CDM essentials for clients and small projects · detailed source study

Optional reference study from the SHAREhub topic pages and selected source records used for this course. The core learning-time estimate excludes this extended reference.

Where does this CDM guide apply?
Where does this CDM guide apply?

Source: appointed-relevent-parties-cdm--scope

Use the project location and actual construction scope before selecting a dutyholder route; this is a build-stage guide, not a project appointment or legal opinion. CDM applies to defined construction work, including many alterations, repairs and demolitions, but not every routine maintenance task. Confirm scope against the relevant regulations. Great Britain uses CDM 2015; Northern Ireland uses its distinct CDM 2016. These pages focus on client and project dutyholders rather than building-control appointments, which are separate roles.

Make appointments from the whole project

Source: appointed-relevent-parties-cdm--review-start

Map the entire project, including trades arriving at different stages, before deciding the appointment route. A single contractor on today's site does not establish that the project is a single-contractor project. Commercial and domestic client routes also differ. Map the entire project, including trades arriving at different stages, before deciding the appointment route. A single contractor on today's site does not establish that the project is a single-contractor project. Construction clients must identify the actual dutyholders before work is organised. Apply it: Which part of this plan would you check at the workface before authorising the task? Construction clients must identify the actual dutyholders before work is organised.

Where a project involves, or is likely to involve, more than one contractor, the client must appoint a principal designer and principal contractor in writing as soon as practicable and before construction begins. Scope, contractor capability, pre-construction information, plan, permit if needed and hand-back. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Contractor isolates services, segregates the occupied area and follows the plan; client coordinates building access. Inspect finished area, reinstate routes and record any residual information needed for future work. Apply it: At which point would you hold this example, and what evidence would allow it to proceed? Designers and contractors may miss asbestos, services or structural constraints.

Incompatible activities can expose workers and other people at the same time. Work starts before a competent owner resolves the method and protection. Use the full topic for the detailed mechanism, task limits and source scope. Apply it: Where is this harm route present in the actual work, and which control breaks it before anyone is exposed? Eliminate: Design plant maintenance so roof-edge access is avoided. Reduce: Assess ground-level or protected-location servicing. Isolate: Provide suitable permanent edge protection and safe access. Control: Coordinate the construction plan, permit and briefing. PPE: Use assessed residual fall protection with a rescue route. Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged.

Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision? Keep one card or the full set for social sharing, team briefings and learning. Each PDF contains one card per page. Read the full topic for explanations, questions and source links.

Map the entire project, including trades arriving at different stages, before deciding the appointment route. Map the entire project, including trades arriving at different stages, before deciding the appointment route. A single contractor on today's site does not establish that the project is a single-contractor project. Construction clients must identify the actual dutyholders before work is organised. Apply it: Which part of this plan would you check at the workface before authorising the task? Use the evidence to improve the actual work arrangement. Construction clients must identify the actual dutyholders before work is organised.

Where a project involves, or is likely to involve, more than one contractor, the client must appoint a principal designer and principal contractor in writing as soon as practicable and before construction begins. Scope, contractor capability, pre-construction information, plan, permit if needed and hand-back. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Fictional example: a practical application of the existing topic lesson. Contractor isolates services, segregates the occupied area and follows the plan; client coordinates building access. Inspect finished area, reinstate routes and record any residual information needed for future work. Apply it: At which point would you hold this example, and what evidence would allow it to proceed?

Connect the task, the route to the person and the control that can fail. Designers and contractors may miss asbestos, services or structural constraints. Incompatible activities can expose workers and other people at the same time. Work starts before a competent owner resolves the method and protection. Use the full topic for the detailed mechanism, task limits and source scope. Apply it: Where is this harm route present in the actual work, and which control breaks it before anyone is exposed? Start with the stronger practicable options and verify their effect. Eliminate: Design plant maintenance so roof-edge access is avoided. Reduce: Assess ground-level or protected-location servicing. Isolate: Provide suitable permanent edge protection and safe access. Control: Coordinate the construction plan, permit and briefing.

PPE: Use assessed residual fall protection with a rescue route. Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged. Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Follow the official sources below and retain the task-specific evidence. Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision?

Simplified learning guide. Use the full topic and the actual work arrangements; existing technical-review and approval statuses still apply. Workplace scenarios labelled fictional are illustrative examples. Identify the people or organisations actually controlling design and construction, obtain suitable capability evidence and make the required roles clear in writing. Notification is an independent decision and cannot replace the appointment test. Use the applicable GB or NI instrument for the location. Compare two illustrative jobs. A householder’s bathroom repair with one contractor uses the applicable domestic-client and sole-contractor planning route; confirm who carries the transferred client duties.

A commercial refurbishment using a builder and later specialist installer is assessed as the whole multi-contractor project, even if their attendance does not overlap; the client records the required principal appointments. Both need a proportionate construction phase plan before construction, and notification remains a separate decision. Illustrative example. A commercial refurbishment uses a builder first and a specialist installer later; the client assumes there is only one contractor because they never overlap. Decision. Review appointments against the whole project contractor pattern and actual design/construction control before start. Evidence to check. Retain project scope, forecast trades, client type, capability checks and written role/document responsibilities. Hold or escalation point. Do not use non-overlap or a notification outcome as a shortcut around the appointment decision. Follow-up.

Revisit when design, procurement or contractor scope changes and brief the affected parties. Open CDM appointment and safe-start gate Read with: HSE CDM dutyholder summary · HSE domestic clients · HSENI CDM 2016 overview · HSE commercial clients.

What is the first CDM appointment decision?
What is the first CDM appointment decision?

Source: appointed-relevent-parties-cdm--decision

Count contractors expected across the whole project, including successive trades and likely subcontractors, then distinguish appointment from notification. Sources for this explanation: HSE CDM dutyholder summary; HSE domestic clients; HSENI CDM 2016 overview.

What must be settled before construction starts?

Source: appointed-relevent-parties-cdm--key-points

A clear client, capable principal roles where required, useful information, realistic time, welfare and a project-specific construction phase plan must be in place. The client owns suitable arrangements and must not offload them by naming an adviser. A principal designer needs influence over pre-construction decisions; a principal contractor needs time to plan the construction phase. Designers should eliminate foreseeable risks where possible, contractors must plan their work, and workers need information and consultation. After a change, revisit roles, plans, design and file rather than treating the original appointment as a one-off form. Sources for this explanation: HSE commercial clients; HSENI CDM 2016 overview.

When and how must principal dutyholders be appointed?

Source: appointed-relevent-parties-cdm--when-required

For a known or reasonably foreseeable multi-contractor project, a commercial client appoints a designer in control and a contractor in writing as soon as practicable, before construction begins. Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE principal designers · HSE planning for construction work. The principal designer should start early enough to influence concept and design risk. The principal contractor must be appointed early enough to help plan the construction phase and prepare the plan. If a commercial client omits either appointment, the client must fulfil that principal role duty; it remains responsible for the project arrangements.

For a domestic client who does not appoint, regulation 7 assigns principal-designer duties to the designer in control and principal-contractor duties to the contractor in control; client duties also transfer under the domestic route. A later second trade triggers a fresh assessment immediately, not only at the next contract renewal. Sources for this explanation: HSE commercial clients; HSE domestic clients; HSENI CDM 2016 overview.

What does each CDM dutyholder actually do?

Source: appointed-relevent-parties-cdm--dutyholders

The client sets suitable arrangements; the principal designer coordinates pre-construction risk; the principal contractor coordinates construction; designers and contractors control their own work. Sources for this explanation: HSE CDM dutyholder summary; HSENI CDM 2016 overview.

How should the client test an appointment?

Source: appointed-relevent-parties-cdm--appointment-evidence

Check the role definition, actual control, project-specific skills, knowledge, experience and organisational capability before recording a clear written appointment. Ask who will make design and site decisions, what time and resources they have, and how they will coordinate the other parties. The check should match risk and complexity. Relevant experience, team availability, supervision, previous performance and design or construction expertise may help. Membership, insurance, third-party schemes and training records can support a proportionate assessment but none is a universal substitute for capability or a fixed CDM legal checklist. Sources for this explanation: HSE CDM dutyholder summary; HSE CDM frequently asked questions.

What must a commercial client do after appointing others?

Source: appointed-relevent-parties-cdm--client-duties

Keep suitable project arrangements under review and ensure information, time, resources, welfare, plan and file are provided or produced as required. The client should provide pre-construction information it holds and obtain missing information proportionately. It must ensure the principal designer and principal contractor carry out their roles, rather than substituting a signature for oversight. Ensure the construction phase plan is prepared before site work and the health and safety file is handed over at project completion where required. Multiple clients should agree the statutory lead arrangement in writing where the regulations allow, while preserving information-sharing duties. Sources for this explanation: HSE commercial clients; HSENI CDM 2016 overview.

How do the two principal roles coordinate?

Source: appointed-relevent-parties-cdm--pd-pc

The principal designer makes design risk and pre-construction information usable; the principal contractor turns it into site coordination and feeds construction changes back. Source basis: HSE principal designers · HSE principal contractors · HSE L153 Managing health and safety in construction · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended). Sources for this explanation: HSE principal designers; HSE principal contractors.

What should designers and contractors check in daily work?

Source: appointed-relevent-parties-cdm--contractors-designers

Designers should remove or reduce foreseeable risk before specifying site controls; contractors must plan and supervise their tasks and coordinate interfaces. A designer might specify permanent roof-edge access rather than rely on repeated temporary edge protection. A contractor must challenge an impracticable design and share method and sequence impacts. Work at height, asbestos, silica, services, structural stability and public access need their own task assessment and controls. A generic RAMS pack is not evidence that the whole project is coordinated, and PPE is a last layer after stronger controls.

Information must cross the project phase boundary

Source: appointed-relevent-parties-cdm--release-cdm-handoffs

This worked coordination record describes a commercial project in Great Britain. Apply the correct GB or Northern Ireland rules and the separate domestic-client route where relevant. A project involving more than one contractor needs principal-role consideration even when the trades work at different times. Excavation example: number the evidence before work: 1 client/site information on services and past use; 2 designer’s relevant risk information; 3 contractor’s checked site conditions and method; 4 resolved changes and relevant handover information. A model view cannot verify any of these records. Notification is a separate check. Do not use the notification threshold to decide whether CDM duties or required appointments apply. Follow the appointment decision and keep the change loop active.

Read with: HSE: CDM dutyholders · HSE: principal designers.

Which CDM documents must exist and who owns them?

Source: appointed-relevent-parties-cdm--documents

Pre-construction information, the construction phase plan and, on multi-contractor projects, the health and safety file serve different decisions and handovers. Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE L153 Managing health and safety in construction · HSE F10 construction notification. Sources for this explanation: HSE planning for construction work; HSE L153 Managing health and safety in construction; HSENI CDM 2016 overview.

What are the before, during and hand-back hold points?
What are the before, during and hand-back hold points?

Source: appointed-relevent-parties-cdm--checks

Use stage gates: check scope and roles before start, control change while work proceeds, and verify the plan, site and file at hand-back.

How can the ISO 45001 hierarchy of controls guide risk reduction by CDM dutyholders?

Source: appointed-relevent-parties-cdm--operational-examples

Match the route to the entire project and revisit it when trades, design, location or hazards change. Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE CDM dutyholder summary · HSENI CDM 2016 overview. These BuildOut Ltd cases are teaching examples. They do not replace a site-specific construction phase plan, competent design, statutory appointment or local emergency procedure. On a refurbishment with several contractors, the client must identify the principal designer and principal contractor route early enough for them to influence planning; an appointment letter alone does not remove a roof-edge fall risk.

The design team first asks whether plant can be maintained from inside the building, eliminating edge access. A ground-level or protected-location service route may substitute for roof work. Where access remains, permanent edge protection and a safe access arrangement are engineering controls selected against the actual structure. A construction-phase plan, permit, briefing and inspection are administrative layers; fall-protection PPE is residual and requires an assessed rescue route. ERICPD Eliminate/Reduce/Isolate/Control map to those choices, while the five-level hierarchy keeps physical design ahead of paperwork. The client checks that the roles, pre-construction information and design decisions are recorded; the principal designer coordinates the residual design risk; the principal contractor checks the installed edge protection and site interface before release.

The competent engineer verifies fixings, loads and inspection criteria for the actual system. ERICPD Discipline means maintaining the barrier and reviewing changes, not blaming a trade worker for a missing design control. If contractor count changes, the plan is absent, the protection is incomplete or the roof condition is unknown, hold the affected work and resolve the appointment, design and construction decisions before access. Sources for this explanation: HSE F10 construction notification; HSENI new construction project notification; HSE domestic clients. ERICPD is a planning crossmap. Its prompts do not add a sixth rung or rank Isolate above engineering. Discipline verifies and sustains every control level.

The hierarchy of controls in ISO 45001:2018 comes under Clause 8.1.2 (Eliminating hazards and reducing OH&S risks), which is located within Clause 8 ("Operation"). ESEAP: Elimination, Substitution, Engineering controls, Administrative controls and PPE. Control order: HSE hierarchy of controls and IOSH hierarchy of control guidance.

What is the compact CDM study model?

Source: appointed-relevent-parties-cdm--study

Separate five decisions: project scope, number of contractors, capable written appointments, project information and plan, then the independent notification threshold. For IOSH Construction learning, explain who is the client, who actually controls design and construction phases, when the roles start, what each must pass on and what evidence proves coordination. This compact study model is a learning aid only. On a live project, use the current regulations and specific arrangements rather than memorising a generic role list.

Which CDM law applies in Great Britain and Northern Ireland?

Source: appointed-relevent-parties-cdm--legal

CDM 2015 is GB law; CDM (Northern Ireland) 2016 is the separate NI instrument. Similar duties do not make either instrument UK-wide. Source basis: Construction (Design and Management) Regulations 2015 (2015, as amended) · Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended) · HSE CDM 2015 legal summary · HSENI CDM 2016 overview. Both regimes cover all in-scope construction projects and require written principal appointments where more than one contractor is involved or reasonably foreseeable. Both require a construction phase plan for every project and a health and safety file for a multi-contractor project. Domestic-client duty transfer is set out in each regime.

The notification test is more than 30 working days with more than 20 workers simultaneously at any point, or more than 500 person-days. Use GB F10 and NI NI10 respectively. A commercial client has the notification duty; on a domestic project regulation 7 passes that duty to the sole contractor, principal contractor or a principal designer with a written agreement to take client duties. Check each instrument for the project; NI schedules and numbering differ. Sources for this explanation: Construction (Design and Management) Regulations 2015; Construction (Design and Management) Regulations (Northern Ireland) 2016.

How could BuildOut Ltd run the appointment process?

Source: appointed-relevent-parties-cdm--business-example

BuildOut Ltd should use a project gate that links the client brief, contractor forecast, written roles, information flow and safe start decision. BuildOut Ltd undertakes construction and refurbishment. On a commercial roof project it asks whether two trades will be engaged, including specialist subcontractors at different stages. Its client representative appoints a capable principal designer while the roof and service design can still change, and a principal contractor with time to plan access, welfare, occupied-premises segregation and trade interfaces. BuildOut gives both principals existing drawings, surveys and service information. The principal contractor signs off a usable construction phase plan before mobilisation; the principal designer keeps design and future maintenance information coordinated.

The client reviews actual site controls and receives the health and safety file at hand-back. When a new trade or unknown service appears, the affected work stops while scope, roles and information are reset.

What competence, training and supervision are needed?

Source: appointed-relevent-parties-cdm--training

Match skills, knowledge, experience, organisational capability, training and supervision to the actual role and risk; no universal CDM card or certificate replaces that assessment. Clients need enough understanding to commission and check the roles, even if they seek specialist support. Principal designers need design control and the ability to coordinate significant risks; principal contractors need capacity to coordinate site work. Workers need relevant task instruction, site-specific induction and supervision. Use proportionate evidence, exercises and observed performance. A training card may help with an individual check, but it is not automatic proof that an organisation can lead this particular project. Record the project decision, dutyholder competence, assessor and reassessment trigger; a training card alone does not appoint a principal role.

Do standards or accreditations satisfy CDM?
Do standards or accreditations satisfy CDM?

Source: appointed-relevent-parties-cdm--standards

Voluntary management standards and procurement schemes may help organise assurance, but only the correct statutory roles and real project controls satisfy CDM duties. ISO 45001 can structure planning, responsibilities, worker participation, checking and improvement. It does not appoint a principal designer or principal contractor, prepare a project plan or prove site controls. Accreditation, insurance and RAMS may be useful evidence depending on the task, but they are not universal statutory appointment conditions. Standards for temporary works, equipment or building design may be relevant to a specific project and must be selected by a competent designer against the actual task.

How should leaders assure CDM delivery?

Source: appointed-relevent-parties-cdm--management-system

Review the quality of decisions and actual controls at project gates, not merely whether a form exists. Set responsibility for scope, appointment, information, plan, change and hand-back. Sample projects for early appointment, site-specific information, workable plans, welfare, worker consultation and file quality. Act on repeated late changes or unclosed defects. Keep a clear record of who authorised each hold and restart. Use incident and near-miss learning to improve design and procurement in the next project.

What indicates that CDM appointments are failing?

Source: appointed-relevent-parties-cdm--warning-signs

Late or unsigned appointments, a principal designer without design control, no plan before work or unmanaged trade interfaces need immediate correction. Other warning signs include generic information packs, undisclosed asbestos or services, a principal contractor with no time to plan, missing welfare, a plan that does not match the site, workers unable to identify the project lead, and a file assembled only after completion. Stop the affected work when a critical unknown or uncontrolled risk is present, then obtain the right design, management and site decision before restart.

Small single-contractor refurbishment

Source: appointed-relevent-parties-cdm--example--one-contractor

Task Material And Setting: BuildOut Ltd repairs a small office partition with one contractor and no expected trade subcontractors; the goal is safe hand-back. People And Prerequisites: Office users, contractor and visitors; locate services, asbestos information and occupied routes before starting. Before: Client identifies site constraints and selects a capable contractor; the contractor prepares a proportionate written construction phase plan and welfare arrangements. During: Contractor isolates services, segregates the occupied area and follows the plan; client coordinates building access. Hold Or Stop: Unexpected second contractor, unknown material or missing service data: stop affected work and reassess appointment and controls. Completion And Hand Back: Inspect finished area, reinstate routes and record any residual information needed for future work.

Evidence: Scope, contractor capability, pre-construction information, plan, permit if needed and hand-back.

Two trades working at different times

Source: appointed-relevent-parties-cdm--example--two-trades

Task Material And Setting: BuildOut Ltd commissions a roof repair followed by an electrician to reroute a cable; the goal is safe coordinated work. People And Prerequisites: Roofers, electrician, occupants and public; the trades need not be on site together for the multi-contractor trigger. Before: Client appoints a designer in control as principal designer and a contractor as principal contractor in writing before construction; checks capability and provides roof, access and service information. During: Principal designer resolves design and maintenance risks; principal contractor plans sequencing, edge protection, site controls and a construction phase plan. Hold Or Stop: No written appointment, unsafe access or unclear service isolation: hold the affected start and escalate to the client.

Completion And Hand Back: Principal designer or successor completes the health and safety file; client accepts the file and any residual risk information. Evidence: Written appointments, risk decisions, plan, coordination brief and file receipt.

A second contractor is added after mobilisation

Source: appointed-relevent-parties-cdm--example--late-subcontractor

Task Material And Setting: A sole-contractor fit-out needs a specialist ventilation installer after opening the ceiling; the goal is to reset control before interface work. People And Prerequisites: Both trades, BuildOut team and building users; concealed services and dust alter the sequence. Before: Pause and revise the project contractor forecast; the client makes written principal appointments as soon as practicable and checks whether the principal designer can influence remaining design. During: Share new information, revise the plan and coordinate access, isolation, temporary works and handover. Hold Or Stop: Do not let the specialist begin because the original job was called single-contractor; unknown ceiling materials or missing principal role means hold.

Completion And Hand Back: Update the file and drawings, verify services and close the change with client sign-off. Evidence: Change notice, appointments, revised plan, briefings and hand-back.

Domestic extension with several trades

Source: appointed-relevent-parties-cdm--example--home-extension

Task Material And Setting: A householder engages a builder, electrician and roofer for an extension; the goal is a safe domestic project. People And Prerequisites: Household members, neighbours and trades; the home is not being improved as a business activity. Before: Identify the designer in control and contractor in control. Domestic client duties normally pass to the principal contractor, or to the principal designer by written agreement; principal roles still apply. During: Principal contractor coordinates trades, site security, welfare and a plan; principal designer addresses build and future-maintenance risk. Hold Or Stop: No clear lead for the construction phase, unprotected household access or undocumented design change: stop and agree control.

Completion And Hand Back: Hand over relevant file information and make the home safe for use. Evidence: Role and duty transfer record, plan, site checks and file handover.

Design change during construction

Source: appointed-relevent-parties-cdm--example--design-change

Task Material And Setting: A beam position changes after BuildOut Ltd opens a floor; the goal is to avoid unsafe improvised support and future maintenance traps. People And Prerequisites: Workers, occupants and future maintainers; structural engineer and principal designer input are needed. Before: Record the changed condition and hold structural work pending competent design and temporary-works assessment. During: Designer checks buildability and future access; principal designer and contractor coordinate revised sequence and information. Hold Or Stop: No approved design, unclear load path or incompatible temporary works: stop and keep the area controlled. Completion And Hand Back: Verify as-built details, update the plan and health and safety file and authorise restart or hand-back. Evidence: Design instruction, calculations, briefings, inspection and updated file.

Large project notification decision
Large project notification decision

Source: appointed-relevent-parties-cdm--example--notification

Task Material And Setting: As a commercial client, BuildOut Ltd plans 35 working days with 20 workers at peak and 540 person-days; the goal is to notify the correct regulator while managing all duties. People And Prerequisites: Commercial client, designers, contractors and regulator; programme estimates are documented. Before: The 540 person-days exceeds the separate notification threshold even though peak staffing is below 21; the commercial client verifies the estimate and notifies HSE by F10 in GB or HSENI by NI10 in NI. During: Maintain written principal appointments because more than one contractor is expected, plus the plan, welfare and coordination. Hold Or Stop: Do not use notification as permission to start or assume a sub-threshold project is exempt from CDM.

Completion And Hand Back: Update notification if required and retain the submission with project records. Evidence: Programme calculation, appointments, plan and notification reference.

Unsafe opening and missing information

Source: appointed-relevent-parties-cdm--example--uncontrolled-opening

Task Material And Setting: During an occupied-building refurbishment, workers uncover an unrecorded void and damaged service; the goal is to protect people and reset the plan. People And Prerequisites: Workers, occupants and visitors; actual structure and energisation state are unknown. Before: Use site rules, reporting and a named authority for changed conditions; keep public access segregated. During: Stop the affected activity, make the area safe without disturbing the service, and obtain competent survey/design advice. Hold Or Stop: Do not proceed on an assumption that the drawing is current, or let another trade enter without revised information. Completion And Hand Back: Client, principal designer and principal contractor review revised design, plan, briefings and safe hand-back. Evidence: Stop record, survey, design decision, plan revision, briefing and release.

Decide scope, the plan and appointments before notification

Source: cdm--review-start

Keep three decisions visible. First identify construction work and the applicable GB or NI regime. Then establish who must prepare and use the construction phase plan and whether principal appointments are needed. Finally apply the separate notification test to the programme and labour forecast. Being below a notification threshold does not answer either planning question. Keep three decisions visible. First identify construction work and the applicable GB or NI regime. CDM makes clients, designers and contractors plan, coordinate and control construction risk from design through handover. Apply it: Which part of this plan would you check at the workface before authorising the task? CDM makes clients, designers and contractors plan, coordinate and control construction risk from design through handover.

Great Britain uses CDM 2015 and Northern Ireland uses CDM (NI) 2016. CDM project register. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Assess: Screens project scope, dutyholder role, notification, high-risk work and information needs. Evidence / response: CDM project register. Analyse: Reviews design risk, site constraints, services, asbestos, welfare and contractor interfaces. Evidence / response: PCI review and risk workshop. Apply it: At which point would you hold this example, and what evidence would allow it to proceed? Late appointments: Design and planning risk is missed. Generic CPP: Real site risks are not controlled. Missing PCI: Asbestos, services or structural hazards are discovered late.

Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Avoid risks: Remove hazards through design or method. Evaluate unavoidable risks: Assess remaining risks before work starts. Combat risks at Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision?

Keep one card or the full set for social sharing, team briefings and learning. Each PDF contains one card per page. Read the full topic for explanations, questions and source links. Keep three decisions visible. Keep three decisions visible. First identify construction work and the applicable GB or NI regime. CDM makes clients, designers and contractors plan, coordinate and control construction risk from design through handover. Apply it: Which part of this plan would you check at the workface before authorising the task? Use the evidence to improve the actual work arrangement. CDM makes clients, designers and contractors plan, coordinate and control construction risk from design through handover. Great Britain uses CDM 2015 and Northern Ireland uses CDM (NI) 2016. CDM project register.

Apply it: What evidence would show that the change improves this task, rather than only completing a record? Fictional example: a practical application of the existing topic lesson. Assess: Screens project scope, dutyholder role, notification, high-risk work and information needs. Evidence / response: CDM project register. Analyse: Reviews design risk, site constraints, services, asbestos, welfare and contractor interfaces. Evidence / response: PCI review and risk workshop. Apply it: At which point would you hold this example, and what evidence would allow it to proceed? Connect the task, the route to the person and the control that can fail. Late appointments: Design and planning risk is missed. Generic CPP: Real site risks are not controlled. Missing PCI: Asbestos, services or structural hazards are discovered late.

Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Start with the stronger practicable options and verify their effect. Avoid risks: Remove hazards through design or method. Evaluate unavoidable risks: Assess remaining risks before work starts. Combat risks at Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Follow the official sources below and retain the task-specific evidence. Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status.

Apply it: Which official source and full-topic section will you use to resolve the next decision? Simplified learning guide. Use the full topic and the actual work arrangements; existing technical-review and approval statuses still apply. Workplace scenarios labelled fictional are illustrative examples. Follow a small repair as the scope changes. One contractor plans the initial work; when a second trade is likely to join, the client must revisit the principal-role decision and coordination before that work starts. Use

CDM Dutyholders and Appointments

for the appointment evidence and Construction Phase Plan for the live site arrangements. For a domestic project, use the existing client-transfer explanation rather than assuming the householder carries every commercial-client task. Illustrative example. A fictional single-contractor repair expands to include a separate electrical contractor. Decision. The client and project lead revisit principal appointments and coordination, and revise the plan before the additional work begins. Evidence to check. Work scope, contractor forecast, role and appointment record, live plan and separate notification calculation. Hold or escalation point. Hold the changed work if the responsible roles or coordination arrangements are unresolved. Follow-up. Review programme, interfaces and the notification forecast whenever scope or labour changes. Read with: HSE CDM 2015 · HSE CDM FAQ · HSE dutyholder responsibilities.

Coordinate the project before work begins
Coordinate the project before work begins

Source: cdm--practical-cdm

Client information, design coordination and construction-phase planning form a connected route. Notification is a separate check, rather than permission to start unsafe work. Establish the work, location, parties and pre-construction information, including what is uncertain. Apply the relevant single/multiple-contractor arrangements and principal roles where required. Information must reach those who need it to plan and control the work. Prepare and use the construction phase plan; check welfare, interfaces, responsibilities and changes. Consider the applicable notification requirement separately. The location marker and records are teaching aids, not a service survey, excavation permit or automatic confirmation of CDM compliance. Further guidance: HSE: construction.

What are the key facts about CDM?

Source: cdm--key-facts

The key facts are that CDM applies across the project lifecycle, assigns dutyholders and requires risk control before work starts.

What are the Construction Design and Management Regulations?

Source: cdm--what-is-it

The Construction Design and Management Regulations are construction health and safety regulations that require projects to be planned, coordinated and controlled from concept to completion. CDM exists because construction risks are often created long before a worker steps onto site. A design can make roof access safer or dangerous. A client can allow enough time and budget or force rushed work. A contractor can plan a safe sequence or improvise around missing information. The regulations create named dutyholders so responsibility does not disappear between organisations. They require cooperation, coordination and communication between the people who commission, design and build.

A strong CDM project feels organised: the right people are appointed early, hazards are known, the construction phase plan is specific, welfare is ready, workers are briefed, contractors are coordinated and the health and safety file is useful at handover.

What work is covered by CDM?

Source: cdm--scope

CDM covers a wide range of building, civil engineering and engineering construction work, including construction, alteration, repair, maintenance, demolition and dismantling. CDM is broader than many people think. It can apply to new build, refurbishment, fit-out, demolition, maintenance, repair, redecoration, commissioning, decommissioning, excavation, site clearance, service installation and work on structures. The practical test is not whether the job feels large or formal. The question is whether construction work is being carried out. A one-day roof repair, intrusive maintenance task or small commercial refurbishment can still need CDM planning. Some routine activities may sit outside CDM if they are not construction work, but they may still fall under other health and safety law.

When in doubt, the safer professional approach is to define the work, identify hazards and plan proportionate controls.

How do the general principles of prevention shape CDM?

Source: cdm--principles

The general principles of prevention require dutyholders to avoid risks where possible and control unavoidable risks at source. CDM is built around prevention. Designers and contractors should not jump straight to PPE or warning signs. They should first ask whether the hazard can be avoided, designed out, substituted, isolated or controlled by safer sequencing and collective measures. This is why early design review is so powerful. A permanent edge-protected access route is better than repeated scaffold improvisation. Ground beams designed around known services are better than discovering utilities during excavation. A maintained plantroom with access space is better than forcing future maintenance into awkward or unsafe positions.

The prevention principles also support better health control: design out silica cutting where possible, plan dust control, avoid manual handling through mechanical aids and ensure welfare is available from the start.

Who are the CDM dutyholders?

Source: cdm--dutyholders

The CDM dutyholders are clients, designers, principal designers, principal contractors, contractors and workers. Each dutyholder has a different influence point. Clients control brief, time, budget and appointments. Designers influence risk through design. Principal designers coordinate pre-construction risk. Principal contractors coordinate construction. Contractors control their own work. Workers cooperate and report risks. The principal designer and principal contractor must be appointed in writing where the project involves, or is likely to involve, more than one contractor. If the client fails to appoint them when required, the client can retain duties that should have been properly allocated. Domestic clients are treated differently from commercial clients. In most domestic projects, the client duties pass to other dutyholders unless specific written arrangements are made.

Which CDM documents are most important?

Source: cdm--documents

The central CDM records are useful pre-construction information, a construction phase plan, a health and safety file where required, and location-specific notification when the threshold is met. CDM paperwork should help people make decisions. It should not exist as a disconnected pack of generic templates. Pre-construction information should tell the project team about existing hazards and constraints. The construction phase plan should explain how the actual work will be managed. The health and safety file should help future work be safer. A small project may need a simple construction phase plan. A complex project may need detailed sequencing, interface management, emergency arrangements, temporary works, fire strategy, logistics and contractor coordination. The best documents are updated as the project changes.

If asbestos, buried services, design changes, temporary works, weather, lifting plans or sequencing changes, the documents should change too.

When must a construction project be notified?

Source: cdm--notification

CDM applies before notification is considered. Notify only if a statutory threshold is forecast to be met, using the correct GB or NI regulator route. Both HSE and HSENI describe a project as notifiable when construction work is scheduled to last longer than 30 working days and have more than 20 people on site at any time, or when it exceeds 500 person-days. The tests are alternatives. Keep a dated programme and labour forecast, review them as the project changes and notify in time when the test is met. These thresholds do not decide whether a principal designer, principal contractor, construction phase plan, welfare or cooperation are needed.

In Great Britain the client normally uses HSE’s F10 route, with special arrangements for domestic projects and some regulator-specific sites. In Northern Ireland the client notifies HSENI under CDM (NI) 2016 using its NI route, commonly NI10; the GB F10 is not the NI notification. Verify the receiving authority and form on the current regulator page, especially for specialist sites. The HSENI NI10 PDF linked below is marked non-accessible; request an accessible route from HSENI if needed.

What should happen during the pre-construction phase?
What should happen during the pre-construction phase?

Source: cdm--preconstruction

The pre-construction phase should identify foreseeable risks, plan design decisions, provide information and prepare for safe construction. Pre-construction is where the project can avoid many hazards cheaply and intelligently. The team should review site constraints, asbestos, surveys, buried services, ground conditions, access, public interface, existing structures, temporary works, logistics, fire, lifting, health risks and future maintenance. The principal designer coordinates health and safety in the pre-construction phase on multi-contractor projects. Designers should not simply pass every risk to the contractor. They should eliminate where possible, reduce where they cannot eliminate, and communicate significant residual risks clearly. The client should ensure enough time and resources are available. Rushed design, poor surveys and late contractor appointment often create avoidable risk on site.

How should the construction phase be controlled?

Source: cdm--construction-phase

The construction phase should be controlled through a project-specific plan, coordination, supervision, communication, welfare, inspections and change control. The construction phase plan should be in place before construction begins. It should explain how the site will be managed, how high-risk work will be controlled, how contractors will coordinate, how the public will be protected and how emergency arrangements will work. The principal contractor coordinates the construction phase on multi-contractor projects. That means more than collecting RAMS. It includes site induction, sequencing, interface management, traffic routes, fire control, temporary works, welfare, worker consultation and monitoring that controls are actually used. Change control is essential. Design changes, additional trades, late materials, weather, sequencing changes and unexpected ground or structural conditions can all create new risks.

What welfare arrangements are required under CDM?

Source: cdm--welfare

CDM requires suitable welfare facilities to be available from the start and maintained throughout construction work. Welfare is a basic control, not a comfort extra. Toilets, washing facilities, drinking water, rest areas, changing facilities and arrangements for hot food or drink where needed all affect hygiene, dignity, fatigue, dust control, skin protection and worker welfare. Poor welfare undermines health controls. Workers exposed to cement, dust, asbestos, lead, biological agents or contaminated ground need washing and changing arrangements. Workers doing hard physical work need rest and hydration. Clients and contractors should confirm welfare arrangements before work starts, especially on short projects where teams may otherwise improvise.

What should happen at handover and close-out?

Source: cdm--handover

CDM close-out should provide useful health and safety information for future operation, maintenance, cleaning, refurbishment and demolition. The health and safety file should not be a box of unused documents. It should tell future dutyholders what they need to know: residual structural risks, maintenance access, buried services, asbestos information, fire precautions, plant details, hazardous materials and unusual design assumptions. The principal designer prepares and updates the health and safety file during the project, then it is handed to the client. If the principal designer's appointment ends before the project finishes, arrangements are needed so the file remains current. Close-out should also review lessons learned. Design decisions, contractor performance, incidents, near misses and late changes should feed into future projects.

How should CDM compliance be checked?

Source: cdm--assurance

CDM compliance should be checked through active monitoring, document review, site verification, worker feedback and close-out evidence. A CDM audit should not only check whether documents exist. It should test whether the documents are useful, current and being used by the people making decisions. First-line assurance is daily supervision: inductions, briefings, permits, welfare checks and control observations. Second-line assurance is project or H&S review: appointments, PCI, CPP, design risk, contractor performance and inspections. Third-line assurance is independent audit or client review of the project management system. Findings should be ranked and assigned to named owners. A finding is not closed because someone updates a document; it is closed when the corrected arrangement is working on site.

Which legal duties apply to CDM?

Source: cdm--legal

Use CDM 2015 for Great Britain and CDM (Northern Ireland) 2016 for Northern Ireland; check hazard-specific law in the same jurisdiction. Clients must make suitable arrangements and provide relevant pre-construction information. Where more than one contractor is involved or likely, the principal designer and principal contractor roles need appointment; the construction phase plan is not limited to notifiable jobs. Designers eliminate or reduce foreseeable risk and pass on significant residual information. Contractors plan, manage and monitor their work and cooperate with the project team. The precise legal route and any domestic-client transfer depend on GB or NI law and project facts. England Building Regulations dutyholder roles are a separate building-control regime.

A project may need both sets of decisions, but do not treat England building-control law as GB-wide or NI CDM law. Work at height, asbestos, fire, lifting and welfare obligations also require their own location-specific legal check.

How could BuildOut Ltd manage CDM?

Source: cdm--business-example

BuildOut Ltd would manage CDM through a project register, appointment checks, design-risk coordination, construction phase planning, welfare verification, contractor control and handover close-out. a fictional construction and fit-out contractor delivering refurbishment, small works, maintenance, demolition-enabling works and multi-trade commercial projects BuildOut starts every job with a CDM triage. The project coordinator records the client, site, scope, number of contractors, likely notification status, high-risk activities, existing information, required appointments and whether BuildOut is acting as contractor, principal contractor or designer. For multi-contractor work, written appointment checks are completed before the construction phase begins. The project team collects pre-construction information such as asbestos surveys, service drawings, structural information, access restrictions, fire constraints, public interface, welfare and emergency arrangements.

During construction, the site manager works from a project-specific construction phase plan. Subcontractors are coordinated through pre-start meetings, daily briefings, permits, inspections and change control. Welfare is checked before mobilisation and weekly thereafter. Design changes are fed back to the principal designer and the health and safety file owner. BuildOut uses assurance at three levels. Supervisors complete binary site checks. H&S advisers review higher-risk projects and sample evidence. Senior management reviews project close-out, incidents, contractor performance and health and safety file quality. Actions are ranked, owned and verified before closure.

What should each role learn and demonstrate?
What should each role learn and demonstrate?

Source: cdm--training

Learning must match the decisions people make, from recognising danger to checking that controls work. Briefings should tell people how to act, but attendance alone does not show competence. Assess the real decision or task, record who assessed it and revisit after a material change, failed control or incident. A local authorisation is task-specific; no universal external certificate is implied.

How does CDM support qualification study and professional development?

Source: cdm--study-development

CDM helps learners understand construction risk governance, dutyholders, planning, coordination, welfare and control of high-risk work. For the IOSH Construction Certificate, CDM is a core organising topic. Learners should know the dutyholders, project documents, notification thresholds, welfare expectations, construction phase controls and how design risk is eliminated or reduced. For the IOSH National General Certificate, CDM supports contractor control, management arrangements, risk assessment and construction hazards. For Diploma study, it supports governance, assurance, lifecycle risk and client leadership. A strong scenario answer should explain who should have done what, when. CDM questions are rarely just about a form; they are about whether dutyholders planned, coordinated and monitored the work well enough to prevent harm.

How can a management system sustain effective decisions?

Source: cdm--management-system

Give each hazard or support route an owner, a control, a check and a response to failure. Project records should show early appointments, design decisions, construction phase plan updates, site observations, worker consultation and useful handover information. A leader should test an actual change in design or programme and verify that the right dutyholders and controls were updated. An owner should sample actual work and corrective actions, not accept a policy or certificate as evidence that the controls work. The free GB regulator guide HSE Managing for health and safety (HSG65) explains a plan–do–check–act approach: assign controls and owners, involve workers, check work as done, and correct failures. For Northern Ireland, use HSENI risk assessment guidance for the local duty.

A certificate alone does not demonstrate that a control works.

What are the warning signs that CDM is not being managed?

Source: cdm--warning-signs

Warning signs include late appointments, generic plans, missing pre-construction information, poor welfare, weak contractor control and no useful handover file. CDM failure usually shows before an accident. The client cannot explain arrangements. The principal designer is appointed after design decisions are made. The principal contractor receives little information. Contractors arrive with generic RAMS. Welfare is incomplete. Workers do not understand the plan. Another warning sign is paperwork without influence. If the construction phase plan does not shape inductions, logistics, permits and inspections, it is not controlling the job. Poor close-out also matters. If the health and safety file is incomplete, future maintenance workers inherit risk that could have been communicated.

Show how the live plan changes the workface

Source: construction-phase-plan--review-start

A meaningful small-job plan names the work and responsible people, the actual site hazards and controls, access, welfare, emergency arrangements and how change will be managed. It should be short enough to use and specific enough to guide the first day. Notification is a separate decision, not an exemption from planning. A meaningful small-job plan names the work and responsible people, the actual site hazards and controls, access, welfare, emergency arrangements and how change will be managed. It should be short enough to use and specific enough to guide the first day. Every construction project needs a suitable construction phase plan before construction begins. Apply it: Which part of this plan would you check at the workface before authorising the task?

Every construction project needs a suitable construction phase plan before construction begins. Make it proportionate to the work, with site rules, management arrangements and specific GB Schedule 3 / NI Schedule 4 risk measures. CPP, PCI review and project risk register. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Assess and plan: Uses tender and pre-construction information to prepare project-specific CPPs. Evidence / response: CPP, PCI review and project risk register. Implement: Turns CPP into site rules, inductions, RAMS, permits and inspections. Evidence / response: Induction records, site plan and permit pack. Apply it: At which point would you hold this example, and what evidence would allow it to proceed?

Generic plan: The CPP may not reflect site risk. No welfare detail: Basic legal and worker needs may be missed. No GB Schedule 3 / NI Schedule 4 consideration: High-risk work may be underplanned. Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Eliminate: Redesign service route to avoid cutting where feasible. Substitute: Use prefabricated or lower-dust method after compatibility check. Engineering: Matched dust capture and a physical occupied-area boundary. Administrative: Permit, access schedule, briefing and inspection. PPE: Task RPE for residual exposure, not substitute for source capture. Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged.

Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision? Keep one card or the full set for social sharing, team briefings and learning. Each PDF contains one card per page. Read the full topic for explanations, questions and source links.

A meaningful small-job plan names the work and responsible people, the actual site hazards and controls, access, welfare, emergency arrangements and how change will be managed. A meaningful small-job plan names the work and responsible people, the actual site hazards and controls, access, welfare, emergency arrangements and how change will be managed. It should be short enough to use and specific enough to guide the first day. Every construction project needs a suitable construction phase plan before construction begins. Apply it: Which part of this plan would you check at the workface before authorising the task? Use the evidence to improve the actual work arrangement. Every construction project needs a suitable construction phase plan before construction begins.

Make it proportionate to the work, with site rules, management arrangements and specific GB Schedule 3 / NI Schedule 4 risk measures. CPP, PCI review and project risk register. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Fictional example: a practical application of the existing topic lesson. Assess and plan: Uses tender and pre-construction information to prepare project-specific CPPs. Evidence / response: CPP, PCI review and project risk register. Implement: Turns CPP into site rules, inductions, RAMS, permits and inspections. Evidence / response: Induction records, site plan and permit pack. Apply it: At which point would you hold this example, and what evidence would allow it to proceed?

Connect the task, the route to the person and the control that can fail. Generic plan: The CPP may not reflect site risk. No welfare detail: Basic legal and worker needs may be missed. No GB Schedule 3 / NI Schedule 4 consideration: High-risk work may be underplanned. Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Start with the stronger practicable options and verify their effect. Eliminate: Redesign service route to avoid cutting where feasible. Substitute: Use prefabricated or lower-dust method after compatibility check. Engineering: Matched dust capture and a physical occupied-area boundary. Administrative: Permit, access schedule, briefing and inspection. PPE: Task RPE for residual exposure, not substitute for source capture.

Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged. Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Follow the official sources below and retain the task-specific evidence. Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision? Simplified learning guide.

Use the full topic and the actual work arrangements; existing technical-review and approval statuses still apply. Workplace scenarios labelled fictional are illustrative examples. Check one plan action at the workface: for example, can the promised welfare be used and does the public exclusion route match the occupied building? If a second trade, intrusive work or a changed access route is introduced, revisit coordination, role decisions and briefings before that scope starts. Use CDM and the appointment guide for those separate decisions rather than duplicating them inside the plan. Illustrative example. A fictional single-contractor domestic repair expands into a more intrusive package involving another trade. Decision. The project lead revises the live arrangements and checks the client and principal-role decisions before the changed work.

Evidence to check. Current scope, site information, welfare and access checks, role decisions and workers’ understanding of revised controls. Hold or escalation point. Do not start changed work using a plan that describes only the original repair. Follow-up. Verify at the workface that the new exclusion and welfare arrangements work, then retain the revision reason. Read with: HSE planning for construction work · HSE principal contractor duties · HSE CIS80 construction phase plan.

Make the plan match today’s workface
Make the plan match today’s workface

Source: construction-phase-plan--practical-construction-phase-plan

A useful small-job plan connects people, sequence, controls, welfare and emergency access to the actual site. Update it when conditions change. Name who controls the work and describe the activity sequence and interfaces with occupied areas. Show welfare, emergency access, public boundaries and the particular controls needed for the job. Brief those doing the work, check the site matches the plan and revise it after relevant change. A plan extract is not a service survey, temporary-works design or excavation release. Further guidance: HSE: construction.

What are the key points about construction phase plans?

Source: construction-phase-plan--key-points

The key points are that the CPP is required before work starts, must be proportionate, must be project-specific and must be used as a live control document.

What is a construction phase plan?

Source: construction-phase-plan--what-is-it

A construction phase plan is the written project plan for managing health, safety and welfare during construction work. The CPP sits between pre-construction planning and work as done on site. It should take the project information, design decisions, known hazards, site constraints and programme, then explain how the construction phase will be organised and controlled. Its value is practical: it gives the project team a common operating framework before people, plant and materials arrive on site. A good CPP is specific to the project. It identifies who is in charge, how contractors will cooperate, what site rules apply, what welfare is provided, how emergencies will be managed, which high-risk activities need special arrangements and how the principal contractor or contractor will monitor the work.

The plan should be detailed enough to manage foreseeable risks but simple enough for the project team to use. A long generic document can fail because people cannot find the controls that matter. A short plan can be suitable for simple work if it genuinely covers the risks and arrangements.

When is a construction phase plan required?

Source: construction-phase-plan--when-required

Prepare it before construction starts for every construction project; notification thresholds and principal-contractor appointment are separate tests. The HSE planning page states that a plan is required for a GB project whether one or several contractors are involved. The contractor prepares it on a single-contractor project; the principal contractor prepares it on a project with more than one contractor. HSENI’s CDM 2016 page sets out the NI route and also requires a plan for all projects. A project can need a plan without meeting the separate regulator-notification threshold. The plan must exist before work, not be completed after mobilisation.

Who is responsible for the construction phase plan?

Source: construction-phase-plan--dutyholders

Responsibility depends on the project structure, but the principal contractor or contractor must prepare the plan before construction begins. The client must make suitable arrangements for managing the project and ensure that the principal contractor or contractor has enough time and resources to plan the work safely. The principal designer provides relevant information from the pre-construction phase, including design risks and information needed for the construction phase. The principal contractor leads planning, management, monitoring and coordination during the construction phase where more than one contractor is involved. They must prepare, implement, review and revise the CPP. Contractors must cooperate, follow the plan, provide information about their work and manage the health and safety of their own workers.

How can the ISO 45001 hierarchy of controls guide risk controls in a construction phase plan?

Source: construction-phase-plan--contents

State how the project will be managed and how its actual high-risk work will be controlled, rather than filing generic policies. Use project scope, site layout, named dutyholders, site rules, access, welfare, emergency and first aid arrangements, consultation, coordination and change control. For GB Schedule 3 / NI Schedule 4 work, identify the specific risk and controls. On a refurbishment beside occupied offices, locate the dust boundary, lifting route, isolation, fire compartmentation and public interface, with owners and hold points. Link to detailed methods and permits without dumping every document into the plan. HSE L153 supports a proportionate approach. ERICPD is a planning crossmap. Its prompts do not add a sixth rung or rank Isolate above engineering. Discipline verifies and sustains every control level.

The hierarchy of controls in ISO 45001:2018 comes under Clause 8.1.2 (Eliminating hazards and reducing OH&S risks), which is located within Clause 8 ("Operation"). ESEAP: Elimination, Substitution, Engineering controls, Administrative controls and PPE. Control order: HSE hierarchy of controls and IOSH hierarchy of control guidance. HSE’s five-level hierarchy sets out elimination, substitution, engineering, administrative controls and PPE for GB. ERICPD is complementary. Choose measures for the actual task and location, and verify physical control performance separately from briefing or permit completion. For the occupied-office cut, HSE capture guidance informs the matched equipment checks. Before authorising cutting, the site manager verifies capture, airflow and the physical boundary against the actual material and layout. Maintain the system and check before each phase and during work.

Failed capture or boundary integrity holds cutting; restore and verify performance before recorded restart. A permit or briefing does not establish physical control performance.

How should GB Schedule 3 / NI Schedule 4 high-risk work be addressed?

Source: construction-phase-plan--schedule-3

GB Schedule 3 / NI Schedule 4 work should be identified in the CPP with specific measures rather than buried in generic risk assessments. GB CDM 2015 Schedule 3 and NI CDM 2016 Schedule 4 identify work involving particular risks. See the NI statutory rule for the local list. These are not the only risks that matter, but they are a strong prompt for the CPP because they often need extra planning, competence, supervision, permits, design input or specialist control. The plan should explain how these risks will be managed for the actual project.

How does pre-construction information feed into the CPP?

Source: construction-phase-plan--pre-construction

Pre-construction information should give the principal contractor or contractor the information needed to plan the construction phase safely. The CPP should not be written in isolation. It should be shaped by information from the client, principal designer, designers, surveys, investigations, existing building information, asbestos records, service drawings, ground information, structural constraints, occupancy, public interfaces and environmental conditions. Weak CPPs often fail because the plan does not absorb design and site information. For example, a refurbishment CPP that ignores asbestos records, hidden services, occupied-building constraints or fragile rooflights will not manage the real project risk.

How should the CPP be kept live?
How should the CPP be kept live?

Source: construction-phase-plan--live-document

The CPP should be reviewed and revised whenever the work, people, sequence, risks or controls change. A construction site changes constantly. New subcontractors arrive, workfaces open and close, temporary works are installed, weather changes, materials are delivered, access routes move and design queries arise. A CPP that is not reviewed becomes less reliable as the project progresses. Keeping the plan live does not mean rewriting it every day. It means having a clear process for updates, version control, briefing changes and checking that revised arrangements are actually used. Changes should flow into inductions, toolbox talks, RAMS, permits, site rules, drawings and inspection checks.

What should a small-project construction phase plan include?

Source: construction-phase-plan--small-projects

A small-project CPP should be simple, proportionate and focused on the real risks of the job. Small projects still need a plan, but they do not need a large corporate manual. A good small-project CPP may be a concise document that sets out the job, who is responsible, site rules, welfare, emergency arrangements, key hazards, controls, workers involved and how changes will be handled. The danger with small jobs is informality. Short duration does not remove the need to control asbestos, work at height, electricity, dust, manual handling, welfare, public protection or fire. The plan should help the contractor think before work starts.

How do GB and NI routes differ?

Source: construction-phase-plan--devolved

The plan requirement is shared in purpose but GB CDM 2015 and NI CDM 2016 are separate instruments and regulators. In GB, HSE principal-contractor guidance assigns the plan to the principal contractor on multi-contractor work and to the contractor on a single-contractor project. In NI, HSENI CDM 2016 gives corresponding local roles. The relevant client appoints principal dutyholders when there is more than one contractor; domestic-client arrangements need the local guidance checked. Notification to HSE or HSENI is a distinct threshold and does not excuse a missing plan.

How does the CPP link to building safety and the health and safety file?

Source: construction-phase-plan--building-safety

The CPP should control construction-phase risk while also helping capture information needed for future maintenance, use and alteration. The CPP is primarily about health and safety during construction, but it should connect to the information flow for the completed asset. Design changes, temporary works decisions, concealed services, fire-stopping, structural changes, access arrangements and residual hazards may need to be captured for the health and safety file or wider building information requirements. For applicable higher-risk building work in England, the CPP should not be treated as the only compliance document. It should sit alongside building regulation, fire safety, quality assurance and golden-thread information arrangements so construction decisions are controlled and recorded properly. The construction phase plan is required for every project.

GB L153 distinguishes the health and safety file, required for projects involving more than one contractor, from the plan. NI has its separate CDM 2016 instrument and local file/plan duties. For applicable higher-risk building work in England, BSR golden-thread guidance describes client, principal designer and principal contractor information arrangements. Do not apply that England regime as a UK-wide rule. Capture relevant as-built information through controlled updates and handover.

What evidence shows a CPP is working?

Source: construction-phase-plan--evidence

Evidence should show that the CPP is understood, implemented, checked and updated during the project. A CPP that sits in a file is not evidence of control. Useful evidence includes inductions, site-rule briefings, supervisor inspections, contractor coordination meetings, permit records, welfare checks, emergency drills, action close-out, design change briefings, worker consultation and revision history. Field evidence matters. If the CPP says pedestrians are segregated but the site layout shows workers crossing plant routes, the plan is not working. If it says welfare is available but washing facilities are missing, the plan is not working. If it says high-risk work is controlled by permits but permits are copied or missing, the plan is not working.

Which legal duties and thresholds matter?

Source: construction-phase-plan--legal

Plan duty, principal appointments and project notification are distinct decisions; apply the work-location instrument. GB CDM 2015 requires a suitable construction phase plan before the construction phase begins; the HSE planning page explains roles. The NI CDM 2016 statutory rule governs NI. The plan should set out site rules and specific measures for GB Schedule 3 / NI Schedule 4 work, as set out in the linked NI statutory rule. A domestic or small job still needs a proportionate plan; a complex project needs more depth. Check notification and appointment facts separately, and review the plan whenever sequence, contractor interfaces or hazards change.

How could BuildOut Ltd manage construction phase plans?

Source: construction-phase-plan--business-example

BuildOut Ltd would manage CPPs as live project control documents linked to tender planning, site setup, contractor coordination, inspections and project review. A fictional construction and refurbishment contractor delivering fit-out, maintenance, civils, small demolition, plant operations, subcontracted specialist work and multi-site projects. BuildOut creates a CPP before work starts for each project. For a simple single-contractor job, the plan is concise and covers site rules, welfare, emergency arrangements and key task controls. For multi-contractor refurbishment, the plan includes dutyholder appointments, pre-construction information, asbestos and services information, traffic routes, public protection, fire arrangements, temporary works, permits, contractor coordination and inspection frequency. The site manager uses the CPP during induction, daily briefings and subcontractor coordination.

High-risk work such as hot works, lifting, demolition, excavation, electrical isolation, work at height and confined spaces is controlled through RAMS, permits, competent supervisors and field checks. The CPP revision log is updated when design changes, new contractors arrive or the site layout changes. BuildOut's regional manager audits CPP quality by sampling whether the plan matches the site. They check welfare, traffic segregation, emergency routes, work-at-height controls, dust controls, contractor briefings, permit quality and action close-out. Lessons from incidents and near misses are fed back into future CPP templates and supervisor training.

What should each role learn and demonstrate?

Source: construction-phase-plan--training

Learning must match the decisions people make, from recognising danger to checking that controls work. Briefings should tell people how to act, but attendance alone does not show competence. Assess the real decision or task, record who assessed it and revisit after a material change, failed control or incident. A local authorisation is task-specific; no universal external certificate is implied.

How can a management system sustain effective decisions?
How can a management system sustain effective decisions?

Source: construction-phase-plan--management-system

Give each hazard or support route an owner, a control, a check and a response to failure. Keep plan, site controls, worker feedback, inspections and changes connected. Audit actual boundaries and hold points rather than document completion alone. An owner should sample actual work and corrective actions, not accept a policy or certificate as evidence that the controls work. The free GB regulator guide HSE Managing for health and safety (HSG65) explains a plan–do–check–act approach: assign controls and owners, involve workers, check work as done, and correct failures. For Northern Ireland, use HSENI risk assessment guidance for the local duty. A certificate alone does not demonstrate that a control works.

What warning signs show a construction phase plan is weak?

Source: construction-phase-plan--warning-signs

Warning signs include generic wording, missing site rules, poor welfare, absent GB Schedule 3 / NI Schedule 4 controls, unmanaged contractors and a plan that is not updated when the site changes. A weak CPP usually looks either too thin or too bloated. A plan that says little about the real project will not guide the work. A huge generic file may hide the important controls. The practical test is whether a supervisor, worker or contractor can use the plan to understand how the site is controlled today.

Documents to download

Source: construction-phase-plan--editable-documents

Download editable resources from the SHAREhub environment. Checklists, forms and spreadsheets are blank; procedures contain a complete example to adapt.

Construction project risk register

: Blank register. Record construction point risks, existing controls, further actions and verification, with an illustrative scoring guide. Corrective action tracker: Blank tracker. Track owners, due dates, completion evidence and verification, with overdue alerts and a completion guide.

Corrective action management procedure

: Completed example procedure. A complete example workflow for assigning actions, reviewing progress, escalating delays and verifying effective closure.

Source tables and records 1
CDM role-based action routes

Table ID: appointed-relevent-parties-cdm-role-routes

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Role

Commercial client or project sponsor

Act before or during work

Define scope, time and resources; make required written principal appointments and provide pre-construction information.

Evidence and hold point

Appointment record, information issue and project gates; hold a start with missing roles.

Row 2

Role

Domestic client

Act before or during work

Ask who is in control; client duties normally pass to the sole or principal contractor, or principal designer by written agreement.

Evidence and hold point

Record the actual lead and give property information; do not assume a householder performs professional CDM duties.

Row 3

Role

Principal designer and designers

Act before or during work

Eliminate or reduce foreseeable risks through design and coordinate design information.

Evidence and hold point

Design risk decisions and file inputs; stop unclear design or unsafe change.

Row 4

Role

Principal contractor and contractors

Act before or during work

Prepare or follow the plan, coordinate trades, welfare, induction, site access and worker consultation.

Evidence and hold point

Plan, briefings and site checks; hold work at uncontrolled interfaces.

Row 5

Role

Workers and supervisors

Act before or during work

Follow site rules, cooperate, report danger and raise changed conditions.

Evidence and hold point

Briefing and stop/report route; do not improvise through missing information.

Row 6

Role

Procurement, safety and audit roles

Act before or during work

Check proportionate capability, role scope, information flow and actual implementation.

Evidence and hold point

Project-specific assessment and verified closure, not certificate collection alone.

Read the complete comparison table
CDM role-based action routes
RowRoleAct before or during workEvidence and hold point
1Commercial client or project sponsorDefine scope, time and resources; make required written principal appointments and provide pre-construction information.Appointment record, information issue and project gates; hold a start with missing roles.
2Domestic clientAsk who is in control; client duties normally pass to the sole or principal contractor, or principal designer by written agreement.Record the actual lead and give property information; do not assume a householder performs professional CDM duties.
3Principal designer and designersEliminate or reduce foreseeable risks through design and coordinate design information.Design risk decisions and file inputs; stop unclear design or unsafe change.
4Principal contractor and contractorsPrepare or follow the plan, coordinate trades, welfare, induction, site access and worker consultation.Plan, briefings and site checks; hold work at uncontrolled interfaces.
5Workers and supervisorsFollow site rules, cooperate, report danger and raise changed conditions.Briefing and stop/report route; do not improvise through missing information.
6Procurement, safety and audit rolesCheck proportionate capability, role scope, information flow and actual implementation.Project-specific assessment and verified closure, not certificate collection alone.
Project route and required actions

Table ID: appointed-relevent-parties-cdm-decision-route

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Situation

One contractor expected

Appointment and document route

No principal designer or principal contractor appointment solely for this project; sole contractor prepares a construction phase plan before work.

Do not confuse with

Notification may still apply if its separate threshold is reached.

Row 2

Situation

More than one contractor expected or reasonably foreseeable

Appointment and document route

Commercial client appoints both principal roles in writing as soon as practicable and before construction; principal contractor plans the phase and the health and safety file is prepared. For domestic clients, use the regulation 7 defaults below.

Do not confuse with

Trades need not overlap on site.

Row 3

Situation

Domestic project

Appointment and document route

On a multi-contractor domestic job, client duties normally pass to the principal contractor or contractor in control, unless the principal designer accepts them by written agreement. If the householder makes no principal appointments, regulation 7 places principal-designer duties on the designer in control and principal-contractor duties on the contractor in control.

Do not confuse with

Do not call a business landlord a domestic client.

Row 4

Situation

Notification threshold reached

Appointment and document route

For a commercial project the client notifies HSE via F10 in GB or HSENI via NI10 in NI. On a domestic project, regulation 7 transfers the regulation 6 notification duty to the sole contractor, principal contractor or principal designer under a written client-duty agreement. Keep appointment and notification tests separate.

Do not confuse with

Notification is not permission to start and is not the appointment trigger.

Read the complete comparison table
Project route and required actions
RowSituationAppointment and document routeDo not confuse with
1One contractor expectedNo principal designer or principal contractor appointment solely for this project; sole contractor prepares a construction phase plan before work.Notification may still apply if its separate threshold is reached.
2More than one contractor expected or reasonably foreseeableCommercial client appoints both principal roles in writing as soon as practicable and before construction; principal contractor plans the phase and the health and safety file is prepared. For domestic clients, use the regulation 7 defaults below.Trades need not overlap on site.
3Domestic projectOn a multi-contractor domestic job, client duties normally pass to the principal contractor or contractor in control, unless the principal designer accepts them by written agreement. If the householder makes no principal appointments, regulation 7 places principal-designer duties on the designer in control and principal-contractor duties on the contractor in control.Do not call a business landlord a domestic client.
4Notification threshold reachedFor a commercial project the client notifies HSE via F10 in GB or HSENI via NI10 in NI. On a domestic project, regulation 7 transfers the regulation 6 notification duty to the sole contractor, principal contractor or principal designer under a written client-duty agreement. Keep appointment and notification tests separate.Notification is not permission to start and is not the appointment trigger.
CDM terms used in project decisions

Table ID: appointed-relevent-parties-cdm-terms

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Term

Construction project

Operational meaning

The whole programme of defined construction work, including preparation and any successive trades.

Common error

Counting each purchase order as a separate project without checking the reality.

Row 2

Term

Pre-construction phase

Operational meaning

Design and preparatory period; it can continue after site work begins.

Common error

Ending design coordination at first site mobilisation.

Row 3

Term

Principal designer

Operational meaning

Designer with control over pre-construction phase on a multi-contractor project.

Common error

Assuming a job title or course certificate automatically creates the role.

Row 4

Term

Principal contractor

Operational meaning

Contractor in control of construction phase on a multi-contractor project.

Common error

Assuming the largest trade is appointed without writing or control.

Row 5

Term

Construction phase plan

Operational meaning

Written, proportionate plan for every construction project before that phase begins.

Common error

Treating a generic RAMS bundle as the project coordination plan.

Row 6

Term

Health and safety file

Operational meaning

Future-work information produced for a multi-contractor project and handed to the client.

Common error

Confusing it with the daily site log or every product manual.

Read the complete comparison table
CDM terms used in project decisions
RowTermOperational meaningCommon error
1Construction projectThe whole programme of defined construction work, including preparation and any successive trades.Counting each purchase order as a separate project without checking the reality.
2Pre-construction phaseDesign and preparatory period; it can continue after site work begins.Ending design coordination at first site mobilisation.
3Principal designerDesigner with control over pre-construction phase on a multi-contractor project.Assuming a job title or course certificate automatically creates the role.
4Principal contractorContractor in control of construction phase on a multi-contractor project.Assuming the largest trade is appointed without writing or control.
5Construction phase planWritten, proportionate plan for every construction project before that phase begins.Treating a generic RAMS bundle as the project coordination plan.
6Health and safety fileFuture-work information produced for a multi-contractor project and handed to the client.Confusing it with the daily site log or every product manual.
Appointment timing and evidence

Table ID: appointed-relevent-parties-cdm-timing

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Gate

Project concept and scope

Client action

Forecast all design and construction parties and interfaces.

Record

Scope, location and contractor forecast.

Row 2

Gate

Before design decisions harden

Client action

Appoint principal designer where multi-contractor work is foreseeable.

Record

Written role, authority, design scope and acceptance.

Row 3

Gate

Before construction phase

Client action

Appoint principal contractor early enough to plan and produce the construction phase plan.

Record

Written role, start date, capability and plan review.

Row 4

Gate

During change

Client action

Check role continuity, new trades, design changes and information transfer.

Record

Updated appointments, plan, design and file actions.

Read the complete comparison table
Appointment timing and evidence
RowGateClient actionRecord
1Project concept and scopeForecast all design and construction parties and interfaces.Scope, location and contractor forecast.
2Before design decisions hardenAppoint principal designer where multi-contractor work is foreseeable.Written role, authority, design scope and acceptance.
3Before construction phaseAppoint principal contractor early enough to plan and produce the construction phase plan.Written role, start date, capability and plan review.
4During changeCheck role continuity, new trades, design changes and information transfer.Updated appointments, plan, design and file actions.
Duties across the project

Table ID: appointed-relevent-parties-cdm-dutyholders

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Dutyholder

Commercial client

Primary decision

Arrange project, resources, information, welfare and required appointments; check principal roles are carried out.

Evidence of performance

Project brief, information register and review gates.

Row 2

Dutyholder

Domestic client

Primary decision

Client duties normally transfer under the regulations; choose capable people and provide known property information.

Evidence of performance

Actual controlling contractor/designer identified.

Row 3

Dutyholder

Principal designer

Primary decision

Plan, manage, monitor and coordinate the pre-construction phase; work with designers and principal contractor.

Evidence of performance

Risk decisions, coordinated information and file.

Row 4

Dutyholder

Principal contractor

Primary decision

Plan, manage, monitor and coordinate construction; plan, welfare, induction, access and worker engagement.

Evidence of performance

Current plan, site controls, coordination and consultation.

Row 5

Dutyholder

Designer

Primary decision

Eliminate, reduce or control foreseeable construction, use and maintenance risk; share residual information.

Evidence of performance

Design revisions and significant residual risk notes.

Row 6

Dutyholder

Contractor

Primary decision

Plan, manage and monitor own work; cooperate and coordinate with project team.

Evidence of performance

Task arrangements, supervision and interface briefings.

Row 7

Dutyholder

Worker

Primary decision

Cooperate, take care and report dangers; be consulted about work affecting them.

Evidence of performance

Induction, voice and report response.

Read the complete comparison table
Duties across the project
RowDutyholderPrimary decisionEvidence of performance
1Commercial clientArrange project, resources, information, welfare and required appointments; check principal roles are carried out.Project brief, information register and review gates.
2Domestic clientClient duties normally transfer under the regulations; choose capable people and provide known property information.Actual controlling contractor/designer identified.
3Principal designerPlan, manage, monitor and coordinate the pre-construction phase; work with designers and principal contractor.Risk decisions, coordinated information and file.
4Principal contractorPlan, manage, monitor and coordinate construction; plan, welfare, induction, access and worker engagement.Current plan, site controls, coordination and consultation.
5DesignerEliminate, reduce or control foreseeable construction, use and maintenance risk; share residual information.Design revisions and significant residual risk notes.
6ContractorPlan, manage and monitor own work; cooperate and coordinate with project team.Task arrangements, supervision and interface briefings.
7WorkerCooperate, take care and report dangers; be consulted about work affecting them.Induction, voice and report response.
Project-specific appointment check

Table ID: appointed-relevent-parties-cdm-capability

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Test

Role and control

Question

Is the principal designer a designer controlling pre-construction work; is the principal contractor a contractor controlling site work?

Useful evidence

Role map and delegated authority.

Row 2

Test

Skills, knowledge and experience

Question

Can named people address this project type and its foreseeable risks?

Useful evidence

Relevant previous work and team plan.

Row 3

Test

Organisational capability

Question

Can the organisation resource and coordinate the role across the project duration?

Useful evidence

People, supervision, programme and escalation route.

Row 4

Test

Interfaces

Question

Can both principals share changes and address design/works interfaces?

Useful evidence

Meeting and information handover method.

Row 5

Test

Written terms

Question

Are scope, date, authority and dutyholder acceptance clear?

Useful evidence

Signed appointment and change control.

Read the complete comparison table
Project-specific appointment check
RowTestQuestionUseful evidence
1Role and controlIs the principal designer a designer controlling pre-construction work; is the principal contractor a contractor controlling site work?Role map and delegated authority.
2Skills, knowledge and experienceCan named people address this project type and its foreseeable risks?Relevant previous work and team plan.
3Organisational capabilityCan the organisation resource and coordinate the role across the project duration?People, supervision, programme and escalation route.
4InterfacesCan both principals share changes and address design/works interfaces?Meeting and information handover method.
5Written termsAre scope, date, authority and dutyholder acceptance clear?Signed appointment and change control.
Principal designer and principal contractor interface

Table ID: appointed-relevent-parties-cdm-interface

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Moment

Concept and preparation

Principal designer lead

Coordinate designers, significant risks and information gaps.

Principal contractor lead

Contribute buildability, sequencing and resources if appointed.

Row 2

Moment

Before mobilisation

Principal designer lead

Pass relevant design and site information promptly.

Principal contractor lead

Prepare plan, welfare, induction, access and contractor coordination.

Row 3

Moment

Construction design change

Principal designer lead

Coordinate design risk and residual information while appointed.

Principal contractor lead

Hold affected work, revise plan and brief contractors.

Row 4

Moment

Principal designer leaves early

Principal designer lead

Hand health and safety file and outstanding design issues to principal contractor.

Principal contractor lead

Maintain and update file and construction controls.

Row 5

Moment

Completion

Principal designer lead

Provide current file to client if still appointed.

Principal contractor lead

Provide as-built and residual information for file and hand-back.

Read the complete comparison table
Principal designer and principal contractor interface
RowMomentPrincipal designer leadPrincipal contractor lead
1Concept and preparationCoordinate designers, significant risks and information gaps.Contribute buildability, sequencing and resources if appointed.
2Before mobilisationPass relevant design and site information promptly.Prepare plan, welfare, induction, access and contractor coordination.
3Construction design changeCoordinate design risk and residual information while appointed.Hold affected work, revise plan and brief contractors.
4Principal designer leaves earlyHand health and safety file and outstanding design issues to principal contractor.Maintain and update file and construction controls.
5CompletionProvide current file to client if still appointed.Provide as-built and residual information for file and hand-back.
Core CDM information and handover

Table ID: appointed-relevent-parties-cdm-documents

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Information

Pre-construction information

Owner and timing

Client provides relevant information as soon as practicable; principal designer helps assemble and share it.

Practical quality test

Includes known site, services, existing structure and hazards; gaps are named.

Row 2

Information

Construction phase plan

Owner and timing

Principal contractor on multi-contractor project, sole contractor otherwise; before construction begins.

Practical quality test

Current arrangements, site rules and project-specific high-risk work.

Row 3

Information

Health and safety file

Owner and timing

Principal designer prepares on multi-contractor project; principal contractor maintains it if PD leaves; client receives and retains it.

Practical quality test

Only useful future-work information, updated for actual build and accessible on later work.

Row 4

Information

Regulator notification

Owner and timing

If threshold met, commercial client submits GB F10 or NI NI10. For a domestic client, regulation 7 passes notification to the sole contractor, principal contractor or principal designer under a written client-duty agreement.

Practical quality test

Calculation, submission and update; separate from appointment and plan.

Read the complete comparison table
Core CDM information and handover
RowInformationOwner and timingPractical quality test
1Pre-construction informationClient provides relevant information as soon as practicable; principal designer helps assemble and share it.Includes known site, services, existing structure and hazards; gaps are named.
2Construction phase planPrincipal contractor on multi-contractor project, sole contractor otherwise; before construction begins.Current arrangements, site rules and project-specific high-risk work.
3Health and safety filePrincipal designer prepares on multi-contractor project; principal contractor maintains it if PD leaves; client receives and retains it.Only useful future-work information, updated for actual build and accessible on later work.
4Regulator notificationIf threshold met, commercial client submits GB F10 or NI NI10. For a domestic client, regulation 7 passes notification to the sole contractor, principal contractor or principal designer under a written client-duty agreement.Calculation, submission and update; separate from appointment and plan.
CDM project stage gates

Table ID: appointed-relevent-parties-cdm-stage-gates

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Stage

Before procurement

Check and action

Define construction scope, location, client, expected trades and site information.

Hold or escalation

Unclear project or contractor forecast: obtain project and legal advice.

Row 2

Stage

Before design freeze

Check and action

Appoint PD if needed; coordinate design risks and residual information.

Hold or escalation

No capable lead or critical unknown: hold decision.

Row 3

Stage

Before site start

Check and action

Appoint PC if needed; verify plan, welfare, access and arrangements.

Hold or escalation

No plan or uncontrolled public interface: do not start.

Row 4

Stage

During construction

Check and action

Coordinate trades, consult workers, update design and plan after change.

Hold or escalation

Unknown services, unstable structure or missing design approval: stop affected work.

Row 5

Stage

At completion

Check and action

Verify safe hand-back and client receipt of required health and safety file.

Hold or escalation

Unresolved critical defect or missing future-work information: retain an agreed hold.

Read the complete comparison table
CDM project stage gates
RowStageCheck and actionHold or escalation
1Before procurementDefine construction scope, location, client, expected trades and site information.Unclear project or contractor forecast: obtain project and legal advice.
2Before design freezeAppoint PD if needed; coordinate design risks and residual information.No capable lead or critical unknown: hold decision.
3Before site startAppoint PC if needed; verify plan, welfare, access and arrangements.No plan or uncontrolled public interface: do not start.
4During constructionCoordinate trades, consult workers, update design and plan after change.Unknown services, unstable structure or missing design approval: stop affected work.
5At completionVerify safe hand-back and client receipt of required health and safety file.Unresolved critical defect or missing future-work information: retain an agreed hold.
Source comparison

Table ID: appointed-relevent-parties-cdm-ericpd-visual-controls

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Column 1

Eliminate

Column 2

Design plant maintenance so roof-edge access is avoided.

Column 3

Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients

Row 2

Column 1

Reduce

Column 2

Assess ground-level or protected-location servicing.

Column 3

Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients

Row 3

Column 1

Isolate

Column 2

Provide suitable permanent edge protection and safe access.

Column 3

Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients

Row 4

Column 1

Control

Column 2

Coordinate the construction plan, permit and briefing.

Column 3

Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients

Row 5

Column 1

PPE

Column 2

Use assessed residual fall protection with a rescue route.

Column 3

Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients

Row 6

Column 1

Discipline

Column 2

Verify appointments, installed protection and changes before access.

Column 3

Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients

Read the complete comparison table
Source comparison
RowColumn 1Column 2Column 3
1EliminateDesign plant maintenance so roof-edge access is avoided.Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
2ReduceAssess ground-level or protected-location servicing.Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
3IsolateProvide suitable permanent edge protection and safe access.Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
4ControlCoordinate the construction plan, permit and briefing.Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
5PPEUse assessed residual fall protection with a rescue route.Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
6DisciplineVerify appointments, installed protection and changes before access.Read the full task example, checks and stop points on this page. HSE F10 construction notification · HSENI new construction project notification · HSE domestic clients
GB and NI CDM legal routes

Table ID: appointed-relevent-parties-cdm-jurisdiction

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Decision

Binding regulation

Great britain

Construction (Design and Management) Regulations 2015.

Northern ireland

Construction (Design and Management) Regulations (NI) 2016. GB source NI source

Row 2

Decision

Written principal appointments

Great britain

Regulation 5: client, multi-contractor trigger, as soon as practicable and before construction.

Northern ireland

Regulation 5: same trigger and written timing requirement in NI instrument. GB source NI source

Row 3

Decision

Notification

Great britain

Regulation 6, HSE F10 if threshold met; commercial client notifies, with domestic regulation 7 transfer.

Northern ireland

Regulation 6, HSENI NI10 if threshold met; commercial client notifies, with domestic regulation 7 transfer. GB source NI source

Row 4

Decision

Domestic client route

Great britain

Regulation 7 transfer/default roles.

Northern ireland

Regulation 7 transfer/default roles under NI law. GB source NI source

Row 5

Decision

Project documents

Great britain

Pre-construction information, plan and multi-contractor file under relevant provisions.

Northern ireland

Corresponding duties in NI 2016; verify NI schedules. GB source NI source

Read the complete comparison table
GB and NI CDM legal routes
RowDecisionGreat britainNorthern ireland
1Binding regulationConstruction (Design and Management) Regulations 2015.Construction (Design and Management) Regulations (NI) 2016. GB source NI source
2Written principal appointmentsRegulation 5: client, multi-contractor trigger, as soon as practicable and before construction.Regulation 5: same trigger and written timing requirement in NI instrument. GB source NI source
3NotificationRegulation 6, HSE F10 if threshold met; commercial client notifies, with domestic regulation 7 transfer.Regulation 6, HSENI NI10 if threshold met; commercial client notifies, with domestic regulation 7 transfer. GB source NI source
4Domestic client routeRegulation 7 transfer/default roles.Regulation 7 transfer/default roles under NI law. GB source NI source
5Project documentsPre-construction information, plan and multi-contractor file under relevant provisions.Corresponding duties in NI 2016; verify NI schedules. GB source NI source
CDM governance risk register examples

Table ID: appointed-relevent-parties-cdm-risk-register

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Risk

Principal role appointed late

Control

Forecast trades early and require written appointment before construction.

Evidence and trigger

Gate approval and dated role acceptance.

Row 2

Risk

Unknown existing structure or services

Control

Collect and share relevant information; survey or redesign before intrusive work.

Evidence and trigger

Information register; hold after discovery.

Row 3

Risk

Design and site sequence conflict

Control

PD and PC coordinate changes and hold affected work.

Evidence and trigger

Design issue, revised plan and briefing.

Row 4

Risk

Welfare or access missing

Control

Verify facilities and segregation before mobilisation.

Evidence and trigger

Site setup check and action closeout.

Row 5

Risk

Health and safety file incomplete

Control

Assign inputs early and review at milestones.

Evidence and trigger

File index, as-built inputs and client receipt.

Read the complete comparison table
CDM governance risk register examples
RowRiskControlEvidence and trigger
1Principal role appointed lateForecast trades early and require written appointment before construction.Gate approval and dated role acceptance.
2Unknown existing structure or servicesCollect and share relevant information; survey or redesign before intrusive work.Information register; hold after discovery.
3Design and site sequence conflictPD and PC coordinate changes and hold affected work.Design issue, revised plan and briefing.
4Welfare or access missingVerify facilities and segregation before mobilisation.Site setup check and action closeout.
5Health and safety file incompleteAssign inputs early and review at milestones.File index, as-built inputs and client receipt.
BuildOut Ltd project gates

Table ID: appointed-relevent-parties-cdm-buildout

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Gate

Scope

Named decision

Client representative confirms construction work, GB or NI site and forecast trades.

Record

Project brief.

Row 2

Gate

Appointment

Named decision

Client names both principals in writing when multi-contractor.

Record

Accepted appointments and capability review.

Row 3

Gate

Safe start

Named decision

Principal contractor confirms current plan, welfare, access and site coordination.

Record

Start authority and plan version.

Row 4

Gate

Change

Named decision

Principal designer and contractor resolve design and method changes.

Record

Hold, revision and briefings.

Row 5

Gate

Hand-back

Named decision

Client receives safe site and required file.

Record

Completion and file receipt.

Read the complete comparison table
BuildOut Ltd project gates
RowGateNamed decisionRecord
1ScopeClient representative confirms construction work, GB or NI site and forecast trades.Project brief.
2AppointmentClient names both principals in writing when multi-contractor.Accepted appointments and capability review.
3Safe startPrincipal contractor confirms current plan, welfare, access and site coordination.Start authority and plan version.
4ChangePrincipal designer and contractor resolve design and method changes.Hold, revision and briefings.
5Hand-backClient receives safe site and required file.Completion and file receipt.
Role practice, observed competence and reassessment

Table ID: appointed-relevent-parties-cdm-training-evidence

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Role and learning

Clients: commission the right roles

Practice on the actual task

Decide project scope, contractor count, written appointments and suitable arrangements before work.

Competence evidence and record

Project case and documented competent appointment decision.

Assessor and reassessment trigger

Client lead rechecks after scope or team change.

Row 2

Role and learning

Principal designers: coordinate design risk

Practice on the actual task

Practise collecting pre-construction information and resolving significant design interfaces.

Competence evidence and record

Reviewed design-risk record and handover to principal contractor.

Assessor and reassessment trigger

Competent client checks after design or appointment change.

Row 3

Role and learning

Principal contractors: coordinate construction

Practice on the actual task

Practise phase planning, inductions, welfare, contractor interface and hand-back.

Competence evidence and record

Observed site review, plan and closed action record.

Assessor and reassessment trigger

Client checks after phase, contractor or incident change.

Row 4

Role and learning

Designers and contractors: deliver own duties

Practice on the actual task

Identify foreseeable risks, share information and follow the actual phase plan.

Competence evidence and record

Task/plan exercise and demonstrated interface communication.

Assessor and reassessment trigger

Principal dutyholder checks after design or method change.

Row 5

Role and learning

Workers and supervisors: use and report

Practice on the actual task

Demonstrate induction, welfare check, safe task method and concern escalation.

Competence evidence and record

Observed work and reported/closed defect.

Assessor and reassessment trigger

Site supervisor checks after new phase or control failure.

Read the complete comparison table
Role practice, observed competence and reassessment
RowRole and learningPractice on the actual taskCompetence evidence and recordAssessor and reassessment trigger
1Clients: commission the right rolesDecide project scope, contractor count, written appointments and suitable arrangements before work.Project case and documented competent appointment decision.Client lead rechecks after scope or team change.
2Principal designers: coordinate design riskPractise collecting pre-construction information and resolving significant design interfaces.Reviewed design-risk record and handover to principal contractor.Competent client checks after design or appointment change.
3Principal contractors: coordinate constructionPractise phase planning, inductions, welfare, contractor interface and hand-back.Observed site review, plan and closed action record.Client checks after phase, contractor or incident change.
4Designers and contractors: deliver own dutiesIdentify foreseeable risks, share information and follow the actual phase plan.Task/plan exercise and demonstrated interface communication.Principal dutyholder checks after design or method change.
5Workers and supervisors: use and reportDemonstrate induction, welfare check, safe task method and concern escalation.Observed work and reported/closed defect.Site supervisor checks after new phase or control failure.
Related SHARE Knowledge Hub pages

Table ID: appointed-relevent-parties-cdm-related-share-knowledge-hub-pages

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Related page

CDM

Why it is useful

Wider overview of CDM duties and construction project management.

Row 2

Related page

Construction phase plan

Why it is useful

Explains the plan needed before construction work starts.

Row 3

Related page

Contractor safety

Why it is useful

Useful for contractor selection, monitoring and competence evidence.

Row 4

Related page

Health, welfare and work environment

Why it is useful

Supports welfare and workplace condition duties on construction projects.

Row 5

Related page

Working at height

Why it is useful

Common construction hazard that should be designed and planned under CDM.

Row 6

Related page

Construction dust

Why it is useful

Common construction health risk that relies on design, planning and contractor control.

Read the complete comparison table
Related SHARE Knowledge Hub pages
RowRelated pageWhy it is useful
1CDMWider overview of CDM duties and construction project management.
2Construction phase planExplains the plan needed before construction work starts.
3Contractor safetyUseful for contractor selection, monitoring and competence evidence.
4Health, welfare and work environmentSupports welfare and workplace condition duties on construction projects.
5Working at heightCommon construction hazard that should be designed and planned under CDM.
6Construction dustCommon construction health risk that relies on design, planning and contractor control.
Source tables and records 2
CDM appointment source register

Table ID: appointed-relevent-parties-cdm-official-source-register

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Authority

UK legislation

Linked source

Construction (Design and Management) Regulations 2015 (2015, as amended)

Jurisdiction

Great Britain

Claim supported

Binding GB client, appointment and project duties. Not Northern Ireland law.

Row 2

Authority

UK legislation

Linked source

Construction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended)

Jurisdiction

Northern Ireland

Claim supported

Binding NI client, appointment and project duties. Use NI schedules and NI10, not GB F10.

Row 3

Authority

HSE

Linked source

HSE CDM 2015 legal summary

Jurisdiction

Great Britain

Claim supported

Confirms GB extent and structure. HSE page is not the NI legal instrument.

Row 4

Authority

HSE

Linked source

HSE CDM dutyholder summary

Jurisdiction

Great Britain

Claim supported

Commercial and domestic clients, designers, principal roles, contractors and workers. Read with the legislation and project facts.

Row 5

Authority

HSE

Linked source

HSE commercial clients

Jurisdiction

Great Britain

Claim supported

Client arrangements, appointments, information, welfare and oversight. An adviser does not automatically take over the client duty.

Row 6

Authority

HSE

Linked source

HSE domestic clients

Jurisdiction

Great Britain

Claim supported

Domestic-client transfer of duties and written agreement option. A business landlord is a commercial client.

Row 7

Authority

HSE

Linked source

HSE principal designers

Jurisdiction

Great Britain

Claim supported

Pre-construction coordination and file duties. Principal designer must be a designer with control of that phase.

Row 8

Authority

HSE

Linked source

HSE principal contractors

Jurisdiction

Great Britain

Claim supported

Construction phase coordination, plan, welfare and worker engagement. Principal contractor role is not the same as every subcontractor.

Row 9

Authority

HSE

Linked source

HSE designers

Jurisdiction

Great Britain

Claim supported

Eliminate, reduce and communicate foreseeable design risks. Design duty can apply to people who specify or alter work, not only architects.

Row 10

Authority

HSE

Linked source

HSE contractors

Jurisdiction

Great Britain

Claim supported

Plan, manage and monitor own work and coordinate with others. Sole contractor prepares the construction phase plan.

Row 11

Authority

HSE

Linked source

HSE construction workers

Jurisdiction

Great Britain

Claim supported

Worker cooperation, reporting and consultation. Worker duties do not remove employer or contractor duties.

Row 12

Authority

HSE

Linked source

HSE planning for construction work

Jurisdiction

Great Britain

Claim supported

Early principal-contractor appointment and construction phase plan. Plan is required for every project, not only notifiable ones.

Row 13

Authority

HSE

Linked source

HSE F10 construction notification

Jurisdiction

Great Britain

Claim supported

GB notification route and sole-contractor form caveat. Notification threshold does not trigger principal appointments.

Row 14

Authority

HSE

Linked source

HSE CDM frequently asked questions

Jurisdiction

Great Britain

Claim supported

Threshold, project scope and multiple dutyholder roles. Check project facts rather than using project value as a trigger.

Row 15

Authority

HSE

Linked source

HSE construction welfare overview

Jurisdiction

Great Britain

Claim supported

Welfare planning and Schedule 2 GB route. Do not rely on old CIS59 CDM 2007 duties.

Row 16

Authority

HSE

Linked source

HSE L153 Managing health and safety in construction

Jurisdiction

Great Britain guidance

Claim supported

Detailed HSE guidance on CDM 2015 and document handover. Guidance on Regulations, not an Approved Code of Practice.

Row 17

Authority

HSENI

Linked source

HSENI CDM 2016 overview

Jurisdiction

Northern Ireland

Claim supported

NI role, all-project and multi-contractor duties. Use alongside NI 2016 Regulations.

Row 18

Authority

HSENI

Linked source

HSENI new construction project notification

Jurisdiction

Northern Ireland

Claim supported

NI notification route. NI10 is distinct from the GB F10 form.

Row 19

Authority

HSE

Linked source

HSE INDG368 Using contractors (2012 revision)

Jurisdiction

Great Britain general guidance

Claim supported

Proportionate contractor selection and coordination. Predates CDM 2015; not authority for CDM role allocation.

Row 20

Authority

HSE

Linked source

HSE HSG150 Health and safety in construction (Third edition 2006)

Jurisdiction

Great Britain practical guidance

Claim supported

Historical task-risk and site-control context. Predates CDM 2015; do not use for current appointment law.

Row 21

Authority

HSE

Linked source

HSE CIS59 construction welfare facilities (CDM 2007-era leaflet)

Jurisdiction

Great Britain historical guidance

Claim supported

Practical welfare planning context. Legal references to CDM 2007 are superseded.

Read the complete comparison table
CDM appointment source register
RowAuthorityLinked sourceJurisdictionClaim supported
1UK legislationConstruction (Design and Management) Regulations 2015 (2015, as amended)Great BritainBinding GB client, appointment and project duties. Not Northern Ireland law.
2UK legislationConstruction (Design and Management) Regulations (Northern Ireland) 2016 (2016, as amended)Northern IrelandBinding NI client, appointment and project duties. Use NI schedules and NI10, not GB F10.
3HSEHSE CDM 2015 legal summaryGreat BritainConfirms GB extent and structure. HSE page is not the NI legal instrument.
4HSEHSE CDM dutyholder summaryGreat BritainCommercial and domestic clients, designers, principal roles, contractors and workers. Read with the legislation and project facts.
5HSEHSE commercial clientsGreat BritainClient arrangements, appointments, information, welfare and oversight. An adviser does not automatically take over the client duty.
6HSEHSE domestic clientsGreat BritainDomestic-client transfer of duties and written agreement option. A business landlord is a commercial client.
7HSEHSE principal designersGreat BritainPre-construction coordination and file duties. Principal designer must be a designer with control of that phase.
8HSEHSE principal contractorsGreat BritainConstruction phase coordination, plan, welfare and worker engagement. Principal contractor role is not the same as every subcontractor.
9HSEHSE designersGreat BritainEliminate, reduce and communicate foreseeable design risks. Design duty can apply to people who specify or alter work, not only architects.
10HSEHSE contractorsGreat BritainPlan, manage and monitor own work and coordinate with others. Sole contractor prepares the construction phase plan.
11HSEHSE construction workersGreat BritainWorker cooperation, reporting and consultation. Worker duties do not remove employer or contractor duties.
12HSEHSE planning for construction workGreat BritainEarly principal-contractor appointment and construction phase plan. Plan is required for every project, not only notifiable ones.
13HSEHSE F10 construction notificationGreat BritainGB notification route and sole-contractor form caveat. Notification threshold does not trigger principal appointments.
14HSEHSE CDM frequently asked questionsGreat BritainThreshold, project scope and multiple dutyholder roles. Check project facts rather than using project value as a trigger.
15HSEHSE construction welfare overviewGreat BritainWelfare planning and Schedule 2 GB route. Do not rely on old CIS59 CDM 2007 duties.
16HSEHSE L153 Managing health and safety in constructionGreat Britain guidanceDetailed HSE guidance on CDM 2015 and document handover. Guidance on Regulations, not an Approved Code of Practice.
17HSENIHSENI CDM 2016 overviewNorthern IrelandNI role, all-project and multi-contractor duties. Use alongside NI 2016 Regulations.
18HSENIHSENI new construction project notificationNorthern IrelandNI notification route. NI10 is distinct from the GB F10 form.
19HSEHSE INDG368 Using contractors (2012 revision)Great Britain general guidanceProportionate contractor selection and coordination. Predates CDM 2015; not authority for CDM role allocation.
20HSEHSE HSG150 Health and safety in construction (Third edition 2006)Great Britain practical guidanceHistorical task-risk and site-control context. Predates CDM 2015; do not use for current appointment law.
21HSEHSE CIS59 construction welfare facilities (CDM 2007-era leaflet)Great Britain historical guidancePractical welfare planning context. Legal references to CDM 2007 are superseded.
CDM appointment acronyms

Table ID: appointed-relevent-parties-cdm-acronyms

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Term

CDM

Meaning and boundary

Construction (Design and Management); GB 2015 and NI 2016 are separate regulations.

Row 2

Term

PD / PC

Meaning and boundary

Principal designer / principal contractor, required on multi-contractor projects.

Row 3

Term

PCI

Meaning and boundary

Pre-construction information relevant to the project and shared early.

Row 4

Term

CPP

Meaning and boundary

Construction phase plan, required before construction for every project.

Row 5

Term

F10 / NI10

Meaning and boundary

GB HSE / NI HSENI notification routes when size test is met.

Row 6

Term

RAMS

Meaning and boundary

Risk assessments and method statements; useful task documents, not a substitute for CPP or principal appointment.

Read the complete comparison table
CDM appointment acronyms
RowTermMeaning and boundary
1CDMConstruction (Design and Management); GB 2015 and NI 2016 are separate regulations.
2PD / PCPrincipal designer / principal contractor, required on multi-contractor projects.
3PCIPre-construction information relevant to the project and shared early.
4CPPConstruction phase plan, required before construction for every project.
5F10 / NI10GB HSE / NI HSENI notification routes when size test is met.
6RAMSRisk assessments and method statements; useful task documents, not a substitute for CPP or principal appointment.
Suggested CDM project records

Table ID: appointed-relevent-parties-cdm-tools

Source: https://www.sharehub.ltd/knowledge-hub/appointed-relevent-parties-cdm.html

Row 1

Record

Contractor forecast and role map

Use

Determine whether principal roles are required, including later trades.

Owner and boundary

Client; review on change.

Row 2

Record

Written appointment and capability check

Use

Define role, authority, scope, timing and project-specific suitability.

Owner and boundary

Client; not a generic certificate collection.

Row 3

Record

PCI and design issue register

Use

Share known site, existing structure and unresolved risks.

Owner and boundary

Client and PD; keep current.

Row 4

Record

CPP and coordination log

Use

Manage site rules, high-risk work, welfare and interfaces.

Owner and boundary

PC or sole contractor; update during work.

Row 5

Record

Health and safety file index

Use

Capture relevant future-work information and client receipt.

Owner and boundary

PD/PC as applicable; multi-contractor project.

Read the complete comparison table
Suggested CDM project records
RowRecordUseOwner and boundary
1Contractor forecast and role mapDetermine whether principal roles are required, including later trades.Client; review on change.
2Written appointment and capability checkDefine role, authority, scope, timing and project-specific suitability.Client; not a generic certificate collection.
3PCI and design issue registerShare known site, existing structure and unresolved risks.Client and PD; keep current.
4CPP and coordination logManage site rules, high-risk work, welfare and interfaces.PC or sole contractor; update during work.
5Health and safety file indexCapture relevant future-work information and client receipt.PD/PC as applicable; multi-contractor project.
CDM in plain English

Table ID: cdm-cdm-in-plain-english

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Area

Lifecycle control

What it means

Manage risk from design through handover.

Practical output

Project CDM plan and review points.

Row 2

Area

Dutyholders

What it means

Named roles with specific responsibilities.

Practical output

Appointments and responsibility matrix.

Row 3

Area

Information flow

What it means

Give the right people the right risk information.

Practical output

Pre-construction information and design risk notes.

Row 4

Area

Planning

What it means

Organise work before it starts.

Practical output

Construction phase plan.

Row 5

Area

Coordination

What it means

Make trades and designers work together safely.

Practical output

Meetings, interfaces and site rules.

Row 6

Area

Legacy information

What it means

Help future work be safer.

Practical output

Health and safety file.

Read the complete comparison table
CDM in plain English
RowAreaWhat it meansPractical output
1Lifecycle controlManage risk from design through handover.Project CDM plan and review points.
2DutyholdersNamed roles with specific responsibilities.Appointments and responsibility matrix.
3Information flowGive the right people the right risk information.Pre-construction information and design risk notes.
4PlanningOrganise work before it starts.Construction phase plan.
5CoordinationMake trades and designers work together safely.Meetings, interfaces and site rules.
6Legacy informationHelp future work be safer.Health and safety file.
CDM scope examples

Table ID: cdm-cdm-scope-examples

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Work type

New build

Likely cdm relevance

Clearly construction work.

Planning focus

Appointments, design risk, CPP and welfare.

Row 2

Work type

Refurbishment

Likely cdm relevance

Usually construction work.

Planning focus

Asbestos, services, access, fire and segregation.

Row 3

Work type

Maintenance on a structure

Likely cdm relevance

Can be construction work depending on activity.

Planning focus

Task risk and existing hazards.

Row 4

Work type

Demolition or dismantling

Likely cdm relevance

Construction work with high-risk sequencing.

Planning focus

Method, exclusion zones and temporary works.

Row 5

Work type

Service installation

Likely cdm relevance

Included where fixed to a structure.

Planning focus

Isolation, coordination and commissioning.

Row 6

Work type

High-pressure cleaning or abrasive cleaning

Likely cdm relevance

Can be included in CDM where it meets the definition.

Planning focus

Exposure, access and containment.

Read the complete comparison table
CDM scope examples
RowWork typeLikely cdm relevancePlanning focus
1New buildClearly construction work.Appointments, design risk, CPP and welfare.
2RefurbishmentUsually construction work.Asbestos, services, access, fire and segregation.
3Maintenance on a structureCan be construction work depending on activity.Task risk and existing hazards.
4Demolition or dismantlingConstruction work with high-risk sequencing.Method, exclusion zones and temporary works.
5Service installationIncluded where fixed to a structure.Isolation, coordination and commissioning.
6High-pressure cleaning or abrasive cleaningCan be included in CDM where it meets the definition.Exposure, access and containment.
Prevention principles in CDM practice

Table ID: cdm-prevention-principles-in-cdm-practice

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Principle

Avoid risks

Cdm application

Remove hazards through design or method.

Example

Prefabricate at ground level.

Row 2

Principle

Evaluate unavoidable risks

Cdm application

Assess remaining risks before work starts.

Example

Temporary works and services assessment.

Row 3

Principle

Combat risks at source

Cdm application

Control the source rather than the worker.

Example

Fixed edge protection, not harness-only reliance.

Row 4

Principle

Adapt work to people

Cdm application

Design access, handling and maintenance around human capability.

Example

Plant with safe access and clearances.

Row 5

Principle

Replace dangerous with less dangerous

Cdm application

Choose safer materials or methods.

Example

Low-dust cutting method.

Row 6

Principle

Prioritise collective measures

Cdm application

Protect everyone before relying on PPE.

Example

Guardrails before fall arrest.

Row 7

Principle

Give instructions

Cdm application

Communicate residual significant risks clearly.

Example

Design risk notes and briefings.

Read the complete comparison table
Prevention principles in CDM practice
RowPrincipleCdm applicationExample
1Avoid risksRemove hazards through design or method.Prefabricate at ground level.
2Evaluate unavoidable risksAssess remaining risks before work starts.Temporary works and services assessment.
3Combat risks at sourceControl the source rather than the worker.Fixed edge protection, not harness-only reliance.
4Adapt work to peopleDesign access, handling and maintenance around human capability.Plant with safe access and clearances.
5Replace dangerous with less dangerousChoose safer materials or methods.Low-dust cutting method.
6Prioritise collective measuresProtect everyone before relying on PPE.Guardrails before fall arrest.
7Give instructionsCommunicate residual significant risks clearly.Design risk notes and briefings.
CDM dutyholder summary

Table ID: cdm-cdm-dutyholder-summary

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Dutyholder

Client

Main role

Make suitable arrangements, appoint dutyholders and provide information.

Evidence

Client brief, appointments and PCI.

Row 2

Dutyholder

Designer

Main role

Eliminate, reduce or control foreseeable risks through design.

Evidence

Design risk register and information.

Row 3

Dutyholder

Principal designer

Main role

Coordinate pre-construction health and safety.

Evidence

Design coordination and H&S file development.

Row 4

Dutyholder

Principal contractor

Main role

Coordinate the construction phase.

Evidence

CPP, site rules, inductions and coordination.

Row 5

Dutyholder

Contractor

Main role

Plan, manage and monitor their work.

Evidence

RAMS, briefings and supervision.

Row 6

Dutyholder

Worker

Main role

Cooperate, follow site rules and report danger.

Evidence

Induction and consultation.

Read the complete comparison table
CDM dutyholder summary
RowDutyholderMain roleEvidence
1ClientMake suitable arrangements, appoint dutyholders and provide information.Client brief, appointments and PCI.
2DesignerEliminate, reduce or control foreseeable risks through design.Design risk register and information.
3Principal designerCoordinate pre-construction health and safety.Design coordination and H&S file development.
4Principal contractorCoordinate the construction phase.CPP, site rules, inductions and coordination.
5ContractorPlan, manage and monitor their work.RAMS, briefings and supervision.
6WorkerCooperate, follow site rules and report danger.Induction and consultation.
Key CDM documents

Table ID: cdm-key-cdm-documents

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Document

Pre-construction information

Purpose

Tell designers and contractors about relevant hazards and constraints.

Quality test

Would it help price and plan the job safely?

Row 2

Document

Construction phase plan

Purpose

Explain how construction health and safety will be managed.

Quality test

Is it specific to the project and updated?

Row 3

Document

F10 notification

Purpose

Notify the enforcing authority where thresholds are met.

Quality test

Is it submitted and updated when details change?

Row 4

Document

Health and safety file

Purpose

Provide information needed for future maintenance or work.

Quality test

Would a future contractor find it useful?

Row 5

Document

Design risk register

Purpose

Track significant design risks and decisions.

Quality test

Does it show eliminated and residual risks?

Row 6

Document

Site rules and logistics plan

Purpose

Control behaviour, access, traffic, welfare and emergencies.

Quality test

Are workers briefed and supervisors checking?

Read the complete comparison table
Key CDM documents
RowDocumentPurposeQuality test
1Pre-construction informationTell designers and contractors about relevant hazards and constraints.Would it help price and plan the job safely?
2Construction phase planExplain how construction health and safety will be managed.Is it specific to the project and updated?
3F10 notificationNotify the enforcing authority where thresholds are met.Is it submitted and updated when details change?
4Health and safety fileProvide information needed for future maintenance or work.Would a future contractor find it useful?
5Design risk registerTrack significant design risks and decisions.Does it show eliminated and residual risks?
6Site rules and logistics planControl behaviour, access, traffic, welfare and emergencies.Are workers briefed and supervisors checking?
Notification decision

Table ID: cdm-notification-check

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Column-1

30-working-day/20-worker test

Column-2

More than 30 working days and more than 20 people on site at any time.

Column-3

More than 30 working days and more than 20 workers simultaneously, per NI Regulation 6.

Row 2

Column-1

Person-day test

Column-2

More than 500 person-days.

Column-3

More than 500 person-days.

Row 3

Column-1

Regulator and record

Column-2

HSE F10 or relevant GB enforcing route; client records submission and updates.

Column-3

HSENI NI notification route; client records submission and updates.

Row 4

Column-1

Under threshold

Column-2

CDM duties, appointments and construction phase plan can still apply.

Column-3

CDM duties, appointments and written construction phase plan can still apply.

Read the complete comparison table
Notification decision
RowColumn-1Column-2Column-3
130-working-day/20-worker testMore than 30 working days and more than 20 people on site at any time.More than 30 working days and more than 20 workers simultaneously, per NI Regulation 6.
2Person-day testMore than 500 person-days.More than 500 person-days.
3Regulator and recordHSE F10 or relevant GB enforcing route; client records submission and updates.HSENI NI notification route; client records submission and updates.
4Under thresholdCDM duties, appointments and construction phase plan can still apply.CDM duties, appointments and written construction phase plan can still apply.
Pre-construction outputs

Table ID: cdm-pre-construction-outputs

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Output

Client brief

What it should contain

Project purpose, constraints, standards and key risks.

Owner

Client.

Row 2

Output

Pre-construction information

What it should contain

Existing hazards, surveys, services, asbestos and site information.

Owner

Client with PD support.

Row 3

Output

Design risk register

What it should contain

Significant risks eliminated, reduced or communicated.

Owner

Designers and PD.

Row 4

Output

Appointments

What it should contain

Written PD and PC appointments where required.

Owner

Client.

Row 5

Output

Programme

What it should contain

Time allowed for planning, design and safe construction.

Owner

Client and project team.

Row 6

Output

Competence checks

What it should contain

Skills, knowledge, experience and organisational capability.

Owner

Client and dutyholders.

Read the complete comparison table
Pre-construction outputs
RowOutputWhat it should containOwner
1Client briefProject purpose, constraints, standards and key risks.Client.
2Pre-construction informationExisting hazards, surveys, services, asbestos and site information.Client with PD support.
3Design risk registerSignificant risks eliminated, reduced or communicated.Designers and PD.
4AppointmentsWritten PD and PC appointments where required.Client.
5ProgrammeTime allowed for planning, design and safe construction.Client and project team.
6Competence checksSkills, knowledge, experience and organisational capability.Client and dutyholders.
Construction phase controls

Table ID: cdm-construction-phase-controls

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Control

Construction phase plan

Why it matters

Sets out site-specific arrangements.

Evidence

Current CPP.

Row 2

Control

Induction and briefings

Why it matters

Workers understand site risks and rules.

Evidence

Attendance and briefing records.

Row 3

Control

Contractor coordination

Why it matters

Prevents interface failures.

Evidence

Coordination meetings.

Row 4

Control

Site inspections

Why it matters

Checks controls remain effective.

Evidence

Inspection and action records.

Row 5

Control

Permit systems

Why it matters

Controls high-risk work such as hot work or excavations.

Evidence

Permits and hand-back checks.

Row 6

Control

Change control

Why it matters

Prevents new hazards being missed.

Evidence

Design and method change log.

Read the complete comparison table
Construction phase controls
RowControlWhy it mattersEvidence
1Construction phase planSets out site-specific arrangements.Current CPP.
2Induction and briefingsWorkers understand site risks and rules.Attendance and briefing records.
3Contractor coordinationPrevents interface failures.Coordination meetings.
4Site inspectionsChecks controls remain effective.Inspection and action records.
5Permit systemsControls high-risk work such as hot work or excavations.Permits and hand-back checks.
6Change controlPrevents new hazards being missed.Design and method change log.
Welfare checks

Table ID: cdm-welfare-checks

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Facility

Toilets

Why it matters

Basic hygiene and dignity.

Evidence

Welfare inspection.

Row 2

Facility

Washing

Why it matters

Controls skin and substance exposure.

Evidence

Hot/warm water and supplies.

Row 3

Facility

Drinking water

Why it matters

Hydration and health.

Evidence

Water availability.

Row 4

Facility

Rest area

Why it matters

Breaks, fatigue and shelter.

Evidence

Suitable rest facilities.

Row 5

Facility

Changing/drying

Why it matters

Contaminated or wet clothing management.

Evidence

Changing facilities.

Row 6

Facility

Maintenance

Why it matters

Facilities remain usable.

Evidence

Cleaning and defect records.

Read the complete comparison table
Welfare checks
RowFacilityWhy it mattersEvidence
1ToiletsBasic hygiene and dignity.Welfare inspection.
2WashingControls skin and substance exposure.Hot/warm water and supplies.
3Drinking waterHydration and health.Water availability.
4Rest areaBreaks, fatigue and shelter.Suitable rest facilities.
5Changing/dryingContaminated or wet clothing management.Changing facilities.
6MaintenanceFacilities remain usable.Cleaning and defect records.
Handover information

Table ID: cdm-handover-information

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Information

Residual risks

Why future users need it

Future work needs to know what remains.

Example

Fragile roof area or unusual loading.

Row 2

Information

Maintenance access

Why future users need it

Safe access needs to be planned.

Example

Access routes and anchor details.

Row 3

Information

Asbestos information

Why future users need it

Prevents uncontrolled disturbance.

Example

Survey and register details.

Row 4

Information

Services

Why future users need it

Prevents strikes during future work.

Example

As-built drawings and service routes.

Row 5

Information

Plant and systems

Why future users need it

Supports safe maintenance.

Example

Manuals, isolation and testing details.

Row 6

Information

Lessons learned

Why future users need it

Improves the next project.

Example

Project review and action log.

Read the complete comparison table
Handover information
RowInformationWhy future users need itExample
1Residual risksFuture work needs to know what remains.Fragile roof area or unusual loading.
2Maintenance accessSafe access needs to be planned.Access routes and anchor details.
3Asbestos informationPrevents uncontrolled disturbance.Survey and register details.
4ServicesPrevents strikes during future work.As-built drawings and service routes.
5Plant and systemsSupports safe maintenance.Manuals, isolation and testing details.
6Lessons learnedImproves the next project.Project review and action log.
CDM assurance levels

Table ID: cdm-cdm-assurance-levels

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Level

First line

Who does it

Site manager, supervisor or trade lead.

What they check

Controls, welfare, inductions, permits and safe work.

Row 2

Level

Second line

Who does it

Client representative, principal designer, principal contractor or H&S adviser.

What they check

Appointments, PCI, CPP, coordination and inspections.

Row 3

Level

Third line

Who does it

Independent auditor, consultant or senior client assurance.

What they check

System effectiveness, evidence quality and legal gaps.

Row 4

Level

Close-out

Who does it

Project team and client.

What they check

H&S file, lessons learned and future actions.

Read the complete comparison table
CDM assurance levels
RowLevelWho does itWhat they check
1First lineSite manager, supervisor or trade lead.Controls, welfare, inductions, permits and safe work.
2Second lineClient representative, principal designer, principal contractor or H&S adviser.Appointments, PCI, CPP, coordination and inspections.
3Third lineIndependent auditor, consultant or senior client assurance.System effectiveness, evidence quality and legal gaps.
4Close-outProject team and client.H&S file, lessons learned and future actions.
CDM duties by work location

Table ID: cdm-jurisdiction-map

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Column-1

Main instrument

Column-2

Construction (Design and Management) Regulations 2015.

Column-3

Construction (Design and Management) Regulations (Northern Ireland) 2016.

Row 2

Column-1

Small or single-contractor work

Column-2

CDM still applies; a construction phase plan is required.

Column-3

CDM still applies; HSENI expects a written construction phase health and safety plan.

Row 3

Column-1

Multiple contractors

Column-2

Appoint principal designer and principal contractor; maintain health and safety file.

Column-3

Appoint principal designer and principal contractor; maintain health and safety file.

Row 4

Column-1

Notification

Column-2

HSE/appropriate GB authority via F10 where threshold met.

Column-3

Client notifies HSENI via NI route where threshold met.

Row 5

Column-1

Building-control interface

Column-2

England Building Regulations roles may additionally apply in England.

Column-3

Check NI building-control requirements separately.

Read the complete comparison table
CDM duties by work location
RowColumn-1Column-2Column-3
1Main instrumentConstruction (Design and Management) Regulations 2015.Construction (Design and Management) Regulations (Northern Ireland) 2016.
2Small or single-contractor workCDM still applies; a construction phase plan is required.CDM still applies; HSENI expects a written construction phase health and safety plan.
3Multiple contractorsAppoint principal designer and principal contractor; maintain health and safety file.Appoint principal designer and principal contractor; maintain health and safety file.
4NotificationHSE/appropriate GB authority via F10 where threshold met.Client notifies HSENI via NI route where threshold met.
5Building-control interfaceEngland Building Regulations roles may additionally apply in England.Check NI building-control requirements separately.
BuildOut CDM management approach

Table ID: cdm-buildout-cdm-management-approach

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Activity

Assess

How buildout manages it

Screens project scope, dutyholder role, notification, high-risk work and information needs.

Evidence

CDM project register.

Row 2

Activity

Analyse

How buildout manages it

Reviews design risk, site constraints, services, asbestos, welfare and contractor interfaces.

Evidence

PCI review and risk workshop.

Row 3

Activity

Train

How buildout manages it

Trains project managers, site managers, designers and supervisors on CDM duties.

Evidence

Training matrix and briefings.

Row 4

Activity

Implement

How buildout manages it

Uses appointments, CPP, welfare plan, site rules, permits and contractor coordination.

Evidence

Project file and site records.

Row 5

Activity

Check

How buildout manages it

Uses inspections, document reviews, worker feedback and audits.

Evidence

Assurance dashboard and action tracker.

Row 6

Activity

Learn

How buildout manages it

Reviews incidents, near misses, design changes and project close-out.

Evidence

Lessons learned record.

Row 7

Activity

Improve

How buildout manages it

Updates templates, procurement standards, designer prompts and contractor controls.

Evidence

Management review and revised procedures.

Read the complete comparison table
BuildOut CDM management approach
RowActivityHow buildout manages itEvidence
1AssessScreens project scope, dutyholder role, notification, high-risk work and information needs.CDM project register.
2AnalyseReviews design risk, site constraints, services, asbestos, welfare and contractor interfaces.PCI review and risk workshop.
3TrainTrains project managers, site managers, designers and supervisors on CDM duties.Training matrix and briefings.
4ImplementUses appointments, CPP, welfare plan, site rules, permits and contractor coordination.Project file and site records.
5CheckUses inspections, document reviews, worker feedback and audits.Assurance dashboard and action tracker.
6LearnReviews incidents, near misses, design changes and project close-out.Lessons learned record.
7ImproveUpdates templates, procurement standards, designer prompts and contractor controls.Management review and revised procedures.
Role-level learning and competence evidence

Table ID: cdm-competence-decisions

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Column-1

Client: project brief, resources and appointments.

Column-2

CDM specialist challenges a programme that omits pre-construction information, welfare and an early appointment.

Column-3

Dated brief and appointment record; revisit after scope or team change.

Row 2

Column-1

Designer/principal designer: foreseeable risk and coordination.

Column-2

Competent reviewer traces one design hazard from elimination choice to residual information handed to the builder.

Column-3

Design decision and coordination record; revisit after design change.

Row 3

Column-1

Principal contractor/contractor: construction plan and site controls.

Column-2

Site lead demonstrates sequence, induction, welfare, interfaces, permits and stop response at the actual site.

Column-3

Plan version, site observation and action close-out; revisit after new activity or contractor.

Row 4

Column-1

Worker/supervisor: task briefing and unsafe-condition report.

Column-2

Supervisor checks understanding through a live task walk-through, including who to tell and when to stop.

Column-3

Induction and task observation; refresh after change or incident.

Row 5

Column-1

Project administrator: jurisdiction and threshold.

Column-2

Competent client representative applies GB/NI form, threshold and update route to a forecast exercise.

Column-3

Calculation and submission record; review when workforce or programme changes.

Read the complete comparison table
Role-level learning and competence evidence
RowColumn-1Column-2Column-3
1Client: project brief, resources and appointments.CDM specialist challenges a programme that omits pre-construction information, welfare and an early appointment.Dated brief and appointment record; revisit after scope or team change.
2Designer/principal designer: foreseeable risk and coordination.Competent reviewer traces one design hazard from elimination choice to residual information handed to the builder.Design decision and coordination record; revisit after design change.
3Principal contractor/contractor: construction plan and site controls.Site lead demonstrates sequence, induction, welfare, interfaces, permits and stop response at the actual site.Plan version, site observation and action close-out; revisit after new activity or contractor.
4Worker/supervisor: task briefing and unsafe-condition report.Supervisor checks understanding through a live task walk-through, including who to tell and when to stop.Induction and task observation; refresh after change or incident.
5Project administrator: jurisdiction and threshold.Competent client representative applies GB/NI form, threshold and update route to a forecast exercise.Calculation and submission record; review when workforce or programme changes.
Source tables and records 3
Study application

Table ID: cdm-study-application

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Learning context

IOSH Construction Certificate

What to know

CDM dutyholders, CPP, PCI, welfare, F10 and construction control.

Scenario application

Refurbishment project starts without asbestos information.

Row 2

Learning context

IOSH National General Certificate

What to know

Contractor management and construction risk.

Scenario application

Client appoints contractor without checking arrangements.

Row 3

Learning context

IOSH Diploma

What to know

Lifecycle risk, assurance and organisational control.

Scenario application

Audit of design-risk management across projects.

Row 4

Learning context

Professional CPD

What to know

Practical CDM governance and evidence.

Scenario application

Project close-out shows poor H&S file quality.

Read the complete comparison table
Study application
RowLearning contextWhat to knowScenario application
1IOSH Construction CertificateCDM dutyholders, CPP, PCI, welfare, F10 and construction control.Refurbishment project starts without asbestos information.
2IOSH National General CertificateContractor management and construction risk.Client appoints contractor without checking arrangements.
3IOSH DiplomaLifecycle risk, assurance and organisational control.Audit of design-risk management across projects.
4Professional CPDPractical CDM governance and evidence.Project close-out shows poor H&S file quality.
Warning signs and consequences

Table ID: cdm-warning-signs-and-consequences

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Warning sign

Late appointments

How harm can develop

Design and planning risk is missed.

Improvement action

Appoint dutyholders early and in writing.

Row 2

Warning sign

Generic CPP

How harm can develop

Real site risks are not controlled.

Improvement action

Rewrite around actual work.

Row 3

Warning sign

Missing PCI

How harm can develop

Asbestos, services or structural hazards are discovered late.

Improvement action

Collect and review information before work.

Row 4

Warning sign

Poor welfare

How harm can develop

Health, hygiene and morale suffer.

Improvement action

Provide facilities before start.

Row 5

Warning sign

Weak coordination

How harm can develop

Trades interfere with each other.

Improvement action

Improve sequencing and meetings.

Row 6

Warning sign

No H&S file

How harm can develop

Future work is less safe.

Improvement action

Plan file ownership and close-out.

Read the complete comparison table
Warning signs and consequences
RowWarning signHow harm can developImprovement action
1Late appointmentsDesign and planning risk is missed.Appoint dutyholders early and in writing.
2Generic CPPReal site risks are not controlled.Rewrite around actual work.
3Missing PCIAsbestos, services or structural hazards are discovered late.Collect and review information before work.
4Poor welfareHealth, hygiene and morale suffer.Provide facilities before start.
5Weak coordinationTrades interfere with each other.Improve sequencing and meetings.
6No H&S fileFuture work is less safe.Plan file ownership and close-out.
Official links and their use

Table ID: cdm-official-links

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Column-1

HSE CDM 2015

Column-2

Great Britain regulator

Column-3

GB statutory framework and roles

Row 2

Column-1

HSE CDM FAQ

Column-2

Great Britain regulator

Column-3

Threshold, domestic duties, appointments and notification

Row 3

Column-1

HSE dutyholder responsibilities

Column-2

Great Britain regulator

Column-3

Client, designer and contractor decision points

Row 4

Column-1

HSE designers

Column-2

Great Britain regulator

Column-3

Design risk and residual information

Row 5

Column-1

HSE construction phase plan

Column-2

Great Britain regulator

Column-3

Plan required for construction phase, including small projects

Row 6

Column-1

HSE F10

Column-2

Great Britain notification route

Column-3

GB notifiable projects

Row 7

Column-1

CDM 2015 legal text

Column-2

Great Britain legislation

Column-3

Exact GB regulations including notification and appointments

Row 8

Column-1

HSENI CDM (NI) 2016

Column-2

Northern Ireland regulator

Column-3

NI duties and notification thresholds

Row 9

Column-1

CDM (NI) 2016 legal text

Column-2

Northern Ireland legislation

Column-3

Exact NI Regulation 6 working-day test and domestic-client route

Row 10

Column-1

HSENI NI10 construction notification

Column-2

Northern Ireland regulator; non-accessible form

Column-3

NI notification route; use accessible HSENI support if needed

Row 11

Column-1

GOV.UK building work requirements

Column-2

England building-control guidance

Column-3

Separate Building Regulations dutyholders

Row 12

Column-1

HSE Managing for health and safety (HSG65)

Column-2

HSE management guidance for Great Britain; check current edition

Column-3

Management-system scope only

Read the complete comparison table
Official links and their use
RowColumn-1Column-2Column-3
1HSE CDM 2015Great Britain regulatorGB statutory framework and roles
2HSE CDM FAQGreat Britain regulatorThreshold, domestic duties, appointments and notification
3HSE dutyholder responsibilitiesGreat Britain regulatorClient, designer and contractor decision points
4HSE designersGreat Britain regulatorDesign risk and residual information
5HSE construction phase planGreat Britain regulatorPlan required for construction phase, including small projects
6HSE F10Great Britain notification routeGB notifiable projects
7CDM 2015 legal textGreat Britain legislationExact GB regulations including notification and appointments
8HSENI CDM (NI) 2016Northern Ireland regulatorNI duties and notification thresholds
9CDM (NI) 2016 legal textNorthern Ireland legislationExact NI Regulation 6 working-day test and domestic-client route
10HSENI NI10 construction notificationNorthern Ireland regulator; non-accessible formNI notification route; use accessible HSENI support if needed
11GOV.UK building work requirementsEngland building-control guidanceSeparate Building Regulations dutyholders
12HSE Managing for health and safety (HSG65)HSE management guidance for Great Britain; check current editionManagement-system scope only
Acronyms and terms

Table ID: cdm-acronyms-and-terms

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Acronym or term

CDM

Meaning

Construction Design and Management

Why it matters

Main construction health and safety framework.

Row 2

Acronym or term

PCI

Meaning

Pre-Construction Information

Why it matters

Key information for planning and designing safely.

Row 3

Acronym or term

CPP

Meaning

Construction Phase Plan

Why it matters

Plan for managing construction health and safety.

Row 4

Acronym or term

PD

Meaning

Principal Designer

Why it matters

Coordinates pre-construction health and safety on multi-contractor projects.

Row 5

Acronym or term

PC

Meaning

Principal Contractor

Why it matters

Coordinates the construction phase on multi-contractor projects.

Row 6

Acronym or term

F10

Meaning

Notification of Construction Project

Why it matters

Online notification route for notifiable projects in Great Britain.

Row 7

Acronym or term

H&S file

Meaning

Health and Safety File

Why it matters

Handover file for future safe work.

Row 8

Acronym or term

RAMS

Meaning

Risk Assessment and Method Statement

Why it matters

Contractor task planning documents.

Row 9

Acronym or term

SKE

Meaning

Skills, Knowledge and Experience

Why it matters

Competence concept for dutyholder capability.

Read the complete comparison table
Acronyms and terms
RowAcronym or termMeaningWhy it matters
1CDMConstruction Design and ManagementMain construction health and safety framework.
2PCIPre-Construction InformationKey information for planning and designing safely.
3CPPConstruction Phase PlanPlan for managing construction health and safety.
4PDPrincipal DesignerCoordinates pre-construction health and safety on multi-contractor projects.
5PCPrincipal ContractorCoordinates the construction phase on multi-contractor projects.
6F10Notification of Construction ProjectOnline notification route for notifiable projects in Great Britain.
7H&S fileHealth and Safety FileHandover file for future safe work.
8RAMSRisk Assessment and Method StatementContractor task planning documents.
9SKESkills, Knowledge and ExperienceCompetence concept for dutyholder capability.
Individual editable BuildOut documents

Table ID: cdm-buildout-documents

Source: https://www.sharehub.ltd/knowledge-hub/cdm.html

Row 1

Document

CDM project mobilisation and coordination procedureBOUK-PRO-CDM · Completed fictional example · v1.0

Purpose

Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover.

Editable download

Download DOCXRead preview

Row 2

Document

Project CDM applicability and dutyholder checklistBOUK-CHK-CDM-01 · Blank editable master · v1.0

Purpose

Check project definition, client type, contractor count, appointments and notification threshold.

Editable download

Download DOCXRead preview

Row 3

Document

Pre-construction information and gap registerBOUK-REG-CDM-01 · Blank register with separate fictional worked entries · v1.0

Purpose

Track asbestos, services, design, client and existing-structure information gaps.

Editable download

Download XLSXRead preview

Row 4

Document

Construction phase planBOUK-PLN-CDM-01 · Completed fictional example · v1.0

Purpose

Set project health and safety arrangements, site rules and specific high-risk measures before construction starts.

Editable download

Download DOCXRead preview

Row 5

Document

F10 notification decision and submission recordBOUK-FRM-CDM-01 · Blank editable master · v1.0

Purpose

Record threshold assessment, responsible dutyholder and update/submission evidence when required.

Editable download

Download DOCXRead preview

Row 6

Document

Coordination meeting and interface action recordBOUK-FRM-CDM-02 · Blank editable master · v1.0

Purpose

Record trade sequencing, shared risks, access and responsibilities.

Editable download

Download DOCXRead preview

Row 7

Document

Health and safety file and handover checklistBOUK-CHK-CDM-02 · Blank editable master · v1.0

Purpose

Gather proportionate residual-risk information and agree file responsibilities and delivery.

Editable download

Download DOCXRead preview

Row 8

Document

Design review and residual-risk communication procedureBOUK-PRO-DES · Completed fictional example · v1.0

Purpose

Record design decisions, interfaces, change control and safety-critical information.

Editable download

Download DOCXRead preview

Row 9

Document

Design hazard and residual-risk registerBOUK-REG-DES-01 · Blank register with separate fictional worked entries · v1.0

Purpose

Track design elimination/reduction decisions and residual risks requiring communication.

Editable download

Download XLSXRead preview

Row 10

Document

Design risk review and change approval recordBOUK-FRM-DES-01 · Blank editable master · v1.0

Purpose

Review buildability, temporary stability, use and maintenance interfaces.

Editable download

Download DOCXRead preview

Row 11

Document

Designer capability and appointment checklistBOUK-CHK-DES-01 · Blank editable master · v1.0

Purpose

Confirm role, skills, knowledge, experience and organisational capability.

Editable download

Download DOCXRead preview

Row 12

Document

Safety-critical design information transmittalBOUK-FRM-DES-02 · Blank editable master · v1.0

Purpose

Record issue and acknowledgement of significant residual risks.

Editable download

Download DOCXRead preview

Row 13

Document

Building-control and higher-risk-building interface screenBOUK-CHK-DES-02 · Blank editable master · v1.0

Purpose

Determine whether additional building-safety appointments, controls and approvals require specialist review.

Editable download

Download DOCXRead preview

Read the complete comparison table
Individual editable BuildOut documents
RowDocumentPurposeEditable download
1CDM project mobilisation and coordination procedureBOUK-PRO-CDM · Completed fictional example · v1.0Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover.Download DOCXRead preview
2Project CDM applicability and dutyholder checklistBOUK-CHK-CDM-01 · Blank editable master · v1.0Check project definition, client type, contractor count, appointments and notification threshold.Download DOCXRead preview
3Pre-construction information and gap registerBOUK-REG-CDM-01 · Blank register with separate fictional worked entries · v1.0Track asbestos, services, design, client and existing-structure information gaps.Download XLSXRead preview
4Construction phase planBOUK-PLN-CDM-01 · Completed fictional example · v1.0Set project health and safety arrangements, site rules and specific high-risk measures before construction starts.Download DOCXRead preview
5F10 notification decision and submission recordBOUK-FRM-CDM-01 · Blank editable master · v1.0Record threshold assessment, responsible dutyholder and update/submission evidence when required.Download DOCXRead preview
6Coordination meeting and interface action recordBOUK-FRM-CDM-02 · Blank editable master · v1.0Record trade sequencing, shared risks, access and responsibilities.Download DOCXRead preview
7Health and safety file and handover checklistBOUK-CHK-CDM-02 · Blank editable master · v1.0Gather proportionate residual-risk information and agree file responsibilities and delivery.Download DOCXRead preview
8Design review and residual-risk communication procedureBOUK-PRO-DES · Completed fictional example · v1.0Record design decisions, interfaces, change control and safety-critical information.Download DOCXRead preview
9Design hazard and residual-risk registerBOUK-REG-DES-01 · Blank register with separate fictional worked entries · v1.0Track design elimination/reduction decisions and residual risks requiring communication.Download XLSXRead preview
10Design risk review and change approval recordBOUK-FRM-DES-01 · Blank editable master · v1.0Review buildability, temporary stability, use and maintenance interfaces.Download DOCXRead preview
11Designer capability and appointment checklistBOUK-CHK-DES-01 · Blank editable master · v1.0Confirm role, skills, knowledge, experience and organisational capability.Download DOCXRead preview
12Safety-critical design information transmittalBOUK-FRM-DES-02 · Blank editable master · v1.0Record issue and acknowledgement of significant residual risks.Download DOCXRead preview
13Building-control and higher-risk-building interface screenBOUK-CHK-DES-02 · Blank editable master · v1.0Determine whether additional building-safety appointments, controls and approvals require specialist review.Download DOCXRead preview
CPP in plain English

Table ID: construction-phase-plan-cpp-in-plain-english

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Element

Project plan

What it means

Sets out how the construction phase will be managed.

What it should not become

A generic company policy folder.

Row 2

Element

Risk control document

What it means

Explains site-specific hazards and arrangements.

What it should not become

A collection of disconnected RAMS.

Row 3

Element

Communication tool

What it means

Helps workers and contractors understand site rules.

What it should not become

A document no one on site has read.

Row 4

Element

Live document

What it means

Changes when the project changes.

What it should not become

A tender-stage file frozen after day one.

Row 5

Element

Evidence source

What it means

Shows planning, coordination and review.

What it should not become

Paperwork with no field implementation.

Read the complete comparison table
CPP in plain English
RowElementWhat it meansWhat it should not become
1Project planSets out how the construction phase will be managed.A generic company policy folder.
2Risk control documentExplains site-specific hazards and arrangements.A collection of disconnected RAMS.
3Communication toolHelps workers and contractors understand site rules.A document no one on site has read.
4Live documentChanges when the project changes.A tender-stage file frozen after day one.
5Evidence sourceShows planning, coordination and review.Paperwork with no field implementation.
Dutyholder responsibilities

Table ID: construction-phase-plan-dutyholder-responsibilities

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Dutyholder

Client

Cpp role

Ensures suitable arrangements and adequate time/resources.

Evidence

Appointment records, project brief and checks.

Row 2

Dutyholder

Principal designer

Cpp role

Provides pre-construction and design risk information.

Evidence

Design risk information and coordination records.

Row 3

Dutyholder

Principal contractor

Cpp role

Prepares, implements, reviews and revises the CPP.

Evidence

Approved CPP, revisions, site rules and inspections.

Row 4

Dutyholder

Contractor

Cpp role

Prepares CPP on single-contractor projects and follows it on all projects.

Evidence

RAMS, briefings, worker consultation and supervision.

Row 5

Dutyholder

Workers

Cpp role

Follow site rules and report hazards.

Evidence

Induction, briefings and reporting records.

Read the complete comparison table
Dutyholder responsibilities
RowDutyholderCpp roleEvidence
1ClientEnsures suitable arrangements and adequate time/resources.Appointment records, project brief and checks.
2Principal designerProvides pre-construction and design risk information.Design risk information and coordination records.
3Principal contractorPrepares, implements, reviews and revises the CPP.Approved CPP, revisions, site rules and inspections.
4ContractorPrepares CPP on single-contractor projects and follows it on all projects.RAMS, briefings, worker consultation and supervision.
5WorkersFollow site rules and report hazards.Induction, briefings and reporting records.
Planning a concrete cut beside occupied offices

Table ID: construction-phase-plan-hierarchy

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Column-1

Eliminate / eliminate

Column-2

Redesign service route to avoid cutting where feasible.

Column-3

Designer records decision; hold intrusive work pending survey.

Row 2

Column-1

Substitute / reduce

Column-2

Use prefabricated or lower-dust method after compatibility check.

Column-3

Principal contractor approves method and interface; hold cutting if compatibility or dust control fails.

Row 3

Column-1

Engineering / isolate and control

Column-2

Matched dust capture and a physical occupied-area boundary.

Column-3

Site manager tests capture and segregation; stop on escape.

Row 4

Column-1

Administrative / discipline

Column-2

Permit, access schedule, briefing and inspection.

Column-3

Supervisor checks before each phase; pause on failed coordination.

Row 5

Column-1

PPE / PPE

Column-2

Task RPE for residual exposure, not substitute for source capture.

Column-3

Competent lead checks fit; no work if required PPE fails.

Read the complete comparison table
Planning a concrete cut beside occupied offices
RowColumn-1Column-2Column-3
1Eliminate / eliminateRedesign service route to avoid cutting where feasible.Designer records decision; hold intrusive work pending survey.
2Substitute / reduceUse prefabricated or lower-dust method after compatibility check.Principal contractor approves method and interface; hold cutting if compatibility or dust control fails.
3Engineering / isolate and controlMatched dust capture and a physical occupied-area boundary.Site manager tests capture and segregation; stop on escape.
4Administrative / disciplinePermit, access schedule, briefing and inspection.Supervisor checks before each phase; pause on failed coordination.
5PPE / PPETask RPE for residual exposure, not substitute for source capture.Competent lead checks fit; no work if required PPE fails.
Examples of high-risk work to consider

Table ID: construction-phase-plan-examples-of-high-risk-work-to-consider

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Work type

Burial, engulfment or serious falls

Why it matters

Can cause fatal injury quickly.

Cpp response

Excavation support, edge protection, fall prevention and rescue.

Row 2

Work type

Chemical or biological substances

Why it matters

May cause acute or chronic health harm.

Cpp response

COSHH controls, hygiene, RPE and health monitoring where relevant.

Row 3

Work type

Work near high-voltage power lines

Why it matters

Electrical contact can be fatal.

Cpp response

Exclusion zones, isolation, permits and utility liaison.

Row 4

Work type

Risk of drowning

Why it matters

Water work or flood-prone areas need rescue planning.

Cpp response

Water safety plan and emergency arrangements.

Row 5

Work type

Wells, underground earthworks and tunnels

Why it matters

Ground, atmosphere and access risks.

Cpp response

Temporary works, ventilation, permits and rescue.

Row 6

Work type

Heavy prefabricated components

Why it matters

Lifting and stability risks.

Cpp response

Lift plans, temporary stability and exclusion zones.

Read the complete comparison table
Examples of high-risk work to consider
RowWork typeWhy it mattersCpp response
1Burial, engulfment or serious fallsCan cause fatal injury quickly.Excavation support, edge protection, fall prevention and rescue.
2Chemical or biological substancesMay cause acute or chronic health harm.COSHH controls, hygiene, RPE and health monitoring where relevant.
3Work near high-voltage power linesElectrical contact can be fatal.Exclusion zones, isolation, permits and utility liaison.
4Risk of drowningWater work or flood-prone areas need rescue planning.Water safety plan and emergency arrangements.
5Wells, underground earthworks and tunnelsGround, atmosphere and access risks.Temporary works, ventilation, permits and rescue.
6Heavy prefabricated componentsLifting and stability risks.Lift plans, temporary stability and exclusion zones.
Pre-construction information links

Table ID: construction-phase-plan-pre-construction-information-links

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Information

Existing hazards

Why it matters

Asbestos, services, contamination and fragile materials can change the work method.

Cpp use

Controls, surveys and permits.

Row 2

Information

Design risks

Why it matters

Residual risks must be communicated into construction.

Cpp use

Sequencing, temporary works and specialist controls.

Row 3

Information

Site constraints

Why it matters

Access, neighbours, public routes and live operations affect planning.

Cpp use

Traffic, segregation and communication plan.

Row 4

Information

Programme

Why it matters

Sequencing can create or reduce risk.

Cpp use

Phasing, coordination and hold points.

Row 5

Information

Health and safety file needs

Why it matters

Future maintenance information must be collected.

Cpp use

Information capture and handover process.

Read the complete comparison table
Pre-construction information links
RowInformationWhy it mattersCpp use
1Existing hazardsAsbestos, services, contamination and fragile materials can change the work method.Controls, surveys and permits.
2Design risksResidual risks must be communicated into construction.Sequencing, temporary works and specialist controls.
3Site constraintsAccess, neighbours, public routes and live operations affect planning.Traffic, segregation and communication plan.
4ProgrammeSequencing can create or reduce risk.Phasing, coordination and hold points.
5Health and safety file needsFuture maintenance information must be collected.Information capture and handover process.
CPP review triggers

Table ID: construction-phase-plan-cpp-review-triggers

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Trigger

New contractor

Why it matters

New work package and interface risks.

Update action

Review coordination, induction and supervision.

Row 2

Trigger

Design change

Why it matters

May change sequence, temporary works or residual risk.

Update action

Update controls and brief affected teams.

Row 3

Trigger

Incident or near miss

Why it matters

Existing arrangements may be weak.

Update action

Investigate, revise plan and verify actions.

Row 4

Trigger

Programme change

Why it matters

Compression or resequencing can create conflict.

Update action

Review simultaneous operations and resources.

Row 5

Trigger

Site layout change

Why it matters

Access, traffic and emergency routes may change.

Update action

Update site plan and brief.

Row 6

Trigger

New high-risk activity

Why it matters

May need permits, specialist controls or notification.

Update action

Add specific measures and authorisation.

Read the complete comparison table
CPP review triggers
RowTriggerWhy it mattersUpdate action
1New contractorNew work package and interface risks.Review coordination, induction and supervision.
2Design changeMay change sequence, temporary works or residual risk.Update controls and brief affected teams.
3Incident or near missExisting arrangements may be weak.Investigate, revise plan and verify actions.
4Programme changeCompression or resequencing can create conflict.Review simultaneous operations and resources.
5Site layout changeAccess, traffic and emergency routes may change.Update site plan and brief.
6New high-risk activityMay need permits, specialist controls or notification.Add specific measures and authorisation.
Small-project CPP essentials

Table ID: construction-phase-plan-small-project-cpp-essentials

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Element

Project details

Practical content

What is being done, where and by whom.

Example

Bathroom refurbishment in occupied house.

Row 2

Element

Responsible person

Practical content

Who controls work and decisions.

Example

Named contractor or site lead.

Row 3

Element

Site rules

Practical content

Access, housekeeping, tools, PPE, welfare and security.

Example

Keep escape routes clear and isolate services.

Row 4

Element

Key risks

Practical content

Only the significant job-specific risks.

Example

Asbestos, dust, work at height and electrical isolation.

Row 5

Element

Emergency arrangements

Practical content

First aid, fire and contacts.

Example

Local A&E, fire route and client contact.

Row 6

Element

Review

Practical content

What will change the plan.

Example

Unexpected asbestos, service damage or new contractor.

Read the complete comparison table
Small-project CPP essentials
RowElementPractical contentExample
1Project detailsWhat is being done, where and by whom.Bathroom refurbishment in occupied house.
2Responsible personWho controls work and decisions.Named contractor or site lead.
3Site rulesAccess, housekeeping, tools, PPE, welfare and security.Keep escape routes clear and isolate services.
4Key risksOnly the significant job-specific risks.Asbestos, dust, work at height and electrical isolation.
5Emergency arrangementsFirst aid, fire and contacts.Local A&E, fire route and client contact.
6ReviewWhat will change the plan.Unexpected asbestos, service damage or new contractor.
Construction phase plan route

Table ID: construction-phase-plan-jurisdiction

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Column-1

Great Britain

Column-2

CDM 2015, HSE guidance.

Column-3

Contractor or principal contractor prepares before work.

Row 2

Column-1

Northern Ireland

Column-2

CDM (NI) 2016, HSENI guidance.

Column-3

Local contractor or principal contractor prepares before work.

Read the complete comparison table
Construction phase plan route
RowColumn-1Column-2Column-3
1Great BritainCDM 2015, HSE guidance.Contractor or principal contractor prepares before work.
2Northern IrelandCDM (NI) 2016, HSENI guidance.Local contractor or principal contractor prepares before work.
Information handover links

Table ID: construction-phase-plan-information-handover-links

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Information

Residual hazards

Why it matters later

Future workers need to know what remains.

Cpp link

H&S file information capture.

Row 2

Information

Design changes

Why it matters later

As-built condition may differ from original design.

Cpp link

Change control and drawing updates.

Row 3

Information

Fire and structural details

Why it matters later

Future safety depends on accurate installation records.

Cpp link

Inspection and quality hold points.

Row 4

Information

Maintenance access

Why it matters later

Future work must be planned safely.

Cpp link

Access strategy and handover notes.

Row 5

Information

Temporary works learning

Why it matters later

Temporary decisions can affect permanent works.

Cpp link

TWC records and close-out.

Read the complete comparison table
Information handover links
RowInformationWhy it matters laterCpp link
1Residual hazardsFuture workers need to know what remains.H&S file information capture.
2Design changesAs-built condition may differ from original design.Change control and drawing updates.
3Fire and structural detailsFuture safety depends on accurate installation records.Inspection and quality hold points.
4Maintenance accessFuture work must be planned safely.Access strategy and handover notes.
5Temporary works learningTemporary decisions can affect permanent works.TWC records and close-out.
CPP assurance evidence

Table ID: construction-phase-plan-cpp-assurance-evidence

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Evidence

Induction records

What it shows

People received site rules and emergency information.

What to watch for

Generic induction not linked to the project.

Row 2

Evidence

Site inspections

What it shows

Controls are checked in the field.

What to watch for

Repeated findings without close-out.

Row 3

Evidence

Coordination meetings

What it shows

Contractors and workfaces are coordinated.

What to watch for

Minutes with no decisions or actions.

Row 4

Evidence

Permit records

What it shows

High-risk work is authorised and controlled.

What to watch for

Office-issued permits or weak handover.

Row 5

Evidence

Revision log

What it shows

The plan is updated after change.

What to watch for

Old versions still in use.

Row 6

Evidence

Worker feedback

What it shows

People can raise issues and improve controls.

What to watch for

No feedback route or no response.

Read the complete comparison table
CPP assurance evidence
RowEvidenceWhat it showsWhat to watch for
1Induction recordsPeople received site rules and emergency information.Generic induction not linked to the project.
2Site inspectionsControls are checked in the field.Repeated findings without close-out.
3Coordination meetingsContractors and workfaces are coordinated.Minutes with no decisions or actions.
4Permit recordsHigh-risk work is authorised and controlled.Office-issued permits or weak handover.
5Revision logThe plan is updated after change.Old versions still in use.
6Worker feedbackPeople can raise issues and improve controls.No feedback route or no response.
BuildOut Ltd worked example

Table ID: construction-phase-plan-buildout-ltd-worked-example

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Management area

Assess and plan

How buildout applies it

Uses tender and pre-construction information to prepare project-specific CPPs.

Evidence and improvement

CPP, PCI review and project risk register.

Row 2

Management area

Implement

How buildout applies it

Turns CPP into site rules, inductions, RAMS, permits and inspections.

Evidence and improvement

Induction records, site plan and permit pack.

Row 3

Management area

Coordinate contractors

How buildout applies it

Runs start-up meetings and weekly coordination for subcontractors.

Evidence and improvement

Meeting notes, interface register and action tracker.

Row 4

Management area

Check controls

How buildout applies it

Supervisors inspect workfaces and compare conditions with the CPP.

Evidence and improvement

Inspection records and photographs.

Row 5

Management area

Learn and update

How buildout applies it

Revises the CPP after change, incident, new contractor or audit finding.

Evidence and improvement

Revision log and briefing records.

Row 6

Management area

Improve system

How buildout applies it

Reviews recurring CPP weaknesses across projects.

Evidence and improvement

Management review and template updates.

Read the complete comparison table
BuildOut Ltd worked example
RowManagement areaHow buildout applies itEvidence and improvement
1Assess and planUses tender and pre-construction information to prepare project-specific CPPs.CPP, PCI review and project risk register.
2ImplementTurns CPP into site rules, inductions, RAMS, permits and inspections.Induction records, site plan and permit pack.
3Coordinate contractorsRuns start-up meetings and weekly coordination for subcontractors.Meeting notes, interface register and action tracker.
4Check controlsSupervisors inspect workfaces and compare conditions with the CPP.Inspection records and photographs.
5Learn and updateRevises the CPP after change, incident, new contractor or audit finding.Revision log and briefing records.
6Improve systemReviews recurring CPP weaknesses across projects.Management review and template updates.
Role-level learning and competence evidence

Table ID: construction-phase-plan-competence-decisions

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Column-1

Single contractor

Column-2

Prepare a proportionate plan and brief it; construction manager assesses.

Column-3

Dated plan and observation; update after sequence change.

Row 2

Column-1

Principal contractor

Column-2

Coordinate multi-contractor interfaces and GB Schedule 3 / NI Schedule 4 controls; client checks.

Column-3

Plan, consultation and inspection log; review after contractor change.

Row 3

Column-1

Designer

Column-2

Show how a hazard was removed or passed on; principal designer checks.

Column-3

Design decision and residual-risk transfer; revisit after redesign.

Read the complete comparison table
Role-level learning and competence evidence
RowColumn-1Column-2Column-3
1Single contractorPrepare a proportionate plan and brief it; construction manager assesses.Dated plan and observation; update after sequence change.
2Principal contractorCoordinate multi-contractor interfaces and GB Schedule 3 / NI Schedule 4 controls; client checks.Plan, consultation and inspection log; review after contractor change.
3DesignerShow how a hazard was removed or passed on; principal designer checks.Design decision and residual-risk transfer; revisit after redesign.
Warning signs and improvements

Table ID: construction-phase-plan-warning-signs-and-improvements

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Warning sign

Generic plan

What it suggests

The CPP may not reflect site risk.

What to improve

Rewrite around project-specific hazards and controls.

Row 2

Warning sign

No welfare detail

What it suggests

Basic legal and worker needs may be missed.

What to improve

Specify toilets, washing, rest and drinking water.

Row 3

Warning sign

No GB Schedule 3 / NI Schedule 4 consideration

What it suggests

High-risk work may be underplanned.

What to improve

Add specific measures and controls.

Row 4

Warning sign

Unclear dutyholders

What it suggests

Coordination and accountability may fail.

What to improve

Define roles, names and escalation.

Row 5

Warning sign

Old site plan

What it suggests

Routes, storage or emergency arrangements may be wrong.

What to improve

Update drawings and brief changes.

Row 6

Warning sign

No evidence of use

What it suggests

The CPP may be a file, not a control.

What to improve

Link to inductions, inspections and actions.

Read the complete comparison table
Warning signs and improvements
RowWarning signWhat it suggestsWhat to improve
1Generic planThe CPP may not reflect site risk.Rewrite around project-specific hazards and controls.
2No welfare detailBasic legal and worker needs may be missed.Specify toilets, washing, rest and drinking water.
3No GB Schedule 3 / NI Schedule 4 considerationHigh-risk work may be underplanned.Add specific measures and controls.
4Unclear dutyholdersCoordination and accountability may fail.Define roles, names and escalation.
5Old site planRoutes, storage or emergency arrangements may be wrong.Update drawings and brief changes.
6No evidence of useThe CPP may be a file, not a control.Link to inductions, inspections and actions.
Source tables and records 4
Official sources and decisions

Table ID: construction-phase-plan-official-links

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Column-1

HSE, Great Britain

Column-2

HSE planning for construction work

Column-3

Great Britain CDM guidance

Column-4

Who prepares plan and when

Row 2

Column-1

HSE, Great Britain

Column-2

HSE principal contractor duties

Column-3

Great Britain CDM guidance

Column-4

Multi-contractor PC plan, review and worker engagement

Row 3

Column-1

HSE, Great Britain

Column-2

HSE CIS80 construction phase plan

Column-3

Great Britain small-project guidance

Column-4

Proportionate plan for small/domestic projects

Row 4

Column-1

HSE, Great Britain

Column-2

HSE CDM 2015 L153

Column-3

Great Britain guidance on regulations

Column-4

GB CDM roles, Schedule 3 and plan content

Row 5

Column-1

HSENI, Northern Ireland

Column-2

HSENI CDM (NI) 2016 overview

Column-3

Northern Ireland regulator guidance

Column-4

NI plan and dutyholder route

Row 6

Column-1

UK legislation

Column-2

CDM Regulations (NI) 2016, latest available text

Column-3

Northern Ireland statutory rule; check effects

Column-4

NI construction phase duties and Schedule 4 work

Row 7

Column-1

HSE

Column-2

HSE Managing for health and safety (HSG65)

Column-3

Great Britain

Column-4

Free GB regulator guidance on planning, doing, checking and acting on health and safety controls.

Row 8

Column-1

HSE

Column-2

HSE five-level hierarchy

Column-3

Great Britain

Column-4

Higher controls first; ERICPD complementary

Row 9

Column-1

HSE

Column-2

HSE CIS69 on-tool extraction

Column-3

Great Britain

Column-4

Actual-task compatible capture, checks and maintenance

Row 10

Column-1

Building Safety Regulator

Column-2

BSR keeping the golden thread

Column-3

England

Column-4

Applicable higher-risk building work: information and dutyholder arrangements

Read the complete comparison table
Official sources and decisions
RowColumn-1Column-2Column-3Column-4
1HSE, Great BritainHSE planning for construction workGreat Britain CDM guidanceWho prepares plan and when
2HSE, Great BritainHSE principal contractor dutiesGreat Britain CDM guidanceMulti-contractor PC plan, review and worker engagement
3HSE, Great BritainHSE CIS80 construction phase planGreat Britain small-project guidanceProportionate plan for small/domestic projects
4HSE, Great BritainHSE CDM 2015 L153Great Britain guidance on regulationsGB CDM roles, Schedule 3 and plan content
5HSENI, Northern IrelandHSENI CDM (NI) 2016 overviewNorthern Ireland regulator guidanceNI plan and dutyholder route
6UK legislationCDM Regulations (NI) 2016, latest available textNorthern Ireland statutory rule; check effectsNI construction phase duties and Schedule 4 work
7HSEHSE Managing for health and safety (HSG65)Great BritainFree GB regulator guidance on planning, doing, checking and acting on health and safety controls.
8HSEHSE five-level hierarchyGreat BritainHigher controls first; ERICPD complementary
9HSEHSE CIS69 on-tool extractionGreat BritainActual-task compatible capture, checks and maintenance
10Building Safety RegulatorBSR keeping the golden threadEnglandApplicable higher-risk building work: information and dutyholder arrangements
Acronyms and plain-English meanings

Table ID: construction-phase-plan-acronyms-and-plain-english-meanings

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Acronym

CDM

Meaning

Construction (Design and Management)

Why it matters

Main construction health and safety regime.

Row 2

Acronym

CPP

Meaning

Construction phase plan

Why it matters

Plan for managing health, safety and welfare during construction.

Row 3

Acronym

F10

Meaning

HSE construction project notification

Why it matters

Required for notifiable projects meeting CDM thresholds.

Row 4

Acronym

HSE

Meaning

Health and Safety Executive

Why it matters

GB regulator and official guidance source.

Row 5

Acronym

HSENI

Meaning

Health and Safety Executive for Northern Ireland

Why it matters

Northern Ireland regulator and official guidance source.

Row 6

Acronym

PCI

Meaning

Pre-construction information

Why it matters

Information needed to plan construction work safely.

Row 7

Acronym

PPE

Meaning

Personal protective equipment

Why it matters

Last-line personal protection where risks remain.

Row 8

Acronym

RAMS

Meaning

Risk assessment and method statement

Why it matters

Task-level planning documents that support but do not replace the CPP.

Row 9

Acronym

SSIP

Meaning

Safety Schemes in Procurement

Why it matters

Common prequalification route for contractor competence evidence.

Read the complete comparison table
Acronyms and plain-English meanings
RowAcronymMeaningWhy it matters
1CDMConstruction (Design and Management)Main construction health and safety regime.
2CPPConstruction phase planPlan for managing health, safety and welfare during construction.
3F10HSE construction project notificationRequired for notifiable projects meeting CDM thresholds.
4HSEHealth and Safety ExecutiveGB regulator and official guidance source.
5HSENIHealth and Safety Executive for Northern IrelandNorthern Ireland regulator and official guidance source.
6PCIPre-construction informationInformation needed to plan construction work safely.
7PPEPersonal protective equipmentLast-line personal protection where risks remain.
8RAMSRisk assessment and method statementTask-level planning documents that support but do not replace the CPP.
9SSIPSafety Schemes in ProcurementCommon prequalification route for contractor competence evidence.
Individual editable BuildOut documents

Table ID: construction-phase-plan-buildout-documents

Source: https://www.sharehub.ltd/knowledge-hub/construction-phase-plan.html

Row 1

Document

Legal and other requirements registerBOUK-REG-GOV-01 · Blank register with separate fictional worked entries · v1.1

Purpose

A detailed GB construction legal baseline with 142 requirement entries, environmental permits and consents, national overlays and eight completed fictional decisions, plus a blank live register.

Editable download

Download XLSXRead preview

Row 2

Document

CDM project mobilisation and coordination procedureBOUK-PRO-CDM · Completed fictional example · v1.0

Purpose

Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover.

Editable download

Download DOCXRead preview

Row 3

Document

Project CDM applicability and dutyholder checklistBOUK-CHK-CDM-01 · Blank editable master · v1.0

Purpose

Check project definition, client type, contractor count, appointments and notification threshold.

Editable download

Download DOCXRead preview

Row 4

Document

Pre-construction information and gap registerBOUK-REG-CDM-01 · Blank register with separate fictional worked entries · v1.0

Purpose

Track asbestos, services, design, client and existing-structure information gaps.

Editable download

Download XLSXRead preview

Row 5

Document

Construction phase planBOUK-PLN-CDM-01 · Completed fictional example · v1.0

Purpose

Set project health and safety arrangements, site rules and specific high-risk measures before construction starts.

Editable download

Download DOCXRead preview

Row 6

Document

F10 notification decision and submission recordBOUK-FRM-CDM-01 · Blank editable master · v1.0

Purpose

Record threshold assessment, responsible dutyholder and update/submission evidence when required.

Editable download

Download DOCXRead preview

Row 7

Document

Coordination meeting and interface action recordBOUK-FRM-CDM-02 · Blank editable master · v1.0

Purpose

Record trade sequencing, shared risks, access and responsibilities.

Editable download

Download DOCXRead preview

Row 8

Document

Health and safety file and handover checklistBOUK-CHK-CDM-02 · Blank editable master · v1.0

Purpose

Gather proportionate residual-risk information and agree file responsibilities and delivery.

Editable download

Download DOCXRead preview

Row 9

Document

Site setup, welfare and housekeeping procedureBOUK-PRO-WEL · Completed fictional example · v1.0

Purpose

Plan boundaries, temporary accommodation, welfare servicing and routes before mobilisation.

Editable download

Download DOCXRead preview

Row 10

Document

Site establishment, welfare and access planBOUK-PLN-WEL-01 · Completed fictional example · v1.0

Purpose

Lay out boundaries, welfare, accommodation, storage and emergency routes.

Editable download

Download DOCXRead preview

Row 11

Document

Welfare readiness and daily condition checkBOUK-CHK-WEL-01 · Blank editable master · v1.0

Purpose

Verify toilets, washing, drinking water, changing and rest facilities are suitable and maintained.

Editable download

Download DOCXRead preview

Row 12

Document

Housekeeping, access and storage inspectionBOUK-CHK-WEL-02 · Blank editable master · v1.0

Purpose

Control slips, trips, waste, stacking and blocked routes.

Editable download

Download DOCXRead preview

Row 13

Document

Occupied premises and vulnerable-person interface assessmentBOUK-RA-WEL-01 · Blank editable master · v1.0

Purpose

Coordinate safe separation, access, dust/noise/fire controls and communication.

Editable download

Download DOCXRead preview

Row 14

Document

Site security, visitors and signage checkBOUK-CHK-WEL-03 · Blank editable master · v1.0

Purpose

Prevent unauthorised access and keep visitors supervised and informed.

Editable download

Download DOCXRead preview

Row 15

Document

Water-edge protection and adverse-weather procedureBOUK-PRO-WAT · Completed fictional example · v1.0

Purpose

Assess changing water/weather conditions, establish rescue/access controls and communicate suspension triggers.

Editable download

Download DOCXRead preview

Row 16

Document

Work-near-water and drowning-risk assessmentBOUK-RA-WAT-01 · Blank editable master · v1.0

Purpose

Evaluate avoidance, barriers, flotation, rescue and changing water conditions.

Editable download

Download DOCXRead preview

Row 17

Document

Water rescue and recovery planBOUK-PLN-WAT-01 · Completed fictional example · v1.0

Purpose

Define suitable equipment, trained people, access and emergency arrangements.

Editable download

Download DOCXRead preview

Row 18

Document

Weather, flood and ground-condition checkBOUK-CHK-WAT-01 · Blank editable master · v1.0

Purpose

Apply project-specific suspension/restart triggers and inspections.

Editable download

Download DOCXRead preview

Row 19

Document

Weather stop-work and restart authorisationBOUK-FRM-WAT-01 · Blank editable master · v1.0

Purpose

Record changed conditions, checks and competent release.

Editable download

Download DOCXRead preview

Row 20

Document

Snagging, cleaning and handover in occupied areas RAMSBOUK-RAMS-WEL-01 · Blank editable master · v1.0

Purpose

Public segregation, cleaning substances, access, isolated tasks and final reinstatement.

Editable download

Download DOCXRead preview

Read the complete comparison table
Individual editable BuildOut documents
RowDocumentPurposeEditable download
1Legal and other requirements registerBOUK-REG-GOV-01 · Blank register with separate fictional worked entries · v1.1A detailed GB construction legal baseline with 142 requirement entries, environmental permits and consents, national overlays and eight completed fictional decisions, plus a blank live register.Download XLSXRead preview
2CDM project mobilisation and coordination procedureBOUK-PRO-CDM · Completed fictional example · v1.0Confirm dutyholders, information, time/resources, construction phase plan, site rules and handover.Download DOCXRead preview
3Project CDM applicability and dutyholder checklistBOUK-CHK-CDM-01 · Blank editable master · v1.0Check project definition, client type, contractor count, appointments and notification threshold.Download DOCXRead preview
4Pre-construction information and gap registerBOUK-REG-CDM-01 · Blank register with separate fictional worked entries · v1.0Track asbestos, services, design, client and existing-structure information gaps.Download XLSXRead preview
5Construction phase planBOUK-PLN-CDM-01 · Completed fictional example · v1.0Set project health and safety arrangements, site rules and specific high-risk measures before construction starts.Download DOCXRead preview
6F10 notification decision and submission recordBOUK-FRM-CDM-01 · Blank editable master · v1.0Record threshold assessment, responsible dutyholder and update/submission evidence when required.Download DOCXRead preview
7Coordination meeting and interface action recordBOUK-FRM-CDM-02 · Blank editable master · v1.0Record trade sequencing, shared risks, access and responsibilities.Download DOCXRead preview
8Health and safety file and handover checklistBOUK-CHK-CDM-02 · Blank editable master · v1.0Gather proportionate residual-risk information and agree file responsibilities and delivery.Download DOCXRead preview
9Site setup, welfare and housekeeping procedureBOUK-PRO-WEL · Completed fictional example · v1.0Plan boundaries, temporary accommodation, welfare servicing and routes before mobilisation.Download DOCXRead preview
10Site establishment, welfare and access planBOUK-PLN-WEL-01 · Completed fictional example · v1.0Lay out boundaries, welfare, accommodation, storage and emergency routes.Download DOCXRead preview
11Welfare readiness and daily condition checkBOUK-CHK-WEL-01 · Blank editable master · v1.0Verify toilets, washing, drinking water, changing and rest facilities are suitable and maintained.Download DOCXRead preview
12Housekeeping, access and storage inspectionBOUK-CHK-WEL-02 · Blank editable master · v1.0Control slips, trips, waste, stacking and blocked routes.Download DOCXRead preview
13Occupied premises and vulnerable-person interface assessmentBOUK-RA-WEL-01 · Blank editable master · v1.0Coordinate safe separation, access, dust/noise/fire controls and communication.Download DOCXRead preview
14Site security, visitors and signage checkBOUK-CHK-WEL-03 · Blank editable master · v1.0Prevent unauthorised access and keep visitors supervised and informed.Download DOCXRead preview
15Water-edge protection and adverse-weather procedureBOUK-PRO-WAT · Completed fictional example · v1.0Assess changing water/weather conditions, establish rescue/access controls and communicate suspension triggers.Download DOCXRead preview
16Work-near-water and drowning-risk assessmentBOUK-RA-WAT-01 · Blank editable master · v1.0Evaluate avoidance, barriers, flotation, rescue and changing water conditions.Download DOCXRead preview
17Water rescue and recovery planBOUK-PLN-WAT-01 · Completed fictional example · v1.0Define suitable equipment, trained people, access and emergency arrangements.Download DOCXRead preview
18Weather, flood and ground-condition checkBOUK-CHK-WAT-01 · Blank editable master · v1.0Apply project-specific suspension/restart triggers and inspections.Download DOCXRead preview
19Weather stop-work and restart authorisationBOUK-FRM-WAT-01 · Blank editable master · v1.0Record changed conditions, checks and competent release.Download DOCXRead preview
20Snagging, cleaning and handover in occupied areas RAMSBOUK-RAMS-WEL-01 · Blank editable master · v1.0Public segregation, cleaning substances, access, isolated tasks and final reinstatement.Download DOCXRead preview