabricated components | Lifting and stability risks. | Lift plans, temporary stability and exclusion zones. |
Pre-construction information links
Table ID: construction-phase-plan-pre-construction-information-links
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Information
Existing hazards
- Why it matters
Asbestos, services, contamination and fragile materials can change the work method.
- Cpp use
Controls, surveys and permits.
Row 2
- Information
Design risks
- Why it matters
Residual risks must be communicated into construction.
- Cpp use
Sequencing, temporary works and specialist controls.
Row 3
- Information
Site constraints
- Why it matters
Access, neighbours, public routes and live operations affect planning.
- Cpp use
Traffic, segregation and communication plan.
Row 4
- Information
Programme
- Why it matters
Sequencing can create or reduce risk.
- Cpp use
Phasing, coordination and hold points.
Row 5
- Information
Health and safety file needs
- Why it matters
Future maintenance information must be collected.
- Cpp use
Information capture and handover process.
Read the complete comparison table
| Row | Information | Why it matters | Cpp use |
|---|---|---|---|
| 1 | Existing hazards | Asbestos, services, contamination and fragile materials can change the work method. | Controls, surveys and permits. |
| 2 | Design risks | Residual risks must be communicated into construction. | Sequencing, temporary works and specialist controls. |
| 3 | Site constraints | Access, neighbours, public routes and live operations affect planning. | Traffic, segregation and communication plan. |
| 4 | Programme | Sequencing can create or reduce risk. | Phasing, coordination and hold points. |
| 5 | Health and safety file needs | Future maintenance information must be collected. | Information capture and handover process. |
CPP review triggers
Table ID: construction-phase-plan-cpp-review-triggers
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Trigger
New contractor
- Why it matters
New work package and interface risks.
- Update action
Review coordination, induction and supervision.
Row 2
- Trigger
Design change
- Why it matters
May change sequence, temporary works or residual risk.
- Update action
Update controls and brief affected teams.
Row 3
- Trigger
Incident or near miss
- Why it matters
Existing arrangements may be weak.
- Update action
Investigate, revise plan and verify actions.
Row 4
- Trigger
Programme change
- Why it matters
Compression or resequencing can create conflict.
- Update action
Review simultaneous operations and resources.
Row 5
- Trigger
Site layout change
- Why it matters
Access, traffic and emergency routes may change.
- Update action
Update site plan and brief.
Row 6
- Trigger
New high-risk activity
- Why it matters
May need permits, specialist controls or notification.
- Update action
Add specific measures and authorisation.
Read the complete comparison table
| Row | Trigger | Why it matters | Update action |
|---|---|---|---|
| 1 | New contractor | New work package and interface risks. | Review coordination, induction and supervision. |
| 2 | Design change | May change sequence, temporary works or residual risk. | Update controls and brief affected teams. |
| 3 | Incident or near miss | Existing arrangements may be weak. | Investigate, revise plan and verify actions. |
| 4 | Programme change | Compression or resequencing can create conflict. | Review simultaneous operations and resources. |
| 5 | Site layout change | Access, traffic and emergency routes may change. | Update site plan and brief. |
| 6 | New high-risk activity | May need permits, specialist controls or notification. | Add specific measures and authorisation. |
Small-project CPP essentials
Table ID: construction-phase-plan-small-project-cpp-essentials
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Element
Project details
- Practical content
What is being done, where and by whom.
- Example
Bathroom refurbishment in occupied house.
Row 2
- Element
Responsible person
- Practical content
Who controls work and decisions.
- Example
Named contractor or site lead.
Row 3
- Element
Site rules
- Practical content
Access, housekeeping, tools, PPE, welfare and security.
- Example
Keep escape routes clear and isolate services.
Row 4
- Element
Key risks
- Practical content
Only the significant job-specific risks.
- Example
Asbestos, dust, work at height and electrical isolation.
Row 5
- Element
Emergency arrangements
- Practical content
First aid, fire and contacts.
- Example
Local A&E, fire route and client contact.
Row 6
- Element
Review
- Practical content
What will change the plan.
- Example
Unexpected asbestos, service damage or new contractor.
Read the complete comparison table
| Row | Element | Practical content | Example |
|---|---|---|---|
| 1 | Project details | What is being done, where and by whom. | Bathroom refurbishment in occupied house. |
| 2 | Responsible person | Who controls work and decisions. | Named contractor or site lead. |
| 3 | Site rules | Access, housekeeping, tools, PPE, welfare and security. | Keep escape routes clear and isolate services. |
| 4 | Key risks | Only the significant job-specific risks. | Asbestos, dust, work at height and electrical isolation. |
| 5 | Emergency arrangements | First aid, fire and contacts. | Local A&E, fire route and client contact. |
| 6 | Review | What will change the plan. | Unexpected asbestos, service damage or new contractor. |
Construction phase plan route
Table ID: construction-phase-plan-jurisdiction
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Column-1
Great Britain
- Column-2
CDM 2015, HSE guidance.
- Column-3
Contractor or principal contractor prepares before work.
Row 2
- Column-1
Northern Ireland
- Column-2
CDM (NI) 2016, HSENI guidance.
- Column-3
Local contractor or principal contractor prepares before work.
Read the complete comparison table
| Row | Column-1 | Column-2 | Column-3 |
|---|---|---|---|
| 1 | Great Britain | CDM 2015, HSE guidance. | Contractor or principal contractor prepares before work. |
| 2 | Northern Ireland | CDM (NI) 2016, HSENI guidance. | Local contractor or principal contractor prepares before work. |
Information handover links
Table ID: construction-phase-plan-information-handover-links
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Information
Residual hazards
- Why it matters later
Future workers need to know what remains.
- Cpp link
H&S file information capture.
Row 2
- Information
Design changes
- Why it matters later
As-built condition may differ from original design.
- Cpp link
Change control and drawing updates.
Row 3
- Information
Fire and structural details
- Why it matters later
Future safety depends on accurate installation records.
- Cpp link
Inspection and quality hold points.
Row 4
- Information
Maintenance access
- Why it matters later
Future work must be planned safely.
- Cpp link
Access strategy and handover notes.
Row 5
- Information
Temporary works learning
- Why it matters later
Temporary decisions can affect permanent works.
- Cpp link
TWC records and close-out.
Read the complete comparison table
| Row | Information | Why it matters later | Cpp link |
|---|---|---|---|
| 1 | Residual hazards | Future workers need to know what remains. | H&S file information capture. |
| 2 | Design changes | As-built condition may differ from original design. | Change control and drawing updates. |
| 3 | Fire and structural details | Future safety depends on accurate installation records. | Inspection and quality hold points. |
| 4 | Maintenance access | Future work must be planned safely. | Access strategy and handover notes. |
| 5 | Temporary works learning | Temporary decisions can affect permanent works. | TWC records and close-out. |
CPP assurance evidence
Table ID: construction-phase-plan-cpp-assurance-evidence
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Evidence
Induction records
- What it shows
People received site rules and emergency information.
- What to watch for
Generic induction not linked to the project.
Row 2
- Evidence
Site inspections
- What it shows
Controls are checked in the field.
- What to watch for
Repeated findings without close-out.
Row 3
- Evidence
Coordination meetings
- What it shows
Contractors and workfaces are coordinated.
- What to watch for
Minutes with no decisions or actions.
Row 4
- Evidence
Permit records
- What it shows
High-risk work is authorised and controlled.
- What to watch for
Office-issued permits or weak handover.
Row 5
- Evidence
Revision log
- What it shows
The plan is updated after change.
- What to watch for
Old versions still in use.
Row 6
- Evidence
Worker feedback
- What it shows
People can raise issues and improve controls.
- What to watch for
No feedback route or no response.
Read the complete comparison table
| Row | Evidence | What it shows | What to watch for |
|---|---|---|---|
| 1 | Induction records | People received site rules and emergency information. | Generic induction not linked to the project. |
| 2 | Site inspections | Controls are checked in the field. | Repeated findings without close-out. |
| 3 | Coordination meetings | Contractors and workfaces are coordinated. | Minutes with no decisions or actions. |
| 4 | Permit records | High-risk work is authorised and controlled. | Office-issued permits or weak handover. |
| 5 | Revision log | The plan is updated after change. | Old versions still in use. |
| 6 | Worker feedback | People can raise issues and improve controls. | No feedback route or no response. |
BuildOut Ltd worked example
Table ID: construction-phase-plan-buildout-ltd-worked-example
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Management area
Assess and plan
- How buildout applies it
Uses tender and pre-construction information to prepare project-specific CPPs.
- Evidence and improvement
CPP, PCI review and project risk register.
Row 2
- Management area
Implement
- How buildout applies it
Turns CPP into site rules, inductions, RAMS, permits and inspections.
- Evidence and improvement
Induction records, site plan and permit pack.
Row 3
- Management area
Coordinate contractors
- How buildout applies it
Runs start-up meetings and weekly coordination for subcontractors.
- Evidence and improvement
Meeting notes, interface register and action tracker.
Row 4
- Management area
Check controls
- How buildout applies it
Supervisors inspect workfaces and compare conditions with the CPP.
- Evidence and improvement
Inspection records and photographs.
Row 5
- Management area
Learn and update
- How buildout applies it
Revises the CPP after change, incident, new contractor or audit finding.
- Evidence and improvement
Revision log and briefing records.
Row 6
- Management area
Improve system
- How buildout applies it
Reviews recurring CPP weaknesses across projects.
- Evidence and improvement
Management review and template updates.
Read the complete comparison table
| Row | Management area | How buildout applies it | Evidence and improvement |
|---|---|---|---|
| 1 | Assess and plan | Uses tender and pre-construction information to prepare project-specific CPPs. | CPP, PCI review and project risk register. |
| 2 | Implement | Turns CPP into site rules, inductions, RAMS, permits and inspections. | Induction records, site plan and permit pack. |
| 3 | Coordinate contractors | Runs start-up meetings and weekly coordination for subcontractors. | Meeting notes, interface register and action tracker. |
| 4 | Check controls | Supervisors inspect workfaces and compare conditions with the CPP. | Inspection records and photographs. |
| 5 | Learn and update | Revises the CPP after change, incident, new contractor or audit finding. | Revision log and briefing records. |
| 6 | Improve system | Reviews recurring CPP weaknesses across projects. | Management review and template updates. |
Role-level learning and competence evidence
Table ID: construction-phase-plan-competence-decisions
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Column-1
Single contractor
- Column-2
Prepare a proportionate plan and brief it; construction manager assesses.
- Column-3
Dated plan and observation; update after sequence change.
Row 2
- Column-1
Principal contractor
- Column-2
Coordinate multi-contractor interfaces and GB Schedule 3 / NI Schedule 4 controls; client checks.
- Column-3
Plan, consultation and inspection log; review after contractor change.
Row 3
- Column-1
Designer
- Column-2
Show how a hazard was removed or passed on; principal designer checks.
- Column-3
Design decision and residual-risk transfer; revisit after redesign.
Read the complete comparison table
| Row | Column-1 | Column-2 | Column-3 |
|---|---|---|---|
| 1 | Single contractor | Prepare a proportionate plan and brief it; construction manager assesses. | Dated plan and observation; update after sequence change. |
| 2 | Principal contractor | Coordinate multi-contractor interfaces and GB Schedule 3 / NI Schedule 4 controls; client checks. | Plan, consultation and inspection log; review after contractor change. |
| 3 | Designer | Show how a hazard was removed or passed on; principal designer checks. | Design decision and residual-risk transfer; revisit after redesign. |
Warning signs and improvements
Table ID: construction-phase-plan-warning-signs-and-improvements
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Warning sign
Generic plan
- What it suggests
The CPP may not reflect site risk.
- What to improve
Rewrite around project-specific hazards and controls.
Row 2
- Warning sign
No welfare detail
- What it suggests
Basic legal and worker needs may be missed.
- What to improve
Specify toilets, washing, rest and drinking water.
Row 3
- Warning sign
No GB Schedule 3 / NI Schedule 4 consideration
- What it suggests
High-risk work may be underplanned.
- What to improve
Add specific measures and controls.
Row 4
- Warning sign
Unclear dutyholders
- What it suggests
Coordination and accountability may fail.
- What to improve
Define roles, names and escalation.
Row 5
- Warning sign
Old site plan
- What it suggests
Routes, storage or emergency arrangements may be wrong.
- What to improve
Update drawings and brief changes.
Row 6
- Warning sign
No evidence of use
- What it suggests
The CPP may be a file, not a control.
- What to improve
Link to inductions, inspections and actions.
Read the complete comparison table
| Row | Warning sign | What it suggests | What to improve |
|---|---|---|---|
| 1 | Generic plan | The CPP may not reflect site risk. | Rewrite around project-specific hazards and controls. |
| 2 | No welfare detail | Basic legal and worker needs may be missed. | Specify toilets, washing, rest and drinking water. |
| 3 | No GB Schedule 3 / NI Schedule 4 consideration | High-risk work may be underplanned. | Add specific measures and controls. |
| 4 | Unclear dutyholders | Coordination and accountability may fail. | Define roles, names and escalation. |
| 5 | Old site plan | Routes, storage or emergency arrangements may be wrong. | Update drawings and brief changes. |
| 6 | No evidence of use | The CPP may be a file, not a control. | Link to inductions, inspections and actions. |
Source tables and records 4
Official sources and decisions
Table ID: construction-phase-plan-official-links
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Column-1
HSE, Great Britain
- Column-2
HSE planning for construction work
- Column-3
Great Britain CDM guidance
- Column-4
Who prepares plan and when
Row 2
- Column-1
HSE, Great Britain
- Column-2
HSE principal contractor duties
- Column-3
Great Britain CDM guidance
- Column-4
Multi-contractor PC plan, review and worker engagement
Row 3
- Column-1
HSE, Great Britain
- Column-2
HSE CIS80 construction phase plan
- Column-3
Great Britain small-project guidance
- Column-4
Proportionate plan for small/domestic projects
Row 4
- Column-1
HSE, Great Britain
- Column-2
HSE CDM 2015 L153
- Column-3
Great Britain guidance on regulations
- Column-4
GB CDM roles, Schedule 3 and plan content
Row 5
- Column-1
HSENI, Northern Ireland
- Column-2
HSENI CDM (NI) 2016 overview
- Column-3
Northern Ireland regulator guidance
- Column-4
NI plan and dutyholder route
Row 6
- Column-1
UK legislation
- Column-2
CDM Regulations (NI) 2016, latest available text
- Column-3
Northern Ireland statutory rule; check effects
- Column-4
NI construction phase duties and Schedule 4 work
Row 7
- Column-1
HSE
- Column-2
HSE Managing for health and safety (HSG65)
- Column-3
Great Britain
- Column-4
Free GB regulator guidance on planning, doing, checking and acting on health and safety controls.
Row 8
- Column-1
HSE
- Column-2
HSE five-level hierarchy
- Column-3
Great Britain
- Column-4
Higher controls first; ERICPD complementary
Row 9
- Column-1
HSE
- Column-2
HSE CIS69 on-tool extraction
- Column-3
Great Britain
- Column-4
Actual-task compatible capture, checks and maintenance
Row 10
- Column-1
Building Safety Regulator
- Column-2
BSR keeping the golden thread
- Column-3
England
- Column-4
Applicable higher-risk building work: information and dutyholder arrangements
Read the complete comparison table
| Row | Column-1 | Column-2 | Column-3 | Column-4 |
|---|---|---|---|---|
| 1 | HSE, Great Britain | HSE planning for construction work | Great Britain CDM guidance | Who prepares plan and when |
| 2 | HSE, Great Britain | HSE principal contractor duties | Great Britain CDM guidance | Multi-contractor PC plan, review and worker engagement |
| 3 | HSE, Great Britain | HSE CIS80 construction phase plan | Great Britain small-project guidance | Proportionate plan for small/domestic projects |
| 4 | HSE, Great Britain | HSE CDM 2015 L153 | Great Britain guidance on regulations | GB CDM roles, Schedule 3 and plan content |
| 5 | HSENI, Northern Ireland | HSENI CDM (NI) 2016 overview | Northern Ireland regulator guidance | NI plan and dutyholder route |
| 6 | UK legislation | CDM Regulations (NI) 2016, latest available text | Northern Ireland statutory rule; check effects | NI construction phase duties and Schedule 4 work |
| 7 | HSE | HSE Managing for health and safety (HSG65) | Great Britain | Free GB regulator guidance on planning, doing, checking and acting on health and safety controls. |
| 8 | HSE | HSE five-level hierarchy | Great Britain | Higher controls first; ERICPD complementary |
| 9 | HSE | HSE CIS69 on-tool extraction | Great Britain | Actual-task compatible capture, checks and maintenance |
| 10 | Building Safety Regulator | BSR keeping the golden thread | England | Applicable higher-risk building work: information and dutyholder arrangements |
Acronyms and plain-English meanings
Table ID: construction-phase-plan-acronyms-and-plain-english-meanings
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Acronym
CDM
- Meaning
Construction (Design and Management)
- Why it matters
Main construction health and safety regime.
Row 2
- Acronym
CPP
- Meaning
Construction phase plan
- Why it matters
Plan for managing health, safety and welfare during construction.
Row 3
- Acronym
F10
- Meaning
HSE construction project notification
- Why it matters
Required for notifiable projects meeting CDM thresholds.
Row 4
- Acronym
HSE
- Meaning
Health and Safety Executive
- Why it matters
GB regulator and official guidance source.
Row 5
- Acronym
HSENI
- Meaning
Health and Safety Executive for Northern Ireland
- Why it matters
Northern Ireland regulator and official guidance source.
Row 6
- Acronym
PCI
- Meaning
Pre-construction information
- Why it matters
Information needed to plan construction work safely.
Row 7
- Acronym
PPE
- Meaning
Personal protective equipment
- Why it matters
Last-line personal protection where risks remain.
Row 8
- Acronym
RAMS
- Meaning
Risk assessment and method statement
- Why it matters
Task-level planning documents that support but do not replace the CPP.
Row 9
- Acronym
SSIP
- Meaning
Safety Schemes in Procurement
- Why it matters
Common prequalification route for contractor competence evidence.
Read the complete comparison table
| Row | Acronym | Meaning | Why it matters |
|---|---|---|---|
| 1 | CDM | Construction (Design and Management) | Main construction health and safety regime. |
| 2 | CPP | Construction phase plan | Plan for managing health, safety and welfare during construction. |
| 3 | F10 | HSE construction project notification | Required for notifiable projects meeting CDM thresholds. |
| 4 | HSE | Health and Safety Executive | GB regulator and official guidance source. |
| 5 | HSENI | Health and Safety Executive for Northern Ireland | Northern Ireland regulator and official guidance source. |
| 6 | PCI | Pre-construction information | Information needed to plan construction work safely. |
| 7 | PPE | Personal protective equipment | Last-line personal protection where risks remain. |
| 8 | RAMS | Risk assessment and method statement | Task-level planning documents that support but do not replace the CPP. |
| 9 | SSIP | Safety Schemes in Procurement | Common prequalification route for contractor competence evidence. |
Individual editable BuildOut documents
Table ID: construction-phase-plan-buildout-documents
Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html
Row 1
- Document
Legal and other requirements registerBOUK-REG-GOV-01 · Blank register with separate fictional worked entries · v1.1
- Purpose
A detailed GB construction legal baseline with 142 requirement entries, environmental permits and consents, national overlays and eight completed fictional decisions, plus a blank live register.
- Editable download
Download XLSXRead preview
Row 2
- Document
CDM project mobilisation and coordination procedureBOUK-PRO-CDM · Completed fictional example · v1.0
- Purpose
Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover.
- Editable download
Download DOCXRead preview
Row 3
- Document
Project CDM applicability and dutyholder checklistBOUK-CHK-CDM-01 · Blank editable master · v1.0
- Purpose
Check project definition, client type, contractor count, appointments and notification threshold.
- Editable download
Download DOCXRead preview
Row 4
- Document
Pre-construction information and gap registerBOUK-REG-CDM-01 · Blank register with separate fictional worked entries · v1.0
- Purpose
Track asbestos, services, design, client and existing-structure information gaps.
- Editable download
Download XLSXRead preview
Row 5
- Document
Construction phase planBOUK-PLN-CDM-01 · Completed fictional example · v1.0
- Purpose
Set project health and safety arrangements, site rules and specific high-risk measures before construction starts.
- Editable download
Download DOCXRead preview
Row 6
- Document
F10 notification decision and submission recordBOUK-FRM-CDM-01 · Blank editable master · v1.0
- Purpose
Record threshold assessment, responsible dutyholder and update/submission evidence when required.
- Editable download
Download DOCXRead preview
Row 7
- Document
Coordination meeting and interface action recordBOUK-FRM-CDM-02 · Blank editable master · v1.0
- Purpose
Record trade sequencing, shared risks, access and responsibilities.
- Editable download
Download DOCXRead preview
Row 8
- Document
Health and safety file and handover checklistBOUK-CHK-CDM-02 · Blank editable master · v1.0
- Purpose
Gather proportionate residual-risk information and agree file responsibilities and delivery.
- Editable download
Download DOCXRead preview
Row 9
- Document
Site setup, welfare and housekeeping procedureBOUK-PRO-WEL · Completed fictional example · v1.0
- Purpose
Plan boundaries, temporary accommodation, welfare servicing and routes before mobilisation.
- Editable download
Download DOCXRead preview
Row 10
- Document
Site establishment, welfare and access planBOUK-PLN-WEL-01 · Completed fictional example · v1.0
- Purpose
Lay out boundaries, welfare, accommodation, storage and emergency routes.
- Editable download
Download DOCXRead preview
Row 11
- Document
Welfare readiness and daily condition checkBOUK-CHK-WEL-01 · Blank editable master · v1.0
- Purpose
Verify toilets, washing, drinking water, changing and rest facilities are suitable and maintained.
- Editable download
Download DOCXRead preview
Row 12
- Document
Housekeeping, access and storage inspectionBOUK-CHK-WEL-02 · Blank editable master · v1.0
- Purpose
Control slips, trips, waste, stacking and blocked routes.
- Editable download
Download DOCXRead preview
Row 13
- Document
Occupied premises and vulnerable-person interface assessmentBOUK-RA-WEL-01 · Blank editable master · v1.0
- Purpose
Coordinate safe separation, access, dust/noise/fire controls and communication.
- Editable download
Download DOCXRead preview
Row 14
- Document
Site security, visitors and signage checkBOUK-CHK-WEL-03 · Blank editable master · v1.0
- Purpose
Prevent unauthorised access and keep visitors supervised and informed.
- Editable download
Download DOCXRead preview
Row 15
- Document
Water-edge protection and adverse-weather procedureBOUK-PRO-WAT · Completed fictional example · v1.0
- Purpose
Assess changing water/weather conditions, establish rescue/access controls and communicate suspension triggers.
- Editable download
Download DOCXRead preview
Row 16
- Document
Work-near-water and drowning-risk assessmentBOUK-RA-WAT-01 · Blank editable master · v1.0
- Purpose
Evaluate avoidance, barriers, flotation, rescue and changing water conditions.
- Editable download
Download DOCXRead preview
Row 17
- Document
Water rescue and recovery planBOUK-PLN-WAT-01 · Completed fictional example · v1.0
- Purpose
Define suitable equipment, trained people, access and emergency arrangements.
- Editable download
Download DOCXRead preview
Row 18
- Document
Weather, flood and ground-condition checkBOUK-CHK-WAT-01 · Blank editable master · v1.0
- Purpose
Apply project-specific suspension/restart triggers and inspections.
- Editable download
Download DOCXRead preview
Row 19
- Document
Weather stop-work and restart authorisationBOUK-FRM-WAT-01 · Blank editable master · v1.0
- Purpose
Record changed conditions, checks and competent release.
- Editable download
Download DOCXRead preview
Row 20
- Document
Snagging, cleaning and handover in occupied areas RAMSBOUK-RAMS-WEL-01 · Blank editable master · v1.0
- Purpose
Public segregation, cleaning substances, access, isolated tasks and final reinstatement.
- Editable download
Download DOCXRead preview
Read the complete comparison table
| Row | Document | Purpose | Editable download |
|---|---|---|---|
| 1 | Legal and other requirements registerBOUK-REG-GOV-01 · Blank register with separate fictional worked entries · v1.1 | A detailed GB construction legal baseline with 142 requirement entries, environmental permits and consents, national overlays and eight completed fictional decisions, plus a blank live register. | Download XLSXRead preview |
| 2 | CDM project mobilisation and coordination procedureBOUK-PRO-CDM · Completed fictional example · v1.0 | Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover. | Download DOCXRead preview |
| 3 | Project CDM applicability and dutyholder checklistBOUK-CHK-CDM-01 · Blank editable master · v1.0 | Check project definition, client type, contractor count, appointments and notification threshold. | Download DOCXRead preview |
| 4 | Pre-construction information and gap registerBOUK-REG-CDM-01 · Blank register with separate fictional worked entries · v1.0 | Track asbestos, services, design, client and existing-structure information gaps. | Download XLSXRead preview |
| 5 | Construction phase planBOUK-PLN-CDM-01 · Completed fictional example · v1.0 | Set project health and safety arrangements, site rules and specific high-risk measures before construction starts. | Download DOCXRead preview |
| 6 | F10 notification decision and submission recordBOUK-FRM-CDM-01 · Blank editable master · v1.0 | Record threshold assessment, responsible dutyholder and update/submission evidence when required. | Download DOCXRead preview |
| 7 | Coordination meeting and interface action recordBOUK-FRM-CDM-02 · Blank editable master · v1.0 | Record trade sequencing, shared risks, access and responsibilities. | Download DOCXRead preview |
| 8 | Health and safety file and handover checklistBOUK-CHK-CDM-02 · Blank editable master · v1.0 | Gather proportionate residual-risk information and agree file responsibilities and delivery. | Download DOCXRead preview |
| 9 | Site setup, welfare and housekeeping procedureBOUK-PRO-WEL · Completed fictional example · v1.0 | Plan boundaries, temporary accommodation, welfare servicing and routes before mobilisation. | Download DOCXRead preview |
| 10 | Site establishment, welfare and access planBOUK-PLN-WEL-01 · Completed fictional example · v1.0 | Lay out boundaries, welfare, accommodation, storage and emergency routes. | Download DOCXRead preview |
| 11 | Welfare readiness and daily condition checkBOUK-CHK-WEL-01 · Blank editable master · v1.0 | Verify toilets, washing, drinking water, changing and rest facilities are suitable and maintained. | Download DOCXRead preview |
| 12 | Housekeeping, access and storage inspectionBOUK-CHK-WEL-02 · Blank editable master · v1.0 | Control slips, trips, waste, stacking and blocked routes. | Download DOCXRead preview |
| 13 | Occupied premises and vulnerable-person interface assessmentBOUK-RA-WEL-01 · Blank editable master · v1.0 | Coordinate safe separation, access, dust/noise/fire controls and communication. | Download DOCXRead preview |
| 14 | Site security, visitors and signage checkBOUK-CHK-WEL-03 · Blank editable master · v1.0 | Prevent unauthorised access and keep visitors supervised and informed. | Download DOCXRead preview |
| 15 | Water-edge protection and adverse-weather procedureBOUK-PRO-WAT · Completed fictional example · v1.0 | Assess changing water/weather conditions, establish rescue/access controls and communicate suspension triggers. | Download DOCXRead preview |
| 16 | Work-near-water and drowning-risk assessmentBOUK-RA-WAT-01 · Blank editable master · v1.0 | Evaluate avoidance, barriers, flotation, rescue and changing water conditions. | Download DOCXRead preview |
| 17 | Water rescue and recovery planBOUK-PLN-WAT-01 · Completed fictional example · v1.0 | Define suitable equipment, trained people, access and emergency arrangements. | Download DOCXRead preview |
| 18 | Weather, flood and ground-condition checkBOUK-CHK-WAT-01 · Blank editable master · v1.0 | Apply project-specific suspension/restart triggers and inspections. | Download DOCXRead preview |
| 19 | Weather stop-work and restart authorisationBOUK-FRM-WAT-01 · Blank editable master · v1.0 | Record changed conditions, checks and competent release. | Download DOCXRead preview |
| 20 | Snagging, cleaning and handover in occupied areas RAMSBOUK-RAMS-WEL-01 · Blank editable master · v1.0 | Public segregation, cleaning substances, access, isolated tasks and final reinstatement. | Download DOCXRead preview |