Buried services and excavation: planning before breaking ground · detailed source study

Optional reference study from the SHAREhub topic pages and selected source records used for this course. The core learning-time estimate excludes this extended reference.

Convert uncertainty into a digging hold point
Convert uncertainty into a digging hold point

Source: buried-services--review-start

Start with owner/private plans and the exact ground-breaking task, then locate and identify the services using suitable competent methods. Plans, a quiet locator and one trial hole are incomplete evidence for the whole excavation. Map what remains uncertain and how that uncertainty will be resolved. Start with owner/private plans and the exact ground-breaking task, then locate and identify the services using suitable competent methods. Plans, a quiet locator and one trial hole are incomplete evidence for the whole excavation. Buried services and utility strike prevention concern underground cables, pipes, ducts, mains, sewers and pipelines that can be damaged during excavation, drilling, piling, post-driving, trenching, demolition, remediation, landscaping or any work that penetrates the ground.

Apply it: Which part of this plan would you check at the workface before authorising the task? Buried services and utility strike prevention concern underground cables, pipes, ducts, mains, sewers and pipelines that can be damaged during excavation, drilling, piling, post-driving, trenching, demolition, remediation, landscaping or any work that penetrates the ground. A strike can cause fatal electric shock, arc-flash burns, gas explosion, fire, flooding, contamination, toxic release, loss of critical services, environmental damage and major disruption. Keep plans, scan marks, trial-hole record, permit, photographs and owner advice. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Repeat locating as cover is removed and resolve the changing trace with a competent operator and asset owner.

Expose alongside services using the assessed method; insulated hand tools may be needed near electric cables. Proceed only after competent physical confirmation of the relevant service and route, updated permit/method and worker briefing. Apply it: At which point would you hold this example, and what evidence would allow it to proceed? Buried-service strikes can injure people immediately and create wider fire, explosion, environmental and public-safety consequences. See HSE HSG47 avoiding danger from underground services Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Elimination: Reroute a foundation, duct or post so the trench avoids the mapped utility corridor; check that new ground is surveyed too.

Substitution: Use a surface-mounted or shallow engineered alternative instead of intrusive trenching where structural and service needs permit; do not substitute one unknown route for another. Engineering: Where contact cannot be avoided, arrange verified de-energisation or diversion by the asset owner; use a controlled trial hole and suitable physical separation from plant. Administrative: Maintain current plans, locator marks, a live permit, tool/plant limits, briefing and re-scan checkpoints as ground changes. PPE: Use task-assessed electrical or excavation PPE as a residual measure with fit and condition checks; it cannot make a live cable strike or gas explosion safe. Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged.

Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision? Keep one card or the full set for social sharing, team briefings and learning. Each PDF contains one card per page. Read the full topic for explanations, questions and source links.

Start with owner/private plans and the exact ground-breaking task, then locate and identify the services using suitable competent methods. Start with owner/private plans and the exact ground-breaking task, then locate and identify the services using suitable competent methods. Plans, a quiet locator and one trial hole are incomplete evidence for the whole excavation. Buried services and utility strike prevention concern underground cables, pipes, ducts, mains, sewers and pipelines that can be damaged during excavation, drilling, piling, post-driving, trenching, demolition, remediation, landscaping or any work that penetrates the ground. Apply it: Which part of this plan would you check at the workface before authorising the task? Use the evidence to improve the actual work arrangement.

Buried services and utility strike prevention concern underground cables, pipes, ducts, mains, sewers and pipelines that can be damaged during excavation, drilling, piling, post-driving, trenching, demolition, remediation, landscaping or any work that penetrates the ground. A strike can cause fatal electric shock, arc-flash burns, gas explosion, fire, flooding, contamination, toxic release, loss of critical services, environmental damage and major disruption. Keep plans, scan marks, trial-hole record, permit, photographs and owner advice. Apply it: What evidence would show that the change improves this task, rather than only completing a record? Fictional example: a practical application of the existing topic lesson. Repeat locating as cover is removed and resolve the changing trace with a competent operator and asset owner.

Expose alongside services using the assessed method; insulated hand tools may be needed near electric cables. Proceed only after competent physical confirmation of the relevant service and route, updated permit/method and worker briefing. Apply it: At which point would you hold this example, and what evidence would allow it to proceed? Connect the task, the route to the person and the control that can fail. Buried-service strikes can injure people immediately and create wider fire, explosion, environmental and public-safety consequences. See HSE HSG47 avoiding danger from underground services Apply it: Who could be exposed, including other trades, cleaners, maintainers and people nearby? Start with the stronger practicable options and verify their effect.

Elimination: Reroute a foundation, duct or post so the trench avoids the mapped utility corridor; check that new ground is surveyed too. Substitution: Use a surface-mounted or shallow engineered alternative instead of intrusive trenching where structural and service needs permit; do not substitute one unknown route for another. Engineering: Where contact cannot be avoided, arrange verified de-energisation or diversion by the asset owner; use a controlled trial hole and suitable physical separation from plant. Administrative: Maintain current plans, locator marks, a live permit, tool/plant limits, briefing and re-scan checkpoints as ground changes. PPE: Use task-assessed electrical or excavation PPE as a residual measure with fit and condition checks; it cannot make a live cable strike or gas explosion safe.

Read the full control table for qualifications, ownership and verification. Use the actual task and applicable jurisdiction; existing technical approval remains unchanged. Apply it: Which stronger option can be used here, and who will verify it before accepting the remaining risk? Follow the official sources below and retain the task-specific evidence. Use the full topic for the decision points, practical examples, detailed control tables and source scope. HSE guidance applies to Great Britain; use HSENI for the Northern Ireland route and the source’s stated jurisdiction. A simplified guide does not change the page’s technical-review or approval status. Apply it: Which official source and full-topic section will you use to resolve the next decision? Simplified learning guide.

Use the full topic and the actual work arrangements; existing technical-review and approval statuses still apply. Workplace scenarios labelled fictional are illustrative examples. A permit records the authorised method and its boundaries; the signature does not prove a service location. Unexpected traces, changed ground or a damaged service change the decision. Keep electrical contact, gas and flooding response routes distinct and maintain current location-specific contacts. Illustrative example. A crew finds a locator trace that changes with position and does not match the recorded route near the intended trench. Decision. Stop the affected ground-breaking and resolve the conflicting evidence through the competent locating/owner arrangements. Evidence to check. Retain plans, instrument/mode checks, marked uncertainties, controlled trial-hole evidence and the revised as-found route. Hold or escalation point.

No dig release from a quiet scan, a single exposed point or a signed permit with unresolved uncertainty. Follow-up. Reissue the method/permit where needed and brief the revised boundary before work resumes. Open Permit-to-dig uncertainty and evidence pack Read with: HSE HSG47 avoiding danger from underground services.

A plan line becomes evidence through checks
A plan line becomes evidence through checks

Source: buried-services--practical-buried-services

Information improves through different checks, but each type has limits. A detected trace is not the same as exposed identification, and knowing a location does not establish whether a service is live or safe. Review current asset-owner information, plan limits, work boundary and relevant site history. A drawn line is recorded evidence, not proof of exact position or depth. A competent survey uses suitable equipment and methods for the service and conditions. Keep ambiguous, untraced or conflicting zones visible; do not label every signal “confirmed”. An assessed safe-excavation route can identify the relevant service and position. Keep identity, ownership and status records connected; changes in ground or scope require the evidence to be revisited. HSG47’s planning, locating/identifying and safe-excavation elements work together.

Hold the next step when uncertainty affects it. No fixed clearance, depth, digging method or tool is authorised by this comparison. Read with: HSE avoiding danger from underground services.

What are the key facts about buried services?

Source: buried-services--key-facts

The key facts are that buried services are common, drawings are imperfect, locating equipment has limits and safe digging depends on behaviour in the ground. Source basis: HSE HSG47 avoiding danger from underground services · HSE underground cables · HSE excavation safety.

What are buried services and utility strike prevention?

Source: buried-services--what-is-it

Buried services are underground utility and process assets that can be damaged when the ground is penetrated, and utility strike prevention is the system used to avoid that damage. See HSE HSG47 avoiding danger from underground services The term includes electricity cables, gas mains and services, water mains, sewers, drains, telecommunications cables, fibre ducts, street-lighting cables, traffic-signal cables, district heating lines, fuel lines, chemical pipelines, process drains, private estate services, earthing systems, chambers, valves, joints and associated equipment. The most dangerous feature of buried services is that they are hidden.

Workers may see a clear patch of ground and assume it is safe, but below the surface there may be multiple services at different depths, in unexpected directions, with poor records or abandoned-looking assets that are still live. Buried-services management is therefore a system of uncertainty reduction. It does not ask one person to guess. It uses records, surveys, locating equipment, visible site clues, trial holes, controlled excavation, supervision, communication and emergency planning to reduce the chance of a strike. Electricity. Low-voltage, high-voltage, street lighting, site supplies and private cables. Contact can cause electrocution, severe burns, arc flash, fire and power loss. Gas. Mains, services, valves, governors and private pipework. Damage can cause gas escape, fire, explosion and evacuation. Water.

Potable mains, fire mains, process water and pressurised systems. Damage can cause flooding, high-pressure injury, undermining and service loss. Sewers and drains. Foul sewers, storm drains, interceptors and process drainage. Damage can cause contamination, infection risk, flooding and confined-space hazards. Telecoms and fibre. Copper, fibre, ducts, cabinets and network chambers. Damage can disrupt communications, emergency services and business continuity. Major hazard pipelines. Fuel, oil, gas, chemical or other hazardous-substance pipelines. Damage can create fire, explosion, toxic exposure or environmental harm.

What harm can buried service strikes cause?

Source: buried-services--hazards

Buried-service strikes can injure people immediately and create wider fire, explosion, environmental and public-safety consequences. See HSE HSG47 avoiding danger from underground services Electricity strikes are often misunderstood. The injury is not only a conventional electric shock; the explosive effect of arcing current can cause deep burns to hands, face and body, ignite clothing and throw hot metal or debris. A cable can be penetrated by a sharp tool, crushed by plant, damaged by a breaker or weakened by abrasion and fail later. Gas strikes can produce a leak that travels into ducts, chambers, buildings or excavations before ignition. Water and sewer strikes may appear less dramatic, but pressurised water can injure workers, flood trenches, undermine support, contaminate ground and create drowning or infection risks.

Fibre and telecoms damage may not injure the person holding the tool, but it can disrupt emergency communications, hospitals, businesses and transport systems. The biggest lesson for supervisors is that the hazard depends on the service, pressure, voltage, substance, work method, depth, surrounding ground, confined spaces, weather and whether other services are nearby. A single excavator bucket can damage gas and electricity together, creating escalation that was not visible in the task description. Electricity cable. Penetration, crushing, abrasion, breaker strike or unsupported exposed cable. Electrocution, arc-flash burns, fire, explosion and power outage. Gas pipe. Mechanical impact, scraping, joint damage, bending or delayed leak from weakened pipe. Gas escape, asphyxiation, fire, explosion and evacuation. Water main. Impact, pipe fracture, joint failure or undermining.

High-pressure jet injury, flooding, trench collapse and public supply loss. Sewer or drain. Breaking pipe, collapse, contamination or cross-connection. Pathogen exposure, pollution, odour, flooding and confined-space risk. Telecoms/fibre. Cutting, pulling, crushing duct or damaging chambers. Service outage, loss of emergency communications and business disruption. Hazardous pipeline. Impact, excavation too close, ground movement or inadequate consultation. Toxic release, fire, explosion, pollution and major incident potential.

What safe system does HSG47 expect for underground services?

Source: buried-services--safe-system

HSG47 is built around planning the work, locating and identifying buried services, and safe excavation. See HSE HSG47 avoiding danger from underground services The safe system should begin before anyone arrives with plant or a breaker. Clients and designers should obtain available information, identify constraints and provide it early. Contractors should review the information, assess the work method, arrange competent survey and decide how the ground will be opened safely. Locating and identifying services is then used to reduce uncertainty at the workface. Plans are interpreted alongside locating-device results, site features, visible covers, cabinets, poles, meters, gullies, valves, scars in reinstatement and local knowledge. The service route is marked clearly and the permit or briefing explains what those marks mean.

Safe excavation is the final control, not the first. If the work starts with an excavator because the programme is tight, the system has already weakened. Ground should be opened cautiously, trial holes used where needed, exposed services supported and protected, and work stopped when conditions do not match the plan. Plan the work. Obtain records, identify service owners, choose method and build risk controls into the programme. Utility searches, drawings, RAMS and construction phase plan. Locate and identify. Use competent survey, CAT/Genny, GPR where suitable, visible features and trial holes. Survey report, scan records, equipment checks and marked drawings. Mark and communicate. Mark routes clearly and brief the team on meaning, uncertainty and limits. Marked work area, toolbox talk and permit conditions. Excavate safely.

Use controlled hand digging, vacuum excavation or restricted plant methods near services. Permit to dig, supervisor checks and inspection records. Update and learn. Record actual positions, strikes, near misses and unexpected findings. As-built updates, investigation reports and action close-out.

How should work be planned before excavation starts?
How should work be planned before excavation starts?

Source: buried-services--planning

Planning should identify what might be underground, who owns it, how reliable the information is and how the work will avoid damage. See HSE HSG47 avoiding danger from underground services Planning must start with the task: excavation, post installation, trenching, piling, moling, drilling, site investigation, demolition, resurfacing, landscaping or breaking concrete. Each method has a different strike mechanism. A post rammer can pierce a cable, a breaker can damage a shallow service, a piling rig can hit deep assets, and trenchless work can intersect services away from the launch pit. The client should provide pre-construction information where CDM applies. That includes known underground services, site surveys, as-built records, previous investigations, private services and constraints.

The contractor should not accept vague statements such as 'services to be confirmed on site' without a clear plan for confirmation. Planning should also include service isolation where possible, emergency contacts, exclusion zones, traffic and pedestrian management, ground conditions, excavation support, confined-space risk, contaminated land, water ingress, night work, public interface and how changes will be authorised. Utility searches. Identifies known service owners and indicative routes. Responses, plans and correspondence. Private services. Private estates often contain unrecorded lighting, drainage, power or process lines. Estate drawings, interviews and site survey. Work method. Different tools create different strike risks. Method statement and plant/tool selection. Isolation feasibility. Dead or isolated services reduce consequence. Isolation certificate or utility confirmation. Emergency plan. People need immediate actions before a strike occurs.

Emergency contacts, briefing and site plan. Competence. Poor interpretation of scans or drawings can be as dangerous as no survey. Training, assessment and supervision record.

How should buried services be located and identified?

Source: buried-services--locating

Buried services should be located by combining records, visual clues, locating devices, competent interpretation and trial holes. See HSE underground cables Cable avoidance tools are useful but not magic. They can detect many conductive services, especially when used with a signal generator, but they can miss non-conductive pipes, plastic services, poorly earthed cables, congested areas or services masked by other signals. Ground penetrating radar can help in some conditions, but its performance depends on ground type, depth, object size, moisture and operator competence. The scan should not be a single sweep done at the start of the week.

Locating devices should be used frequently and repeatedly as work progresses because the excavation face changes, services may be exposed, and the route may not match the first interpretation. Trial holes are often the point where uncertainty becomes knowledge. They should be positioned and excavated carefully to confirm route and depth before mechanical excavation continues. Where a service is exposed, it should be identified, supported, protected and not used as a step, handle, prop or working platform. Utility drawings. Identifying likely service owners, routes and constraints. May be incomplete, approximate, out of date or missing private services. CAT passive modes. Detecting some live power and radio signals. Can miss quiet, dead, shielded or non-conductive services. CAT with Genny.

Applying a signal to improve tracing of conductive services. Requires correct connection/induction and competent interpretation. Ground penetrating radar. Detecting some non-metallic or unknown buried features. Affected by ground conditions, depth, clutter and operator skill. Trial holes. Confirming actual position and depth. Must be dug safely and may still require service-owner advice. Site clues. Covers, valves, poles, meters, trenches, scars and local knowledge. Clues support the assessment but do not prove absence. A utility survey can improve the plan, but cannot prove that every buried service has been found. HSG47 requires planning, locating and identifying services, followed by safe excavation.

HSE HSG47 underground-services guidance Vacuum excavation and jetting can assist safe exposure, but method selection must account for ground conditions, ejected material and damage to older or fragile services. Confirm the utility owner’s requirements, use competent operators and repeat locating as the excavation changes; neither suction nor a survey label makes an unknown service safe.

How should buried services be marked and communicated?

Source: buried-services--marking

Service markings should be clear, current, protected from confusion and explained to everyone working in the area. See HSE HSG47 avoiding danger from underground services Markings are a communication control. They help plant operators, groundworkers, supervisors and visitors understand where extra caution is needed. They should match the latest scan and permit, be refreshed if weather or traffic removes them, and be protected where the work area changes. Colour conventions and plans can support recognition, but they should not be treated as proof. Some services are not laid to expected depth, some are abandoned but still hazardous, some private services are unrecorded, and some routes move around obstacles.

The safer phrase is: 'This is the best verified information we currently have, and these are the limits of confidence.' The briefing should explain the markings, no-dig zones, hand-dig zones, trial-hole locations, plant exclusion rules, emergency stop points and who can authorise a change. Ground markings. Mark confirmed and suspected routes, trial holes and exclusion areas. Makes risk visible at the workface. Permit drawing. Attach marked-up plan to the permit or task briefing. Connects authorisation to actual location. Briefing. Explain markings, uncertainty, limits and stop-work triggers. Prevents workers guessing what a colour or line means. Refresh checks. Check markings after rain, traffic, resurfacing or shift change. Prevents people working from lost or stale information. As-built update. Record actual locations and unexpected findings.

Improves future planning and estate records. A paint mark is a communication aid; its meaning depends on the survey, limitations and confirmed findings behind it. When markings are covered, washed away or displaced by work, do not reconstruct them from memory and continue. Re-establish the service information with competent locating and verification appropriate to the planned method. A replacement crew must understand both what is known and what remains uncertain. For an illustrative trench reopened by a later shift, the supervisor walks the work area with the crew, compares current plans and survey findings with the surviving marks and identifies verified trial holes, exposed services and protected areas. Confirm the exact extent of the authorised task, tools, plant restrictions, owner contacts and stop conditions.

If the proposed depth, route or work method has changed, or the marks cannot be related reliably to the evidence, hold the affected excavation and update the assessment and permit before briefing the crew. Yesterday’s completed survey does not automatically authorise today’s different excavation. Guidance and scope: Original SHARE crew-change example applying HSE GB underground-service guidance. Plans and scans have limitations; no universal safe digging depth, offset or permission to assume an unmarked area is clear is given. HSE HSG47 avoiding danger from underground services HSE underground cables

What should a permit to dig control?
What should a permit to dig control?

Source: buried-services--permit

A permit to dig should confirm that the ground-breaking work has been planned, checked, briefed, authorised and handed back safely. See HSE HSG47 avoiding danger from underground services A permit to dig is not a permission slip for excavation. It is a control point where the supervisor checks that the work area, service information, survey, equipment, people, method, emergency arrangements and limits are ready. If the permit is issued from an office without field verification, it is weak. The permit should be specific to the location and task. It should identify the permitted area, depth, method, drawings used, services expected, survey equipment used, serial/calibration status, marks on the ground, isolation status, plant restrictions, hand-dig requirements, supervision, emergency contacts, hold points and expiry time.

The hand-back is just as important. The supervisor should confirm whether services were exposed, supported, damaged, diverted, made dead, re-energised, backfilled, protected or left with temporary arrangements. Scope. Exact work area, depth, method and timing. Permit description and marked drawing. Information. Utility plans, private-service records and survey results reviewed. Attached plans and survey report. Detection. Competent scan completed with suitable equipment. CAT/Genny serial, check date and operator name. Controls. Hand digging, plant exclusion, isolation, barriers and emergency arrangements defined. Permit conditions and briefing signatures. Authorisation. Supervisor verifies workface conditions before work starts. Field sign-off and hold points. Cancellation. Area left safe, services protected and records updated. Close-out sign-off and as-built notes.

How should excavation be carried out safely near buried services?

Source: buried-services--excavation

Excavation near buried services should be cautious, supervised and adjusted as information improves. See HSE underground cables Safe digging is a set of behaviours. Workers should not use picks, breakers, pins, forks or excavator teeth aggressively into ground where services may exist. Once a service is suspected or located, excavation should normally proceed alongside it rather than directly above it, using suitable hand tools or vacuum excavation where appropriate. Mechanical excavation can rapidly turn uncertainty into a strike. If plant is used, it should operate under defined limits, with a banksman or supervisor, clear exclusion zones, no blind digging, no scraping directly across services and stop points before entering higher-risk zones. Exposed services must be protected.

Cables and pipes can be damaged by being left unsupported, struck by spoil, used as steps, exposed to weather, bent, scraped, vibrated or backfilled with unsuitable material. Backfilling should avoid sharp materials and should restore protection, support and marker information. Hand digging. Use controlled, suitable tools near known or suspected services. Aggressive use of picks, bars or breakers. Trial holes. Confirm route and depth before wider excavation. Assuming drawings prove exact location. Plant control. Set exclusion zones, depth limits and supervision. Excavator used before service position is confirmed. Service support. Support and protect exposed services. Cables left hanging across trench or used as access. Backfill. Use suitable material and reinstate markers/protection. Sharp rubble or concrete placed against service. Stop-work trigger.

Pause if conditions differ from plan. Continuing after unexpected pipe, duct or cable is found.

What should workers do if a buried service is damaged?

Source: buried-services--emergency

Workers should stop work, keep people away, raise the alarm and follow the service-specific emergency plan. See HSE HSG47 avoiding danger from underground services Emergency actions must be briefed before work starts because a strike is not the moment to invent the response. The right action depends on the service: electricity, gas, water, sewer, telecoms or hazardous pipeline. Workers should know who calls the service owner, who controls the area, who stops plant, who prevents re-entry and who reports the incident. With suspected live electrical damage, people should avoid touching equipment, exposed cable or anyone in contact with electricity until it is safe. With gas, ignition sources should be controlled, people moved away and emergency services or the gas emergency number contacted.

With water or sewer damage, the risks include trench flooding, undermining, contamination and confined-space atmospheres. Near misses matter. A scraped duct, cracked pipe, unexpected service or minor cable damage can become a delayed failure if left unreported. Electricity. Stop work, keep clear, prevent contact, isolate if competent route exists and contact the network owner/emergency services. Damaged cables can arc, re-energise or remain live. Gas. Stop work, remove ignition sources if safe, evacuate, call emergency gas response and prevent re-entry. Gas can travel and ignite away from the strike point. Water. Stop work, leave excavation if flooding or instability develops and contact the service owner. Flooding can collapse ground or trap workers. Sewer/drain. Stop work, avoid contact, consider contamination and confined-space risk.

Sewage can expose workers to pathogens and toxic atmospheres. Telecoms/fibre. Stop work and contact service owner. Service damage can disrupt emergency communications and critical systems. Hazardous pipeline. Stop work, evacuate according to the pipeline emergency plan and contact the operator immediately. Contents may be flammable, toxic, pressurised or environmentally harmful.

How can ERICPD be applied to buried-services risk?

Source: buried-services--ericpd

ERICPD helps prioritise avoiding or reducing ground-strike risk before relying on PPE or worker judgement. See HSE HSG47 avoiding danger from underground services The strongest buried-services control is to avoid breaking ground near the service at all. Designers can reroute work, relocate foundations, use above-ground solutions, isolate services, divert services or programme work after de-energisation. Where the work must proceed, the aim is to reduce uncertainty and separate people and plant from the hazard. Administrative controls, such as permits and briefings, are essential but they should sit on top of good design, reliable information and physical controls. PPE may reduce some injury severity, but it cannot prevent a gas explosion, arc flash or flooding incident. Eliminate. Avoid ground-breaking or reroute work away from services.

Use surface-mounted ducting or relocate fence line. Reduce. Reduce depth, energy or exposure where possible. Make cable dead, lower plant size or limit excavation footprint. Isolate. Separate people and plant from service routes. No-dig zones, barriers, exclusion areas and remote methods. Control. Use survey, permits, trial holes, hand digging and supervision. Permit to dig with marked service routes and hold points. PPE. Use suitable PPE for residual task risks. Eye/face protection, gloves, safety footwear and flame-resistant clothing where justified. Discipline. Reinforce stop-work rules, competence and behaviour. Supervisor checks, observations and near-miss learning.

Do UK jurisdiction differences matter for buried services?
Do UK jurisdiction differences matter for buried services?

Source: buried-services--uk-differences

The practical controls are largely consistent, but regulator routes, street works, utility ownership and Northern Ireland guidance should be checked locally. See Construction (Design and Management) Regulations (Northern Ireland) 2016 For most buried-services work, the core controls do not change between England, Wales, Scotland and Northern Ireland: plan the work, obtain information, locate and mark services, use safe digging practice and stop if the work does not match the plan. Differences can matter where the work falls under street works, highways permits, utility-owner requirements, environmental consents, railway land, major hazard pipelines or Northern Ireland regulatory routes. Organisations working across the UK should therefore use one strong safe-digging standard, supported by local legal and utility checks for the place where the work is being carried out.

The page is UK-facing, so official HSE guidance is used as the main GB reference. Northern Ireland readers should also check HSENI guidance and local utility requirements. Street works. Permit, notice and reinstatement arrangements can depend on highway authority and nation. Check local street works and highways requirements. Utility owners. Plans, emergency numbers and isolation rules differ by asset owner. Keep current service-owner contacts and requirements. Northern Ireland. HSENI is the workplace health and safety regulator. Check HSENI safety alerts and NI utility procedures. Major hazard pipelines. Operator consultation and land-use restrictions can be site-specific. Contact pipeline operator before work near notified routes. Environmental permits. Discharge, contaminated water and pollution response may need local regulator approval.

Check Environment Agency, NRW, SEPA, NIEA or local authority route.

Which legal duties apply to buried services?

Source: buried-services--legal

Buried-services duties come from health and safety, construction, work equipment, electrical, gas, pipeline, street works and reporting law. Legal compliance is not achieved by having a permit form alone. Dutyholders must plan, manage and monitor the work, provide information, assess risks, use competent people, maintain suitable equipment, prevent danger from electricity and gas, coordinate with service owners and report specified dangerous occurrences where required. The table separates Great Britain and Northern Ireland instruments; check the current national route for the work location. The GB construction regulation is CDM 2015; the relevant Northern Ireland underground-services provision is CDM (NI) 2016 regulation 24(4). HSG47 is guidance, not a universal 500 mm excavation permission.

How should buried-services risks be recorded in a risk register?

Source: buried-services--risk-register

A buried-services register should connect each ground-breaking activity to service uncertainty, controls, owners and verification evidence. See HSE HSG47 avoiding danger from underground services A useful register does not simply say 'underground services present'. It explains what services may be present, how reliable the information is, what detection has been completed, what work method is allowed, what is prohibited, what emergency action is required and what evidence proves the controls are live. For long projects, the register should change as knowledge improves. Every trial hole, exposed service, strike, near miss and as-built update should improve the next excavation.

How could BuildOut Ltd manage buried services on construction projects?

Source: buried-services--business-example

BuildOut Ltd could manage buried-services risk through early utility searches, competent surveys, permit-to-dig control and disciplined field supervision. a fictional construction and refurbishment contractor delivering housing, commercial fit-out, groundworks and small civil engineering projects BuildOut treats buried services as a pre-construction and workface control issue. During tender and planning, the project manager requests utility records, asks the client for private-service information, checks previous site investigations, reviews drawings for conflicts and identifies where diversions, isolation or redesign could remove the need to dig near services. Before ground-breaking work starts, BuildOut commissions a competent utility survey matched to the task risk. The surveyor records equipment used, limitations, confidence levels and areas where further trial holes or service-owner consultation are required.

The site team then creates a marked-up buried-services plan, identifies no-dig and hand-dig zones, and writes permit conditions that match the actual ground. The permit issuer walks the work area before authorisation. They check markings are visible, CAT/Genny checks are current, workers understand the markings, plant restrictions are clear, emergency contacts are displayed and the supervisor knows when to stop. Plant operators are briefed on depth limits and exclusion zones; groundworkers are briefed on hand-digging technique, exposed-service protection and unexpected-service escalation. BuildOut checks performance at three levels. First-line supervisors complete daily checks on markings, permits and trial holes. Second-line H&S advisers sample permit quality, interview operatives and review whether CAT/Genny use is genuine rather than tick-box.

Third-line audits look across projects for repeated causes: missing private-service records, poor client information, weak contractor competence, expired locator checks, plant working too close or near misses not being learned from. When a strike or near miss occurs, BuildOut investigates the system rather than blaming the worker holding the tool. It asks whether the client information was adequate, whether drawings were challenged, whether survey limitations were understood, whether the permit was field-verified, whether supervision was present and whether programme pressure encouraged shortcuts. Assess. Reviews utility plans, client information, private services and task method before work starts. Pre-construction information review and buried-services risk register. Analyse. Compares drawings, site clues, survey results and proposed excavation method. Marked-up plan, survey report and conflict log. Train.

Trains supervisors, plant operators and groundworkers in HSG47 principles, CAT/Genny limits and stop-work rules. Training matrix, practical assessment and toolbox talk record. Implement. Uses permits to dig, service markings, trial holes, plant exclusion zones and emergency contacts. Signed permit, photographs, scan sheet and daily supervisor check. Check. Samples permits, observes digging, interviews workers and audits contractor evidence. Assurance checklist, H&S inspection and audit report. Learn. Investigates strikes, near misses, unexpected services and poor survey confidence. Investigation report, root causes and lessons learned briefing. Improve. Updates procedures, procurement, competence, survey specifications and client information requirements. Revised standard, supplier review and management review action.

What training is useful for buried-services work?
What training is useful for buried-services work?

Source: buried-services--training

Training should be layered so everyone understands the hazard, while high-risk roles can plan, locate, authorise and excavate safely. General awareness is needed for anyone who may enter or influence a ground-breaking work area. It should explain the types of buried services, harm from strikes, site markings, exclusion zones, emergency actions and the right to stop work. Short topical training is useful for workers most exposed to the hazard: groundworkers, fencing teams, landscapers, demolition workers, maintenance teams, trial-hole teams and plant operators. This should be practical and include local drawings, markings, tools, plant limits and emergency actions. Supervisors, permit issuers, survey coordinators and managers need deeper training.

They should understand HSG47, CDM duties, utility searches, survey limitations, permit quality, competence checks, contractor control, incident investigation and how to challenge weak information. Competence means a person can carry out the actual task safely, recognise a changed condition and respond correctly. Attendance alone is insufficient. The matrix makes assessment, ownership, records and reassessment explicit.

How does buried-services safety support qualification study and professional development?

Source: buried-services--study-development

Buried-services safety helps learners connect CDM planning, excavation hazards, contractor control, permits and supervision. For IOSH Construction Certificate learners, buried services sit within excavation safety, underground and overhead services, CDM dutyholders, pre-construction information, construction phase planning, temporary works, permit systems and contractor management. Scenario questions may describe a site where workers start digging from poor drawings, no survey or weak supervision. A strong answer explains the full control chain: client information, designer avoidance, utility searches, survey, locating devices, ground marking, permit to dig, safe excavation, emergency arrangements, supervision, inspection and learning. It should also mention that plans are indicative and that locators have limitations. For professional development, buried-services competence is highly practical.

People need to understand not just the law, but how decisions at tender, design, planning, permit issue and the workface affect whether a worker meets a live cable or gas pipe. IOSH Construction. Excavation, underground services, CDM, permits and contractor control. Explain controls before digging near a suspected cable route. Supervisor development. Permit quality, field verification and stop-work decisions. Reject a permit where plans conflict with site markings. Plant operator competence. No-dig zones, banksman communication and mechanical excavation limits. Stop plant before entering hand-dig zone. H&S adviser CPD. Audit permit systems, survey confidence and contractor competence. Review a utility strike and identify system causes. Client/project manager CPD. Pre-construction information and programme planning. Allow time and budget for utility survey and diversion.

How can management systems strengthen buried-services control?

Source: buried-services--management-system

Management systems make buried-services controls repeatable, evidenced and improved across projects. A management system should define when utility searches are required, who can approve survey specifications, who can issue permits, what competence is required, how CAT/Genny equipment is checked, how markings are maintained, how plant exclusion zones are enforced and how incidents are investigated. A voluntary management framework clauses can help organise this without turning it into paperwork. The practical value is in making buried-services controls visible in procurement, planning, operations, monitoring and improvement. The practical management cycle is to assign owners, provide resources and competence, verify controls or workload changes, investigate failure and improve. ISO certification alone does not prove the task is safe.

Which incidents show why buried-services controls matter?

Source: buried-services--major-learning

HSE learning shows that failures usually involve missing plans, poor locating, weak supervision or continuing after damage. Utility strikes are useful learning cases because they often look simple after the event. The worker struck the cable, but the system failed earlier: information was not obtained, drawings were not challenged, the locator was not used properly, the permit was weak, supervision was absent or work continued after warning signs. Use these examples to test whether local buried-services controls would have prevented the event. HSE: Fencing contractor fined after underground cable strike. A worker suffered electric shock and burns after striking a live underground cable while installing fencing. HSE found suitable controls had not been implemented.

Work liable to create risk from underground services should not proceed without planning, locating, marking and safe excavation controls. HSE: Failure to use a cable locator. A labourer received burns after an underground 415 V electrical supply was damaged during excavation where a locator had not been used. Plans must be supported by a cable locator and trial holes where needed; advice from the electricity distributor must be acted on. HSE: Gas pipes and electrical cables struck by mechanical digger. A mechanical digger struck several gas pipes and an electricity cable, yet work continued. If work does not go to plan, stop and reassess; continuing after damage can seriously endanger workers and the public.

What are the warning signs that buried-services risk is not controlled?

Source: buried-services--warning-signs

Warning signs include vague drawings, no scan evidence, office-issued permits, lost markings, aggressive digging and weak stop-work behaviour. Buried-services failures normally give warning before the strike. Plans arrive late, private services are ignored, surveys are treated as guaranteed, CAT readings are not recorded, paint markings are faded, plant moves into hand-dig zones, workers cannot explain emergency actions or supervisors sign permits without visiting the workface. Each warning sign has a harm pathway. Missing drawings can put workers directly above a live cable. No Genny use can miss a service that passive mode does not detect. Poor handover can leave the next shift digging from old markings. Continuing after a scrape can turn minor damage into a fatal event later. No private-service information.

Estate lighting, power, drainage or process lines may be missed. Interview site owner, survey private services and update records. Permit issued from office. Workface conditions and markings may not match the permit. Require field verification before authorisation. CAT/Genny details missing. No proof equipment was suitable, checked or used by a competent person. Record serial, check status, mode and operator. Faded or confusing markings. Workers may dig in the wrong place or misunderstand service routes. Refresh markings and rebrief before work continues. Mechanical excavation too close. Bucket or breaker can strike service before it is exposed. Set exclusion zones, trial holes and supervisor hold points. Unexpected service ignored. Unknown live service may be damaged later. Stop, identify, consult and revise permit. No near-miss learning.

Repeated weak signals remain until a serious strike occurs. Investigate and update procedure, training and procurement.

When do plans and scans still leave the location uncertain?
When do plans and scans still leave the location uncertain?

Source: buried-services--uncertainty-stop

Plans indicate possible routes but are not proof of the exact position, depth or presence of private services. A trained person should use a suitable locator in appropriate modes, mark the interpretation, repeat scans as ground is opened and use trial holes or other suitable confirmation before intrusive plant work. Plastic or non-conductive services and congested ground may not be detected. See HSE HSG47 avoiding danger from underground services If the plan, site clues and locator disagree, or a signal cannot be explained, stop the relevant excavation. Ask the asset owner or competent surveyor for better information and redesign or expose carefully; do not guess a depth from a colour chart or an old drawing.

What happens if a cable or pipe is struck or suspected damaged?

Source: buried-services--strike-response

Stop work, withdraw people from the danger area without touching the service or plant if electrical contact is possible, prevent ignition or entry into gas accumulation areas, and summon the relevant utility emergency service. Do not attempt an improvised repair or assume an apparently minor scrape is harmless. See HSE HSG47 avoiding danger from underground services The supervisor secures the area, preserves facts and arranges competent utility assessment. Work restarts only after the owner confirms status, the method and permit are revised and the team is rebriefed. Emergency service and evacuation details depend on the asset and site plan.

How do decisions work on a real shift?

Source: buried-services--worked-decisions

These examples show prerequisites, controls, stop conditions, decision owner, hand-back and evidence. Adapt them to the actual site, person and jurisdiction. See HSE HSG47 avoiding danger from underground services Source basis: HSE HSG47 avoiding danger from underground services · HSE underground cables · HSE excavation safety. Source basis: HSE HSG47 avoiding danger from underground services · HSE underground cables · HSE excavation safety.

How can the ISO 45001 hierarchy of controls prevent buried-service strikes during excavation?

Source: buried-services--control-hierarchy

ERICPD (Eliminate, Reduce including substitution, Isolate, Control, PPE, Discipline) and HSE’s five-level hierarchy (elimination, substitution, engineering, administrative, PPE) guide related but non-identical choices. Start at source; consider feasibility and any risk shifted elsewhere. Discipline means maintaining, supervising and learning from controls, not blaming workers. See HSE hierarchy; HSE five-level hierarchy of control ERICPD is a planning crossmap. Its prompts do not add a sixth rung or rank Isolate above engineering. Discipline verifies and sustains every control level. The hierarchy of controls in ISO 45001:2018 comes under Clause 8.1.2 (Eliminating hazards and reducing OH&S risks), which is located within Clause 8 ("Operation"). ESEAP: Elimination, Substitution, Engineering controls, Administrative controls and PPE. Control order: HSE hierarchy of controls and IOSH hierarchy of control guidance.

How does the hierarchy apply to each material harm route?

Source: buried-services--hazard-control-map

Each route below maps all five HSE levels to ERICPD, records where a stronger control may not be feasible, and states who checks failure and when the task must stop. It supplements the general task hierarchy above; site conditions and the affected people still govern the final control choice.

What does official guidance add to this decision?

Source: buried-services--standards-application

Plan the work, locate and identify services, and excavate safely. Survey confidence is a planning input, never proof that every service has been found. Use the current HSE HSG47 underground-services guidance and the jurisdiction-specific duties listed on this page to verify the actual task and controls. If a contract or competent design specifies a published technical standard, obtain authorised access to its current text and check its exact scope and edition. Apply the standard only within its stated scope; this guidance does not reproduce its clauses.

Duct trench beside a marked cable

Source: buried-services--example--buried-services-example-01

Task Material And Setting: A contractor must excavate a pavement duct. Drawings show a cable but the locator trace shifts near a cabinet and a private supply is suspected. People And Prerequisites: The client and excavation supervisor need network and private-service records, site observations, locator competence/equipment checks, utility-owner advice, trial-hole method and a clear permit hold point. Before: Hold the excavator, obtain all available operator/private plans, inspect covers and cabinets, scan in suitable modes and mark uncertainty; agree a safe trial-hole method. During: Repeat locating as cover is removed and resolve the changing trace with a competent operator and asset owner. Expose alongside services using the assessed method; insulated hand tools may be needed near electric cables.

Vacuum/air/water methods need suitable ground conditions and controls for ejected material and fragile cables; they are not automatically harmless. Support exposed assets without moving them or using them as footholds. Hold Or Stop: Stop when signals conflict, the service is not positively identified, cover is unexpected or the excavator enters the agreed exclusion area. Decision Owner: Client supplies known records; principal contractor controls the method; supervisor owns the permit and stop point; utility owner advises on its asset. Completion And Hand Back: Proceed only after competent physical confirmation of the relevant service and route, updated permit/method and worker briefing. If safe work requires the service to be made dead, obtain owner isolation confirmation. Record as-found depth/route, support and agreed protection/backfill for later workers.

Evidence: Keep plans, scan marks, trial-hole record, permit, photographs and owner advice. Changed Conditions: Reassess when the task, people, asset, work design, evidence or legal scope changes. Source Scope: HSG47/HSE cable guidance is GB technical guidance; NI CDM 2016 applies separately. A plan, quiet locator or trial hole at one point does not guarantee the whole route or safe clearance. Source boundary: HSG47/HSE cable guidance is GB technical guidance; NI CDM 2016 applies separately. A plan, quiet locator or trial hole at one point does not guarantee the whole route or safe clearance.

Unexpected gas pipe under an industrial slab

Source: buried-services--example--buried-services-example-02

Task Material And Setting: During slab breaking a team uncovers an unmarked pipe with a gas smell near a basement intake. People And Prerequisites: The incident controller needs the site’s correct local gas emergency contact, safe evacuation and access plan, connected drains/basements/air intakes and asset-owner control route. Before: Stop work and withdraw without approaching the suspected release or operating switches in the affected atmosphere. Prevent access and ignition from a safe location and contact the local gas emergency service; call emergency services for immediate danger. Do not test, move or improvise repair of the pipe. During: Treat connected drains, ducts, basement spaces and the intake as possible gas-migration routes.

The incident lead sets safe exclusion and communications with the asset owner and responders; staff must not enter a basement to investigate or attempt ventilation without their safe direction. Hold Or Stop: No restart while release, identity, isolation or atmosphere is uncertain; no improvised repair. Decision Owner: Site incident controller owns evacuation and area control; gas owner controls asset isolation and repair. Completion And Hand Back: Resume only after the asset owner controls the release and gives appropriate clearance, competent area/migration checks confirm safety, and the supervisor revises the plans, excavation/support method and permit. Brief the whole crew and record what changed before plant returns. Evidence: Keep incident chronology, utility response, revised drawings and investigation actions.

Changed Conditions: Reassess when the task, people, asset, work design, evidence or legal scope changes. Source Scope: The gas response is an illustration under HSG47 and applicable local emergency arrangements. Do not assume one national contact number, enter a suspected atmosphere or use a permit as utility clearance. Source boundary: The gas response is an illustration under HSG47 and applicable local emergency arrangements. Do not assume one national contact number, enter a suspected atmosphere or use a permit as utility clearance.

Use this route before digging; use Excavations for the open trench
Use this route before digging; use Excavations for the open trench

Source: excavation--review-start

The pre-dig supervisor obtains current information from the client and service owners and asks the competent locator to resolve conflicting evidence. The temporary-works or support designer confirms the support and sequence where design is needed. The responsible site manager releases the defined stage only after the approved method, service controls, competent checks and briefing are in place. A permit, drawing or locator result alone cannot authorise digging. Unexpected ground, water, a service or a changed load reopens the decision. Keep the existing full planning and worked examples; use the open-trench companion for current workface inspection. Content amended 19 October 2026 by the SHARE Knowledge Hub editorial team. This records an editorial content change; the existing technical-review and approval status still applies.

Resolve the evidence before the first ground disturbance

Source: excavation--practical-excavation

Records, locating and controlled exposure contribute different information. A conflict between them, uncertain ground or an adjacent structure can prevent a valid release decision. Compare current service information, locating limitations, ground conditions and adjoining structures. Use suitable competent assessment of exposure, support, access and work method for the actual conditions. Record who can release the work and on what evidence. Keep an unknown service or conflicting result on hold rather than guessing. The linked Excavations topic covers conditions during the open excavation. This scene is not a digging method or support design. Further guidance: HSE: construction.

What must be confirmed before anyone enters an excavation?

Source: excavation--field-ready-controls

Confirm the excavation is stable through suitable support or safe battering, buried services are identified and controlled, entry and edges are protected, and a competent inspection has found it safe. Stop for changed ground, water, plant loading or an unexpected service. CAT means cable avoidance tool and Genny means signal generator; they help locate buried services but do not replace plans and safe exposure. RAMS means risk assessment and method statement. SHEQ means safety, health, environment and quality; it describes a management function, not a substitute for the competent workface decision. A utility trench crosses a road with incomplete service plans. The contractor obtains updated information, scans and marks the route, exposes services by a safe method, installs designed support and controls traffic and access.

A newly found cable stops mechanical digging until its owner and a competent lead agree the revised method.

What are the key facts about excavation safety?

Source: excavation--key-facts

The key facts are that excavation risk changes rapidly and must be controlled through planning, physical protection, competent inspection and stop-work discipline.

What is excavation safety in practical terms?

Source: excavation--meaning

Excavation planning is the evidence-led decision to dig, avoid digging or change the method before people and plant are exposed. Source basis: HSE excavations guidance · HSE HSG47 avoiding danger from underground services · HSENI CDM 2016 guidance. Source basis: HSE excavations guidance · HSE HSG47 avoiding danger from underground services · HSENI CDM 2016 guidance. Excavation includes trenches, pits, basements, foundations, drainage runs, utility connections, trial holes, shafts, cofferdams, caissons and temporary ground openings. The work may be small and short-term, but the hazards can be severe if the excavation collapses, strikes a cable, damages a gas main, undermines a wall or fills with water. See HSE excavations guidance. The safest excavation is often the one avoided or reduced at design stage.

Trenchless techniques, different routing, prefabrication, changed sequence or design coordination can remove or reduce the need for people to enter an excavation. Where excavation is necessary, the management system should define who provides information, who verifies services, who designs support, who authorises work, who inspects, who supervises and what happens when conditions change.

What hazards are created by excavation work?

Source: excavation--hazards

Excavation hazards include collapse, falling materials, falls, buried services, plant, water, contaminated ground, hazardous atmospheres and undermined structures. A good excavation assessment should describe how harm can happen. Do not simply list 'collapse' or 'services'. Explain whether people will enter the trench, how deep it is, what soil is present, where spoil will go, what plant will pass nearby, what services are known or suspected and how quickly the workface will change. Hazards can combine. A trench near a road may have vibration, traffic loading, buried services, poor access and public interface. A drainage excavation may also involve sewer gases, water ingress and confined-space entry.

How should excavation work be planned before digging starts?

Source: excavation--planning

Before release, verify service records and site detection, ground and water assumptions, temporary works design, access and plant arrangements, competent inspection and rescue needs; record who can stop the work. Planning should start with information gathering. Clients and designers should provide relevant information on ground conditions, existing services, underground structures, watercourses, previous site use and adjacent structures. Contractors should verify this information rather than assuming plans are complete. A pre-dig release is conditional. Record the design assumptions, source of each buried-service plan, locator limitations, trial-hole locations, temporary works reviewer, plant route, competent inspector and rescue contact. If a contractor changes the route or depth, the information and authority must be revisited before the cut continues. The method should be selected before plant arrives.

Decide whether trenchless methods are practicable, whether workers need to enter, what support is required, how services will be located, how public and traffic interfaces will be controlled and what inspections are required.

What should a pre-dig release decision contain?

Source: excavation--permit-to-dig

A permit-to-dig is a controlled hand-off from planning to the workface. It does not prove the ground or services are safe by itself; the named authoriser must check the evidence and define what changes cancel the release.

How should collapse risk be controlled?

Source: excavation--collapse

Collapse risk should be controlled by avoiding entry where possible, then using designed support, trench boxes, battering or other engineered controls. Source basis: HSE excavations guidance. Source basis: HSE excavations guidance. The sides of a trench can collapse without warning. Soil may look firm but fail after rain, drying, vibration, loading near the edge, excavation below previous backfill, nearby traffic or changes in groundwater. Never infer safety from a fixed depth, a 45-degree slope or how firm the side looks. A competent, site-specific assessment must justify any work without support or safe battering and must be revisited when conditions change.

Control options include trench boxes, hydraulic or timber shoring, sheet piles, battered sides, benching, ground treatment, reduced depth, remote working or sequencing that avoids people entering. The choice depends on ground, depth, duration, work activity, access and adjacent loads. Shoring supports the ground; a trench box primarily shields people working inside it. The box does not stabilise adjacent structures or make unprotected edges safe. The design must address access, lifting, box position, movement and work beyond its protected footprint.

How should buried services be managed during excavation?
How should buried services be managed during excavation?

Source: excavation--services

Buried services should be managed through planning, locating, marking, safe digging and stop-work rules. HSG47 sets out the basic safe-system logic for work near underground services: plan the work, locate and identify services, then excavate safely. Plans are useful but not perfect. Services may be unrecorded, inaccurately located, altered, shallow, damaged or shown using different symbols. See HSE HSG47 avoiding danger from underground services. Treat a service drawing as a lead, not a clearance certificate. Compare plans from each owner with on-site detection, identify private and abandoned services, mark uncertainty, and prove position by an appropriate exposure method before mechanical digging. A missing record or conflicting signal is a reason to stop and resolve the route.

Cable avoidance tools and signal generators are valuable only when used by trained people who understand their limitations. Trial holes should be used to confirm location, and mechanical excavation should be controlled near known or suspected services. If an unexpected service is found, stop and reassess.

How should falls and falling materials be prevented?

Source: excavation--edge-protection

Falls and falling materials should be prevented by edge protection, safe access, spoil control, plant exclusion and protected crossing points. People can fall into excavations from open edges, poor lighting, narrow routes, unprotected crossings or failed covers. Materials can fall into excavations from spoil heaps, stacked materials, kerbs, tools, plant movement or poorly managed edge loading. Edge protection should be substantial enough for the risk. In some cases barriers, guardrails, toe boards, trench box extensions, covers, signage, lighting and exclusion zones will be needed. Spoil should be set back far enough that it does not surcharge the trench edge or fall into the excavation.

How do water, weather and ground conditions change excavation risk?

Source: excavation--water-ground

Water, weather and ground conditions can rapidly reduce stability and change the controls needed. Water adds weight, reduces soil strength, erodes faces, hides services and can flood low areas. Rain, drying, freeze-thaw, vibration and pumping can all change stability. Excavations near rivers, lakes, the sea, drains or made ground need careful review. Dewatering should be planned. Pumping from sumps may help remove water, but it can also affect ground stability. Temporary works design should consider water pressure and weather. Inspections should be repeated after events that may affect strength or stability.

When can an excavation create a confined-space or atmosphere risk?

Source: excavation--atmospheres

An excavation can create confined-space or atmosphere risk where access is restricted and there is danger from gases, fumes, low oxygen, flooding or engulfment. Not every excavation is a confined space, but some clearly can become one. Examples include deep manholes, sewer work, shafts, pits, contaminated land excavations, trenches connected to drains or work where diesel or petrol exhaust can collect. Low points can trap gases and fumes. See HSE confined spaces guidance. If confined-space risk is foreseeable, the work needs specific assessment, atmosphere testing where appropriate, ventilation, isolation, supervision, communication and rescue arrangements. Rescue should not rely on unplanned entry by colleagues.

How should plant and vehicle interface be controlled?

Source: excavation--plant

Plant and vehicle interface should be controlled by segregation, exclusion zones, competent operators, edge-distance rules and clear communication. Excavators, dumpers, delivery vehicles and compactors can strike people, overload excavation edges, damage services or block emergency access. The work area should be planned so plant movements do not conflict with people, access points, spoil storage or open edges. Plant operators should understand buried-service controls and exclusion zones. Supervisors should check that nobody is working in a machine's slew radius and that loads are not placed where they can destabilise the excavation.

What inspections are needed for excavations?

Source: excavation--inspection

Excavations should be inspected by a competent person before work starts each shift and after events that may affect strength or stability. Inspection is not a paperwork ritual. It is a live control that decides whether people can enter or work near the excavation. The competent person must understand collapse mechanisms, support systems, water, edge protection, spoil, access, services and changing conditions. See HSE excavations guidance. Where a report is required, it should record the location, description, date, time, matters identified, actions taken, further action needed and the person making the report. Defects that could create danger should be corrected before work continues.

What emergency arrangements are needed for excavation work?

Source: excavation--emergency

Emergency arrangements should cover collapse, service strike, flooding, hazardous atmosphere, injury and rescue without exposing rescuers to uncontrolled risk. Excavation emergencies can escalate quickly. A trench collapse may bury a person and leave rescuers exposed to further collapse. A gas strike may create fire or explosion risk. A cable strike may cause burns and live electrical danger. Flooding or atmosphere issues may make entry unsafe. The emergency plan should be specific to the excavation. It should include stop-work rules, evacuation, utility emergency contacts, first aid, rescue equipment, competent rescue arrangements where needed, incident command and how the work area will be secured.

How can the ISO 45001 hierarchy of controls prevent collapse and service-strike risks during trench excavation?

Source: excavation--ericpd

Use HSE’s hierarchy to eliminate or substitute a hazard where practicable, then apply engineering and administrative controls before relying on PPE. Check each chosen control against the actual task and stop when it fails. For excavation, the hierarchy is highly practical. The strongest control may be avoiding the excavation entirely through design, trenchless techniques or rerouting. Where excavation remains necessary, engineered support, physical segregation and competent inspection are more reliable than telling people to be careful. Five-level control hierarchy for excavation: eliminate entry or excavation where practicable; substitute a less intrusive method or route only after checking its hazards; engineer ground support, trench boxes, barriers and service protection; use administrative controls such as permits, briefings, inspection and stop-work decisions; use PPE for residual exposure.

Shoring is an engineering control, while a permit is an administrative control. PPE has a place, such as head protection, high-visibility clothing, protective footwear, eye protection or respiratory protection in contaminated ground, but PPE does not stop a trench collapsing or a gas main igniting. A groundworks team proposes a new service trench. Drawings alone do not establish service position or make the ground safe for entry. ERICPD is a planning crossmap. Its prompts do not add a sixth rung or rank Isolate above engineering. Discipline verifies and sustains every control level. The hierarchy of controls in ISO 45001:2018 comes under Clause 8.1.2 (Eliminating hazards and reducing OH&S risks), which is located within Clause 8 ("Operation"). ESEAP: Elimination, Substitution, Engineering controls, Administrative controls and PPE.

Control order: HSE hierarchy of controls and IOSH hierarchy of control guidance. Illustrative seven-step decision route; this is a SHARE teaching example, not a prescribed legal checklist.

What legal duties apply to excavation work?
What legal duties apply to excavation work?

Source: excavation--legal

Select the construction and confined-space duty by site nation and actual work. GB CDM 2015 and NI CDM 2016 are separate instruments; not every excavation is a confined space. The client, designers, principal contractor and contractors can each influence the pre-dig risk at different stages. In GB, apply CDM 2015; in NI, apply CDM 2016 and local guidance. The practical question is who supplies the information, who tests it, who designs temporary works and who is authorised to release the task. A competent person should inspect support or battering before work and after stability-affecting events. The workface must be safe before entry; legal details and written-report triggers depend on the applicable instrument and circumstances.

How should excavation appear in a risk register?

Source: excavation--risk-register

Excavation risk register entries should identify the actual excavation scenario, not just a generic hazard label. A good risk register separates different excavation scenarios. A shallow landscaping trench, a deep service trench in made ground, a basement excavation, a sewer manhole entry and a trial hole near a high-voltage cable do not have the same controls. A useful planning risk entry identifies the service or ground uncertainty, the design response, the evidence required before release, the person with authority to reject the work, and the trigger for a fresh assessment. A generic “permit to dig in place” entry does not capture those decisions. Risk register actions should be verifiable at the workface.

If the entry says 'support excavation', the evidence should show what support, who designed it, who installed it, who inspected it and what defects were corrected.

How could BuildOut Ltd manage excavation safety?

Source: excavation--business-example

BuildOut Ltd could manage excavation safety through early design review, service control, temporary works, contractor rules, supervision and inspection evidence. Source basis: HSE excavations guidance · HSE HSG47 avoiding danger from underground services · HSENI CDM 2016 guidance. Source basis: HSE excavations guidance · HSE HSG47 avoiding danger from underground services · HSENI CDM 2016 guidance. Source basis: HSE excavations guidance · HSE HSG47 avoiding danger from underground services · HSENI CDM 2016 guidance. BuildOut Ltd (fictional example). a fictional construction and refurbishment contractor delivering groundwork, drainage, foundations, utility diversions, temporary works and occupied-site refurbishments.

BuildOut Ltd should hold a pre-start coordination meeting before plant arrives: compare the latest utility drawings with detection results, decide whether the route can be changed, commission support design if needed, and brief the authorised supervisor on the precise release and stop conditions. BuildOut would treat excavation as a planned construction-risk package, not a last-minute site task. During tender and pre-construction, the project manager would request utility plans, ground information, existing structure information, asbestos and contamination data, drainage records and access constraints. The designer and temporary works coordinator would consider trenchless methods, route changes, reduced depth or design sequencing before excavation is accepted. Before work starts, BuildOut would create an excavation risk assessment, permit to dig and temporary works brief.

A trained supervisor would confirm service plans, CAT and Genny checks, markings, trial holes, edge protection, spoil set-back, plant segregation, access, inspection arrangements and emergency contacts.

Groundworkers and plant operators

would receive a task briefing that explains the actual services, support system and stop-work triggers. During the work, supervisors would inspect the excavation at the start of shift and after rain, collapse, plant impact or change. The SHEQ team would audit evidence quality and speak with workers at the excavation, not just review paperwork. Procurement would only use contractors with evidence of excavation competence, service-avoidance training and suitable equipment. Lessons from service strikes, near misses, water ingress and inspection defects would be reviewed across projects.

What training and competence are needed for excavation work?

Source: excavation--training

Training should be tiered so everyone understands basic danger while supervisors and specialist roles can plan, inspect and control excavation safely. General awareness can be delivered through induction, short briefings or digital learning. It should explain collapse, buried services, exclusion zones, safe access, edge protection and the right to stop when the ground or service information does not match the plan. People directly involved in excavation need practical, task-specific training. Groundworkers, plant operators and supervisors should understand safe digging, service avoidance, CAT and Genny limitations, trial holes, plant segregation, support systems and emergency response. Supervisors, temporary works coordinators and managers need deeper competence.

They should be able to select controls, recognise instability, interpret inspections, manage design change, review contractor competence and know when to involve a structural engineer, temporary works designer, utility operator or confined-space specialist.

How does excavation support IOSH Construction CN1-04 study?

Source: excavation--study

Excavation supports CN1-04 by testing whether learners can identify hazards, select controls and explain safe working in confined spaces. A strong CN1-04 answer should not list 'collapse, services, falls' and stop. It should explain the harm mechanism, the planning duty, the hierarchy of control and the evidence that proves the control is in place. For example, for buried services, mention plans, locating, marking, trial holes, safe digging, competent supervision and stop-work rules. Scenario questions may describe a trench in wet ground, excavation near a boundary wall, workers entering an unsupported trench, plant operating at the edge, diesel equipment in a pit, a missing inspection report or a gas service strike. The answer should identify immediate controls, management failures and longer-term improvements.

How do management frameworks support this topic?

Source: excavation--management-system

HSE’s Plan–Do–Check–Act guidance helps assign ownership, deliver controls, check evidence and improve weak arrangements. Apply the relevant legal duties and task-specific technical evidence separately. Official management guidance: HSE Managing for health and safety (HSG65)

What are the warning signs that excavation safety is failing?

Source: excavation--warning-signs

Warning signs include unsupported sides, missing service checks, spoil near edges, poor access, water ingress, no inspections and weak supervision. Warning signs should be treated as stop-and-fix issues, not audit observations for later. If people are in an unsupported trench, if water is entering, if plant is loading the edge or if services are not confirmed, the risk is immediate. A good supervisor links the visible defect to harm. Spoil near the edge can surcharge the ground and fall onto workers. Missing service records can lead to cable strike, burns, gas explosion or flooding. Missing inspection reports may mean nobody has checked stability after conditions changed.

A decision that changes work
A decision that changes work

Source: excavation--example--excavation-decision

Task Material And Setting: Utility trench in variable ground next to traffic and buried services. People And Prerequisites: Client, designer, contractor, supervisor, plant operator and competent inspector; plans, location evidence and support design are available. Before: Verify ground, service route, water and adjacent structures; install support or designed battering, guarded access and plant separation. During: Repeat locator checks as cover is removed, maintain support and barriers, and inspect before each working shift. Hold Or Stop: Stop entry when support, water, edge loading, atmosphere or an unexpected service makes the excavation uncertain. Completion And Hand Back: Confirm service condition, remove temporary supports by safe sequence, reinstate ground and close permits. Evidence: Service plans and markings, ground/support basis, excavation inspection, briefing, defect action and hand-back record.

Source boundary: HSE material is GB technical guidance; its physical-risk explanation can inform NI practice, but NI duties and regulator authority must be checked against NI instruments and HSENI.

Source tables and records 1
Legal duties linked to buried services

Table ID: buried-services-legal-duties-linked-to-buried-services

Source: https://www.sharehub.ltd/knowledge-hub/buried-services.html

Row 1

Duty or regulation

Health and Safety at Work etc. Act 1974

Jurisdiction

Great Britain

How it applies

General duties to protect employees and others affected by excavation and ground-breaking work.

Practical evidence

Risk assessments, safe systems, training, supervision and contractor control.

Row 2

Duty or regulation

Management of Health and Safety at Work Regulations 1999

Jurisdiction

Great Britain

How it applies

Requires suitable risk assessment, arrangements, coordination and competent assistance.

Practical evidence

Buried-services risk assessment, emergency plan and competence records.

Row 3

Duty or regulation

Construction (Design and Management) Regulations 2015

Jurisdiction

Great Britain

How it applies

Requires construction work to be planned, managed and monitored; Regulation 25 requires suitable steps where underground services create risk.

Practical evidence

Pre-construction information, construction phase plan, permits, surveys and supervision.

Row 4

Duty or regulation

Provision and Use of Work Equipment Regulations 1998

Jurisdiction

Great Britain

How it applies

Applies to excavators, breakers, locators, drills and other work equipment.

Practical evidence

Equipment selection, inspection, maintenance and training records.

Row 5

Duty or regulation

Electricity at Work Regulations 1989

Jurisdiction

Great Britain

How it applies

Requires electrical systems and work near electricity to prevent danger.

Practical evidence

Isolation records, safe digging methods and electrical risk controls.

Row 6

Duty or regulation

Gas Safety (Management) Regulations 1996

Jurisdiction

Great Britain

How it applies

Relevant to gas networks and emergency arrangements.

Practical evidence

Gas emergency response, network-owner contact and work controls.

Row 7

Duty or regulation

Pipelines Safety Regulations 1996

Jurisdiction

Great Britain

How it applies

Protects pipeline integrity and requires third parties not to damage pipelines.

Practical evidence

Pipeline searches, operator consultation and exclusion arrangements.

Row 8

Duty or regulation

Electricity Safety, Quality and Continuity Regulations 2002

Jurisdiction

Great Britain

How it applies

Relevant to electricity network safety and continuity.

Practical evidence

Network-owner information, isolation and reporting routes.

Row 9

Duty or regulation

Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013

Jurisdiction

Great Britain

How it applies

May require reporting of specified injuries, dangerous occurrences or pipeline/electrical incidents.

Practical evidence

Incident assessment, RIDDOR decision record and investigation.

Row 10

Duty or regulation

New Roads and Street Works Act 1991

Jurisdiction

Great Britain

How it applies

Coordinates street works in England and Wales and road works in Scotland, where relevant to the excavation.

Practical evidence

Street works notices, permits, plans and reinstatement records.

Row 11

Column 1

Health and Safety at Work (Northern Ireland) Order 1978

Jurisdiction

Northern Ireland

How it applies

General duty for safe excavation.

Practical evidence

NI safe-system record.

Row 12

Column 1

Management of Health and Safety at Work Regulations (Northern Ireland) 2000

Jurisdiction

Northern Ireland

How it applies

Assess risk and coordinate work.

Practical evidence

NI task assessment.

Row 13

Column 1

CDM Regulations (Northern Ireland) 2016, regulation 24(4)

Jurisdiction

Northern Ireland

How it applies

Take steps to prevent danger from underground services during construction.

Practical evidence

Pre-construction information and dig method.

Row 14

Column 1

Electricity at Work Regulations (Northern Ireland) 1991

Jurisdiction

Northern Ireland

How it applies

Prevent danger from electricity.

Practical evidence

Isolation and utility advice.

Row 15

Column 1

Provision and Use of Work Equipment Regulations (Northern Ireland) 1999

Jurisdiction

Northern Ireland

How it applies

Suitable, checked excavation and locating equipment.

Practical evidence

Locator and plant checks.

Read the complete comparison table
Legal duties linked to buried services
RowDuty or regulationJurisdictionHow it appliesPractical evidenceColumn 1
1Health and Safety at Work etc. Act 1974Great BritainGeneral duties to protect employees and others affected by excavation and ground-breaking work.Risk assessments, safe systems, training, supervision and contractor control.
2Management of Health and Safety at Work Regulations 1999Great BritainRequires suitable risk assessment, arrangements, coordination and competent assistance.Buried-services risk assessment, emergency plan and competence records.
3Construction (Design and Management) Regulations 2015Great BritainRequires construction work to be planned, managed and monitored; Regulation 25 requires suitable steps where underground services create risk.Pre-construction information, construction phase plan, permits, surveys and supervision.
4Provision and Use of Work Equipment Regulations 1998Great BritainApplies to excavators, breakers, locators, drills and other work equipment.Equipment selection, inspection, maintenance and training records.
5Electricity at Work Regulations 1989Great BritainRequires electrical systems and work near electricity to prevent danger.Isolation records, safe digging methods and electrical risk controls.
6Gas Safety (Management) Regulations 1996Great BritainRelevant to gas networks and emergency arrangements.Gas emergency response, network-owner contact and work controls.
7Pipelines Safety Regulations 1996Great BritainProtects pipeline integrity and requires third parties not to damage pipelines.Pipeline searches, operator consultation and exclusion arrangements.
8Electricity Safety, Quality and Continuity Regulations 2002Great BritainRelevant to electricity network safety and continuity.Network-owner information, isolation and reporting routes.
9Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013Great BritainMay require reporting of specified injuries, dangerous occurrences or pipeline/electrical incidents.Incident assessment, RIDDOR decision record and investigation.
10New Roads and Street Works Act 1991Great BritainCoordinates street works in England and Wales and road works in Scotland, where relevant to the excavation.Street works notices, permits, plans and reinstatement records.
11Northern IrelandGeneral duty for safe excavation.NI safe-system record.Health and Safety at Work (Northern Ireland) Order 1978
12Northern IrelandAssess risk and coordinate work.NI task assessment.Management of Health and Safety at Work Regulations (Northern Ireland) 2000
13Northern IrelandTake steps to prevent danger from underground services during construction.Pre-construction information and dig method.CDM Regulations (Northern Ireland) 2016, regulation 24(4)
14Northern IrelandPrevent danger from electricity.Isolation and utility advice.Electricity at Work Regulations (Northern Ireland) 1991
15Northern IrelandSuitable, checked excavation and locating equipment.Locator and plant checks.Provision and Use of Work Equipment Regulations (Northern Ireland) 1999
Buried-services register fields

Table ID: buried-services-buried-services-register-fields

Source: https://www.sharehub.ltd/knowledge-hub/buried-services.html

Row 1

Field

Work activity

What to record

Ground-breaking task and location.

Example

Fence posts along east boundary. See HSE HSG47 avoiding danger from underground services

Row 2

Field

Possible services

What to record

Known, suspected and private services.

Example

LV cable, gas service and telecoms duct. See HSE HSG47 avoiding danger from underground services

Row 3

Field

Information confidence

What to record

How reliable the plans and survey are.

Example

Utility plan old; CAT signal confirmed route. See HSE HSG47 avoiding danger from underground services

Row 4

Field

Controls

What to record

Survey, markings, permit, trial holes and plant limits.

Example

Hand dig within marked corridor. See HSE HSG47 avoiding danger from underground services

Row 5

Field

Owner

What to record

Person accountable for maintaining controls.

Example

Site supervisor or permit issuer. See HSE HSG47 avoiding danger from underground services

Row 6

Field

Evidence

What to record

Records proving control was applied.

Example

Signed permit, scan sheet and briefing. See HSE HSG47 avoiding danger from underground services

Row 7

Field

Stop trigger

What to record

Condition requiring work to pause.

Example

Unexpected duct, gas smell or lost marking. See HSE HSG47 avoiding danger from underground services

Read the complete comparison table
Buried-services register fields
RowFieldWhat to recordExample
1Work activityGround-breaking task and location.Fence posts along east boundary. See HSE HSG47 avoiding danger from underground services
2Possible servicesKnown, suspected and private services.LV cable, gas service and telecoms duct. See HSE HSG47 avoiding danger from underground services
3Information confidenceHow reliable the plans and survey are.Utility plan old; CAT signal confirmed route. See HSE HSG47 avoiding danger from underground services
4ControlsSurvey, markings, permit, trial holes and plant limits.Hand dig within marked corridor. See HSE HSG47 avoiding danger from underground services
5OwnerPerson accountable for maintaining controls.Site supervisor or permit issuer. See HSE HSG47 avoiding danger from underground services
6EvidenceRecords proving control was applied.Signed permit, scan sheet and briefing. See HSE HSG47 avoiding danger from underground services
7Stop triggerCondition requiring work to pause.Unexpected duct, gas smell or lost marking. See HSE HSG47 avoiding danger from underground services
Training Matrix

Table ID: buried-services-training-matrix-decision-table

Source: https://www.sharehub.ltd/knowledge-hub/buried-services.html

Row 1

Column 1

Groundworker

Column 2

Read marks, protect exposed services and stop on uncertainty

Column 3

Observed safe trial hole and unexpected-service drill

Column 4

Site supervisor

Column 5

Task observation and briefing

Column 6

Ground or plan changes

Row 2

Column 1

Locator operator

Column 2

Use modes, check instrument and explain limitations

Column 3

Demonstrate repeated scan and interpretation against trial hole

Column 4

Competent survey lead

Column 5

Equipment and scan record

Column 6

Device, site or ground changes

Row 3

Column 1

Supervisor

Column 2

Issue live permit, set plant limits and utility response

Column 3

Walk through conflicting drawing and locator case

Column 4

Principal contractor

Column 5

Permit and decision log

Column 6

Unexpected asset or method change

Row 4

Column 1

Adviser

Column 2

Check GB/NI law, HSG47 and isolation advice

Column 3

Review service strike investigation and revised controls

Column 4

Independent competent reviewer

Column 5

Source and case review

Column 6

Law or guidance changes

Read the complete comparison table
Training Matrix
RowColumn 1Column 2Column 3Column 4Column 5Column 6
1GroundworkerRead marks, protect exposed services and stop on uncertaintyObserved safe trial hole and unexpected-service drillSite supervisorTask observation and briefingGround or plan changes
2Locator operatorUse modes, check instrument and explain limitationsDemonstrate repeated scan and interpretation against trial holeCompetent survey leadEquipment and scan recordDevice, site or ground changes
3SupervisorIssue live permit, set plant limits and utility responseWalk through conflicting drawing and locator casePrincipal contractorPermit and decision logUnexpected asset or method change
4AdviserCheck GB/NI law, HSG47 and isolation adviceReview service strike investigation and revised controlsIndependent competent reviewerSource and case reviewLaw or guidance changes
Control Hierarchy

Table ID: buried-services-control-hierarchy-decision-table

Source: https://www.sharehub.ltd/knowledge-hub/buried-services.html

Row 1

Column 1

Elimination

Column 2

Eliminate

Column 3

Reroute a foundation, duct or post so the trench avoids the mapped utility corridor; check that new ground is surveyed too.

Column 4

Designer signs the alternative alignment and utility owner checks clashes; hold approval if the new route is not investigated. See HSE HSG47 avoiding danger from underground services

Row 2

Column 1

Substitution

Column 2

Reduce / substitute

Column 3

Use a surface-mounted or shallow engineered alternative instead of intrusive trenching where structural and service needs permit; do not substitute one unknown route for another.

Column 4

Designer verifies load, access and maintenance needs; stop if design basis or private service information is missing. See HSE HSG47 avoiding danger from underground services

Row 3

Column 1

Engineering

Column 2

Isolate / Control

Column 3

Where contact cannot be avoided, arrange verified de-energisation or diversion by the asset owner; use a controlled trial hole and suitable physical separation from plant.

Column 4

Utility owner confirms isolation status; trained operator repeatedly scans and supervisor inspects exposure. Stop on unknown signal or failed isolation. See HSE underground cables; HSE HSG47 avoiding danger from underground services

Row 4

Column 1

Administrative

Column 2

Control / Discipline

Column 3

Maintain current plans, locator marks, a live permit, tool/plant limits, briefing and re-scan checkpoints as ground changes.

Column 4

Supervisor checks marks and permit at each shift/change; stop when they are obscured, stale or inconsistent. See HSE HSG47 avoiding danger from underground services

Row 5

Column 1

PPE

Column 2

PPE

Column 3

Use task-assessed electrical or excavation PPE as a residual measure with fit and condition checks; it cannot make a live cable strike or gas explosion safe.

Column 4

Supervisor verifies selected PPE and replacement; withdraw people when asset identity or energy state is uncertain. See HSE underground cables

Read the complete comparison table
Control Hierarchy
RowColumn 1Column 2Column 3Column 4
1EliminationEliminateReroute a foundation, duct or post so the trench avoids the mapped utility corridor; check that new ground is surveyed too.Designer signs the alternative alignment and utility owner checks clashes; hold approval if the new route is not investigated. See HSE HSG47 avoiding danger from underground services
2SubstitutionReduce / substituteUse a surface-mounted or shallow engineered alternative instead of intrusive trenching where structural and service needs permit; do not substitute one unknown route for another.Designer verifies load, access and maintenance needs; stop if design basis or private service information is missing. See HSE HSG47 avoiding danger from underground services
3EngineeringIsolate / ControlWhere contact cannot be avoided, arrange verified de-energisation or diversion by the asset owner; use a controlled trial hole and suitable physical separation from plant.Utility owner confirms isolation status; trained operator repeatedly scans and supervisor inspects exposure. Stop on unknown signal or failed isolation. See HSE underground cables; HSE HSG47 avoiding danger from underground services
4AdministrativeControl / DisciplineMaintain current plans, locator marks, a live permit, tool/plant limits, briefing and re-scan checkpoints as ground changes.Supervisor checks marks and permit at each shift/change; stop when they are obscured, stale or inconsistent. See HSE HSG47 avoiding danger from underground services
5PPEPPEUse task-assessed electrical or excavation PPE as a residual measure with fit and condition checks; it cannot make a live cable strike or gas explosion safe.Supervisor verifies selected PPE and replacement; withdraw people when asset identity or energy state is uncertain. See HSE underground cables
Hazard Control Map

Table ID: buried-services-hazard-control-map-decision-table

Source: https://www.sharehub.ltd/knowledge-hub/buried-services.html

Row 1

Column 1

Electric cable strike

Column 2

Eliminate: reroute the dig; substitute/reduce: surface solution or different method; engineering/isolate: owner-confirmed de-energisation, physical exposure and plant separation; administrative/control and discipline: plans, trained locator, repeated scan, permit and marks; PPE: residual task protection only.

Column 3

Diversion or isolation may be unavailable; then the designer and utility owner must agree a safe verified exposure method before plant approaches.

Column 4

Supervisor checks scan/trial-hole evidence and owner advice; stop on conflicting signals, unknown depth, damaged sheath or uncertain isolation. See HSE HSG47 avoiding danger from underground services; HSE underground cables

Row 2

Column 1

Gas or other flammable pipe strike

Column 2

Eliminate: route the work outside the pipeline corridor; substitute/reduce: non-intrusive solution where suitable; engineering/isolate: owner-controlled diversion/shutoff and physical separation; administrative/control and discipline: operator consultation, marking, permit and emergency plan; PPE: residual personal protection cannot prevent explosion.

Column 3

Pipeline shutdown may be impracticable; agreement on route, method and exclusion from mechanical impact is then decisive.

Column 4

Pipeline owner and site supervisor check as-found position and method; stop for gas smell, unexpected pipe, failed mark or loss of owner clearance. See HSE HSG47 avoiding danger from underground services; HSE gas pipelines and excavation FAQ

Row 3

Column 1

Water, sewer or pressure-main damage

Column 2

Eliminate: avoid the asset corridor; substitute/reduce: above-ground or less intrusive route; engineering/isolate: owner-controlled depressurisation/diversion, exposure and support; administrative/control and discipline: records, survey, permit and emergency flooding plan; PPE: residual hygiene/splash protection.

Column 3

A non-conductive plastic main may escape cable locating; trial exposure and operator records are needed even with a negative scan.

Column 4

Supervisor and asset owner check location, pressure state and supports; stop on unexplained service, water ingress, unstable trench or contamination. See HSE HSG47 avoiding danger from underground services

Row 4

Column 1

Unknown private or telecom service and collapse

Column 2

Eliminate: avoid excavation or choose a surveyed route; substitute/reduce: surface installation; engineering/isolate: controlled trial hole, protected service and supported excavation; administrative/control and discipline: private-owner enquiry, repeated survey, temporary works and permit; PPE: residual head/hand/eye protection.

Column 3

A negative locator does not establish absence; competent survey and safe excavation remain necessary.

Column 4

Designer/supervisor check as-found services and ground stability; stop if an unknown line appears, ground moves or support cannot be verified. See HSE HSG47 avoiding danger from underground services; HSE excavation safety; HSENI excavation method statement example

Read the complete comparison table
Hazard Control Map
RowColumn 1Column 2Column 3Column 4
1Electric cable strikeEliminate: reroute the dig; substitute/reduce: surface solution or different method; engineering/isolate: owner-confirmed de-energisation, physical exposure and plant separation; administrative/control and discipline: plans, trained locator, repeated scan, permit and marks; PPE: residual task protection only.Diversion or isolation may be unavailable; then the designer and utility owner must agree a safe verified exposure method before plant approaches.Supervisor checks scan/trial-hole evidence and owner advice; stop on conflicting signals, unknown depth, damaged sheath or uncertain isolation. See HSE HSG47 avoiding danger from underground services; HSE underground cables
2Gas or other flammable pipe strikeEliminate: route the work outside the pipeline corridor; substitute/reduce: non-intrusive solution where suitable; engineering/isolate: owner-controlled diversion/shutoff and physical separation; administrative/control and discipline: operator consultation, marking, permit and emergency plan; PPE: residual personal protection cannot prevent explosion.Pipeline shutdown may be impracticable; agreement on route, method and exclusion from mechanical impact is then decisive.Pipeline owner and site supervisor check as-found position and method; stop for gas smell, unexpected pipe, failed mark or loss of owner clearance. See HSE HSG47 avoiding danger from underground services; HSE gas pipelines and excavation FAQ
3Water, sewer or pressure-main damageEliminate: avoid the asset corridor; substitute/reduce: above-ground or less intrusive route; engineering/isolate: owner-controlled depressurisation/diversion, exposure and support; administrative/control and discipline: records, survey, permit and emergency flooding plan; PPE: residual hygiene/splash protection.A non-conductive plastic main may escape cable locating; trial exposure and operator records are needed even with a negative scan.Supervisor and asset owner check location, pressure state and supports; stop on unexplained service, water ingress, unstable trench or contamination. See HSE HSG47 avoiding danger from underground services
4Unknown private or telecom service and collapseEliminate: avoid excavation or choose a surveyed route; substitute/reduce: surface installation; engineering/isolate: controlled trial hole, protected service and supported excavation; administrative/control and discipline: private-owner enquiry, repeated survey, temporary works and permit; PPE: residual head/hand/eye protection.A negative locator does not establish absence; competent survey and safe excavation remain necessary.Designer/supervisor check as-found services and ground stability; stop if an unknown line appears, ground moves or support cannot be verified. See HSE HSG47 avoiding danger from underground services; HSE excavation safety; HSENI excavation method statement example
Official source register

Table ID: buried-services-official-links

Source: https://www.sharehub.ltd/knowledge-hub/buried-services.html

Row 1

Column 1

Legislation

Column 2

Health and Safety at Work etc. Act 1974

Column 3

Great Britain

Column 4

General duties to employees and others.

Row 2

Column 1

Legislation

Column 2

Management of Health and Safety at Work Regulations 1999

Column 3

Great Britain

Column 4

Assessment, prevention, arrangements, competence and emergency planning.

Row 3

Column 1

Legislation

Column 2

Health and Safety at Work (Northern Ireland) Order 1978

Column 3

Northern Ireland

Column 4

General duties in Northern Ireland.

Row 4

Column 1

Legislation

Column 2

Management of Health and Safety at Work Regulations (Northern Ireland) 2000

Column 3

Northern Ireland

Column 4

Northern Ireland management duties.

Row 5

Column 1

HSE guidance

Column 2

HSE HSG65: Managing for health and safety

Column 3

Great Britain

Column 4

Plan, do, check and act management approach.

Row 6

Column 1

HSE guidance

Column 2

HSE five-level hierarchy of control

Column 3

Great Britain

Column 4

Order elimination, substitution and engineering before administrative measures and PPE.

Row 7

Column 1

HSE guidance

Column 2

HSE HSG47 avoiding danger from underground services

Column 3

Great Britain

Column 4

2014 third edition: plan, locate and identify, then excavate safely.

Row 8

Column 1

HSE guidance

Column 2

HSE underground cables

Column 3

Great Britain

Column 4

Plans, trained locator use, repeated scanning, trial holes and safe digging.

Row 9

Column 1

HSE guidance

Column 2

HSE gas pipelines and excavation FAQ

Column 3

Great Britain

Column 4

Operator consultation and precautions near gas pipelines.

Row 10

Column 1

Legislation

Column 2

Construction (Design and Management) Regulations 2015

Column 3

Great Britain

Column 4

GB construction dutyholders and pre-construction information.

Row 11

Column 1

Legislation

Column 2

Construction (Design and Management) Regulations (Northern Ireland) 2016

Column 3

Northern Ireland

Column 4

Separate NI construction dutyholder route.

Row 12

Column 1

Legislation

Column 2

Electricity at Work Regulations (Northern Ireland) 1991

Column 3

Northern Ireland

Column 4

NI precautions near electricity and isolation.

Row 13

Column 1

Legislation

Column 2

NI Provision and Use of Work Equipment Regulations 1999

Column 3

Northern Ireland

Column 4

NI suitability, maintenance and training for equipment.

Row 14

Column 1

HSENI guidance

Column 2

HSENI excavation method statement example

Column 3

Northern Ireland

Column 4

NI planning, utility detection and marking example.

Row 15

Column 1

HSE guidance

Column 2

HSE excavation safety

Column 3

Great Britain

Column 4

Prevent trench collapse and manage excavation stability.

Row 16

Column 1

UK legislation

Column 2

Provision and Use of Work Equipment Regulations 1998

Column 3

Great Britain

Column 4

GB suitability, guarding, maintenance and use of equipment at the task interface.

Row 17

Column 1

UK legislation

Column 2

Electricity at Work Regulations 1989

Column 3

Great Britain

Column 4

GB electrical system safety at equipment, transfer and excavation interfaces.

Row 18

Column 1

UK legislation

Column 2

Gas Safety (Management) Regulations 1996

Column 3

Great Britain

Column 4

GB gas-network management duties where the affected asset falls within scope.

Row 19

Column 1

UK legislation

Column 2

Pipelines Safety Regulations 1996

Column 3

Great Britain

Column 4

GB pipeline safety duties where an underground line meets the defined pipeline scope.

Row 20

Column 1

UK legislation

Column 2

Electricity Safety, Quality and Continuity Regulations 2002

Column 3

Great Britain

Column 4

GB electricity network safety, quality and continuity obligations at service-owner interface.

Row 21

Column 1

UK legislation

Column 2

Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013

Column 3

Great Britain

Column 4

GB specified incident and dangerous-occurrence reporting criteria; not all strikes are reportable.

Row 22

Column 1

UK legislation

Column 2

New Roads and Street Works Act 1991

Column 3

Great Britain

Column 4

GB street-works coordination duties where excavation is in the relevant road or street.

Read the complete comparison table
Official source register
RowColumn 1Column 2Column 3Column 4
1LegislationHealth and Safety at Work etc. Act 1974Great BritainGeneral duties to employees and others.
2LegislationManagement of Health and Safety at Work Regulations 1999Great BritainAssessment, prevention, arrangements, competence and emergency planning.
3LegislationHealth and Safety at Work (Northern Ireland) Order 1978Northern IrelandGeneral duties in Northern Ireland.
4LegislationManagement of Health and Safety at Work Regulations (Northern Ireland) 2000Northern IrelandNorthern Ireland management duties.
5HSE guidanceHSE HSG65: Managing for health and safetyGreat BritainPlan, do, check and act management approach.
6HSE guidanceHSE five-level hierarchy of controlGreat BritainOrder elimination, substitution and engineering before administrative measures and PPE.
7HSE guidanceHSE HSG47 avoiding danger from underground servicesGreat Britain2014 third edition: plan, locate and identify, then excavate safely.
8HSE guidanceHSE underground cablesGreat BritainPlans, trained locator use, repeated scanning, trial holes and safe digging.
9HSE guidanceHSE gas pipelines and excavation FAQGreat BritainOperator consultation and precautions near gas pipelines.
10LegislationConstruction (Design and Management) Regulations 2015Great BritainGB construction dutyholders and pre-construction information.
11LegislationConstruction (Design and Management) Regulations (Northern Ireland) 2016Northern IrelandSeparate NI construction dutyholder route.
12LegislationElectricity at Work Regulations (Northern Ireland) 1991Northern IrelandNI precautions near electricity and isolation.
13LegislationNI Provision and Use of Work Equipment Regulations 1999Northern IrelandNI suitability, maintenance and training for equipment.
14HSENI guidanceHSENI excavation method statement exampleNorthern IrelandNI planning, utility detection and marking example.
15HSE guidanceHSE excavation safetyGreat BritainPrevent trench collapse and manage excavation stability.
16UK legislationProvision and Use of Work Equipment Regulations 1998Great BritainGB suitability, guarding, maintenance and use of equipment at the task interface.
17UK legislationElectricity at Work Regulations 1989Great BritainGB electrical system safety at equipment, transfer and excavation interfaces.
18UK legislationGas Safety (Management) Regulations 1996Great BritainGB gas-network management duties where the affected asset falls within scope.
19UK legislationPipelines Safety Regulations 1996Great BritainGB pipeline safety duties where an underground line meets the defined pipeline scope.
20UK legislationElectricity Safety, Quality and Continuity Regulations 2002Great BritainGB electricity network safety, quality and continuity obligations at service-owner interface.
21UK legislationReporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013Great BritainGB specified incident and dangerous-occurrence reporting criteria; not all strikes are reportable.
22UK legislationNew Roads and Street Works Act 1991Great BritainGB street-works coordination duties where excavation is in the relevant road or street.
Acronyms and terms

Table ID: buried-services-acronyms-and-terms

Source: https://www.sharehub.ltd/knowledge-hub/buried-services.html

Row 1

Acronym or term

CAT

Meaning

Cable Avoidance Tool

Why it matters

Locating device used to detect some buried conductive services.

Row 2

Acronym or term

Genny

Meaning

Signal Generator

Why it matters

Applies a signal to help trace conductive buried services.

Row 3

Acronym or term

GPR

Meaning

Ground Penetrating Radar

Why it matters

Survey technology used to detect some buried features, depending on conditions.

Row 4

Acronym or term

HSG47

Meaning

Avoiding danger from underground services

Why it matters

Main HSE guidance for buried-services work.

Row 5

Acronym or term

CDM

Meaning

Construction (Design and Management) Regulations

Why it matters

Legal framework for planning and managing construction work.

Row 6

Acronym or term

RAMS

Meaning

Risk Assessment and Method Statement

Why it matters

Documents the safe system of work.

Row 7

Acronym or term

LV

Meaning

Low Voltage

Why it matters

Electrical distribution category still capable of fatal injury.

Row 8

Acronym or term

HV

Meaning

High Voltage

Why it matters

Higher-energy electrical systems requiring specialist controls.

Row 9

Acronym or term

GDU

Meaning

Gas Distribution Utility

Why it matters

May own gas mains and services requiring consultation.

Row 10

Acronym or term

RIDDOR

Meaning

Reporting of Injuries, Diseases and Dangerous Occurrences Regulations

Why it matters

Reporting route for specified incidents.

Read the complete comparison table
Acronyms and terms
RowAcronym or termMeaningWhy it matters
1CATCable Avoidance ToolLocating device used to detect some buried conductive services.
2GennySignal GeneratorApplies a signal to help trace conductive buried services.
3GPRGround Penetrating RadarSurvey technology used to detect some buried features, depending on conditions.
4HSG47Avoiding danger from underground servicesMain HSE guidance for buried-services work.
5CDMConstruction (Design and Management) RegulationsLegal framework for planning and managing construction work.
6RAMSRisk Assessment and Method StatementDocuments the safe system of work.
7LVLow VoltageElectrical distribution category still capable of fatal injury.
8HVHigh VoltageHigher-energy electrical systems requiring specialist controls.
9GDUGas Distribution UtilityMay own gas mains and services requiring consultation.
10RIDDORReporting of Injuries, Diseases and Dangerous Occurrences RegulationsReporting route for specified incidents.
Potential downloadable documents

Table ID: buried-services-potential-downloadable-documents

Source: https://www.sharehub.ltd/knowledge-hub/buried-services.html

Row 1

Document

Buried-services planning checklist

Purpose

Check utility searches, private services, survey needs and emergency arrangements.

Owner

Project manager.

Row 2

Document

Permit to dig template

Purpose

Control authorisation, survey evidence, markings, method and hand-back.

Owner

Site manager or permit issuer.

Row 3

Document

CAT and Genny use record

Purpose

Record equipment checks, modes, operator and findings.

Owner

Surveyor or supervisor.

Row 4

Document

Safe digging toolbox talk

Purpose

Brief workers on markings, trial holes, tools, plant limits and stop-work rules.

Owner

Supervisor.

Row 5

Document

Unexpected service report

Purpose

Capture unexpected finds and update records.

Owner

Supervisor or site engineer.

Row 6

Document

Utility strike investigation template

Purpose

Identify planning, survey, permit, supervision and behavioural causes.

Owner

H&S adviser.

Read the complete comparison table
Potential downloadable documents
RowDocumentPurposeOwner
1Buried-services planning checklistCheck utility searches, private services, survey needs and emergency arrangements.Project manager.
2Permit to dig templateControl authorisation, survey evidence, markings, method and hand-back.Site manager or permit issuer.
3CAT and Genny use recordRecord equipment checks, modes, operator and findings.Surveyor or supervisor.
4Safe digging toolbox talkBrief workers on markings, trial holes, tools, plant limits and stop-work rules.Supervisor.
5Unexpected service reportCapture unexpected finds and update records.Supervisor or site engineer.
6Utility strike investigation templateIdentify planning, survey, permit, supervision and behavioural causes.H&S adviser.
Individual editable BuildOut documents

Table ID: buried-services-buildout-documents

Source: https://www.sharehub.ltd/knowledge-hub/buried-services.html

Row 1

Document

Ground-breaking, service verification and excavation inspection procedureBOUK-PRO-EXC · Completed fictional example · v1.0

Purpose

Plan survey and trial holes, support/batter excavations, inspect and coordinate permits.

Editable download

Download DOCXRead preview

Row 2

Document

Excavation, ground and service-strike assessmentBOUK-RA-EXC-01 · Blank editable master · v1.0

Purpose

Evaluate ground stability, services, water, access, plant loads and adjacent structures.

Editable download

Download DOCXRead preview

Row 3

Document

Permit to dig and break groundBOUK-PTW-EXC-01 · Blank editable master · v1.0

Purpose

Confirm plans, locating/survey, trial holes, isolation/interfaces and work limits.

Editable download

Download DOCXRead preview

Row 4

Document

Excavation support, access and backfill RAMSBOUK-RAMS-EXC-01 · Blank editable master · v1.0

Purpose

Set sequence, shoring/battering, edge protection, inspections and safe reinstatement.

Editable download

Download DOCXRead preview

Row 5

Document

Excavation inspection and defect reportBOUK-FRM-EXC-01 · Blank editable master · v1.0

Purpose

Record competent inspections, defects and safe-work restrictions.

Editable download

Download DOCXRead preview

Row 6

Document

Utility detection, trial-hole and as-built recordBOUK-FRM-EXC-02 · Blank editable master · v1.0

Purpose

Capture verified service position, limitations, markings and communicated changes.

Editable download

Download DOCXRead preview

Row 7

Document

Site clearance and shallow groundworks RAMSBOUK-RAMS-EXC-02 · Blank editable master · v1.0

Purpose

Service discovery, vegetation, plant/public separation and changing ground conditions.

Editable download

Download DOCXRead preview

Row 8

Document

Piling and ground-improvement works RAMSBOUK-RAMS-EXC-03 · Blank editable master · v1.0

Purpose

Ground-bearing platforms, rig stability, services, noise/vibration and exclusion interfaces.

Editable download

Download DOCXRead preview

Row 9

Document

Drainage and sanitary installation RAMSBOUK-RAMS-EXC-04 · Blank editable master · v1.0

Purpose

Ground/services, biological exposure, handling, testing and confined-space screening.

Editable download

Download DOCXRead preview

Read the complete comparison table
Individual editable BuildOut documents
RowDocumentPurposeEditable download
1Ground-breaking, service verification and excavation inspection procedureBOUK-PRO-EXC · Completed fictional example · v1.0Plan survey and trial holes, support/batter excavations, inspect and coordinate permits.Download DOCXRead preview
2Excavation, ground and service-strike assessmentBOUK-RA-EXC-01 · Blank editable master · v1.0Evaluate ground stability, services, water, access, plant loads and adjacent structures.Download DOCXRead preview
3Permit to dig and break groundBOUK-PTW-EXC-01 · Blank editable master · v1.0Confirm plans, locating/survey, trial holes, isolation/interfaces and work limits.Download DOCXRead preview
4Excavation support, access and backfill RAMSBOUK-RAMS-EXC-01 · Blank editable master · v1.0Set sequence, shoring/battering, edge protection, inspections and safe reinstatement.Download DOCXRead preview
5Excavation inspection and defect reportBOUK-FRM-EXC-01 · Blank editable master · v1.0Record competent inspections, defects and safe-work restrictions.Download DOCXRead preview
6Utility detection, trial-hole and as-built recordBOUK-FRM-EXC-02 · Blank editable master · v1.0Capture verified service position, limitations, markings and communicated changes.Download DOCXRead preview
7Site clearance and shallow groundworks RAMSBOUK-RAMS-EXC-02 · Blank editable master · v1.0Service discovery, vegetation, plant/public separation and changing ground conditions.Download DOCXRead preview
8Piling and ground-improvement works RAMSBOUK-RAMS-EXC-03 · Blank editable master · v1.0Ground-bearing platforms, rig stability, services, noise/vibration and exclusion interfaces.Download DOCXRead preview
9Drainage and sanitary installation RAMSBOUK-RAMS-EXC-04 · Blank editable master · v1.0Ground/services, biological exposure, handling, testing and confined-space screening.Download DOCXRead preview
Source tables and records 2
Excavation field control model

Table ID: excavation-excavation-field-control-model

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Control area

Decision tree

What good looks like

Decide whether excavation needs design, temporary works, permit-to-dig or specialist support.

Evidence

Excavation decision record.

Row 2

Control area

Collapse and engulfment

What good looks like

Control ground movement, edge loading, support, battering or shoring.

Evidence

Design or inspection record.

Row 3

Control area

Buried services

What good looks like

Locate, mark, expose and protect services before digging.

Evidence

Plans, CAT/Genny checks and trial holes.

Row 4

Control area

Water ingress

What good looks like

Assess groundwater, rain, flooding, pumps and emergency escape.

Evidence

Inspection and weather review.

Row 5

Control area

Plant interface

What good looks like

Separate excavations from plant, spoil, lifting and vehicle movement.

Evidence

Traffic and exclusion plan.

Row 6

Control area

Stop-work triggers

What good looks like

Cracks, water, unsupported sides, unmarked services or changed ground stop the job.

Evidence

Stop-work and review log.

Row 7

Control area

Rescue warning

What good looks like

Do not improvise trench rescue; call emergency services and protect others from entering.

Evidence

Emergency briefing.

Read the complete comparison table
Excavation field control model
RowControl areaWhat good looks likeEvidence
1Decision treeDecide whether excavation needs design, temporary works, permit-to-dig or specialist support.Excavation decision record.
2Collapse and engulfmentControl ground movement, edge loading, support, battering or shoring.Design or inspection record.
3Buried servicesLocate, mark, expose and protect services before digging.Plans, CAT/Genny checks and trial holes.
4Water ingressAssess groundwater, rain, flooding, pumps and emergency escape.Inspection and weather review.
5Plant interfaceSeparate excavations from plant, spoil, lifting and vehicle movement.Traffic and exclusion plan.
6Stop-work triggersCracks, water, unsupported sides, unmarked services or changed ground stop the job.Stop-work and review log.
7Rescue warningDo not improvise trench rescue; call emergency services and protect others from entering.Emergency briefing.
Excavation safety elements

Table ID: excavation-excavation-safety-elements

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Element

Pre-construction information

Why it matters

Ground, services and structural information influence method and risk.

Evidence

Drawings, surveys and site information pack.

Row 2

Element

Risk assessment and method

Why it matters

Controls must match depth, ground and work activity.

Evidence

RAMS, excavation plan and permit to dig.

Row 3

Element

Temporary works

Why it matters

Support, shoring or battering may need design and approval.

Evidence

Design brief, drawings and inspection records.

Row 4

Element

Service avoidance

Why it matters

Cable, gas, water and telecom strikes can kill and disrupt.

Evidence

HSG47-style plan, scan, mark and trial-hole records.

Row 5

Element

Inspection

Why it matters

Conditions change with weather, water, loading and vibration.

Evidence

Competent inspection reports and defect actions.

Row 6

Element

Emergency planning

Why it matters

Collapse, engulfment or service strike needs rapid controlled response.

Evidence

Rescue plan, briefings and emergency contacts.

Read the complete comparison table
Excavation safety elements
RowElementWhy it mattersEvidence
1Pre-construction informationGround, services and structural information influence method and risk.Drawings, surveys and site information pack.
2Risk assessment and methodControls must match depth, ground and work activity.RAMS, excavation plan and permit to dig.
3Temporary worksSupport, shoring or battering may need design and approval.Design brief, drawings and inspection records.
4Service avoidanceCable, gas, water and telecom strikes can kill and disrupt.HSG47-style plan, scan, mark and trial-hole records.
5InspectionConditions change with weather, water, loading and vibration.Competent inspection reports and defect actions.
6Emergency planningCollapse, engulfment or service strike needs rapid controlled response.Rescue plan, briefings and emergency contacts.
Excavation hazards and harm mechanisms

Table ID: excavation-excavation-hazards-and-harm-mechanisms

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Hazard

Collapse

How harm can occur

Ground fails and buries, crushes or traps people.

Control focus

Support, battering, trench boxes or no-entry methods.

Row 2

Hazard

Falling materials

How harm can occur

Spoil, tools, kerbs or materials fall into the excavation.

Control focus

Setback, edge protection and material control.

Row 3

Hazard

Falls

How harm can occur

People fall into the excavation or from access routes.

Control focus

Barriers, covers, crossings and safe access.

Row 4

Hazard

Buried services

How harm can occur

Cables, gas pipes or other services are struck.

Control focus

Plans, locating, marking, trial holes and safe digging.

Row 5

Hazard

Plant and vehicles

How harm can occur

Excavator or vehicle strikes people or overloads the edge.

Control focus

Traffic management, exclusion zones and edge distance.

Row 6

Hazard

Water ingress

How harm can occur

Groundwater or surface water destabilises sides or floods work.

Control focus

Dewatering, drainage, support design and weather review.

Row 7

Hazard

Hazardous atmospheres

How harm can occur

Gases, fumes or low oxygen collect in low areas.

Control focus

Atmosphere assessment, ventilation and confined-space controls.

Row 8

Hazard

Adjacent structures

How harm can occur

Foundations, walls or scaffolds are undermined.

Control focus

Structural assessment and temporary works design.

Read the complete comparison table
Excavation hazards and harm mechanisms
RowHazardHow harm can occurControl focus
1CollapseGround fails and buries, crushes or traps people.Support, battering, trench boxes or no-entry methods.
2Falling materialsSpoil, tools, kerbs or materials fall into the excavation.Setback, edge protection and material control.
3FallsPeople fall into the excavation or from access routes.Barriers, covers, crossings and safe access.
4Buried servicesCables, gas pipes or other services are struck.Plans, locating, marking, trial holes and safe digging.
5Plant and vehiclesExcavator or vehicle strikes people or overloads the edge.Traffic management, exclusion zones and edge distance.
6Water ingressGroundwater or surface water destabilises sides or floods work.Dewatering, drainage, support design and weather review.
7Hazardous atmospheresGases, fumes or low oxygen collect in low areas.Atmosphere assessment, ventilation and confined-space controls.
8Adjacent structuresFoundations, walls or scaffolds are undermined.Structural assessment and temporary works design.
Pre-dig planning checks

Table ID: excavation-pre-dig-planning-checks

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Check

Need to excavate

What to confirm

Can the work be avoided, rerouted or completed by trenchless method?

Record

Design review and method selection.

Row 2

Check

Services

What to confirm

Which utilities, drainage, ducts or unknown services may be present?

Record

Service drawings, surveys and HSG47 plan.

Row 3

Check

Ground

What to confirm

Soil type, made ground, water, contamination and previous disturbance.

Record

Ground information and site observations.

Row 4

Check

Structures

What to confirm

Nearby walls, roads, scaffolds, foundations and trees.

Record

Structural review and exclusion distances.

Row 5

Check

Support

What to confirm

Shoring, trench box, battering, benching or no-entry method.

Record

Temporary works design and approval.

Row 6

Check

People and plant

What to confirm

Access, segregation, edge loads and public interface.

Record

Traffic plan and induction briefing.

Row 7

Check

Emergency

What to confirm

Collapse, service strike, flooding or atmosphere response.

Record

Rescue plan and emergency contacts.

Read the complete comparison table
Pre-dig planning checks
RowCheckWhat to confirmRecord
1Need to excavateCan the work be avoided, rerouted or completed by trenchless method?Design review and method selection.
2ServicesWhich utilities, drainage, ducts or unknown services may be present?Service drawings, surveys and HSG47 plan.
3GroundSoil type, made ground, water, contamination and previous disturbance.Ground information and site observations.
4StructuresNearby walls, roads, scaffolds, foundations and trees.Structural review and exclusion distances.
5SupportShoring, trench box, battering, benching or no-entry method.Temporary works design and approval.
6People and plantAccess, segregation, edge loads and public interface.Traffic plan and induction briefing.
7EmergencyCollapse, service strike, flooding or atmosphere response.Rescue plan and emergency contacts.
Pre Dig Release

Table ID: excavation-pre-dig-release

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Decision

Need to excavate

Evidence before release

Design review of trenchless, rerouting and no-entry options.

Hold or recheck trigger

Method or location changes.

Row 2

Decision

Ground and structures

Evidence before release

Ground information, temporary works basis and adjacent-load review.

Hold or recheck trigger

Unknown fill, movement, water or new surcharge.

Row 3

Decision

Buried services

Evidence before release

Current plans, competent locating survey, markings and safe exposure method.

Hold or recheck trigger

Plans and detection disagree or an unexpected service appears.

Row 4

Decision

Workface interface

Evidence before release

Plant route, edge protection, access, spoil location and public segregation.

Hold or recheck trigger

Traffic, sequence or neighbouring work changes.

Row 5

Decision

Release and hand-back

Evidence before release

Named supervisor, competent inspection, worker briefing and emergency response.

Hold or recheck trigger

Defect, weather event, shift change or lost critical control.

Read the complete comparison table
Pre Dig Release
RowDecisionEvidence before releaseHold or recheck trigger
1Need to excavateDesign review of trenchless, rerouting and no-entry options.Method or location changes.
2Ground and structuresGround information, temporary works basis and adjacent-load review.Unknown fill, movement, water or new surcharge.
3Buried servicesCurrent plans, competent locating survey, markings and safe exposure method.Plans and detection disagree or an unexpected service appears.
4Workface interfacePlant route, edge protection, access, spoil location and public segregation.Traffic, sequence or neighbouring work changes.
5Release and hand-backNamed supervisor, competent inspection, worker briefing and emergency response.Defect, weather event, shift change or lost critical control.
Collapse control options

Table ID: excavation-collapse-control-options

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Control

Avoid entry

When it may be used

Inspection, connection or installation can be done from outside.

Key checks

Tooling, visibility and rescue implications.

Row 2

Control

Trench box

When it may be used

Linear trenches where box movement is practical.

Key checks

Correct size, installation, ground contact and access.

Row 3

Control

Shoring

When it may be used

Where sides need direct support.

Key checks

Competent design, installation and inspection.

Row 4

Control

Battering

When it may be used

Where space allows sides to be sloped back.

Key checks

Safe angle, soil type and weather effects.

Row 5

Control

Benching

When it may be used

Where stepped excavation controls face height.

Key checks

Geotechnical suitability and edge stability.

Row 6

Control

Temporary works design

When it may be used

Complex depth, poor ground, adjacent structures or unusual loading.

Key checks

Design brief, approval and inspection regime.

Read the complete comparison table
Collapse control options
RowControlWhen it may be usedKey checks
1Avoid entryInspection, connection or installation can be done from outside.Tooling, visibility and rescue implications.
2Trench boxLinear trenches where box movement is practical.Correct size, installation, ground contact and access.
3ShoringWhere sides need direct support.Competent design, installation and inspection.
4BatteringWhere space allows sides to be sloped back.Safe angle, soil type and weather effects.
5BenchingWhere stepped excavation controls face height.Geotechnical suitability and edge stability.
6Temporary works designComplex depth, poor ground, adjacent structures or unusual loading.Design brief, approval and inspection regime.
Buried service controls

Table ID: excavation-buried-service-controls

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Control

Service plans

Good practice

Obtain and review current utility information before work.

Evidence

Plans and service enquiry records.

Row 2

Control

Site scan

Good practice

Use suitable locating devices repeatedly as work progresses.

Evidence

CAT and Genny check record.

Row 3

Control

Marking

Good practice

Mark service routes clearly on the ground.

Evidence

Photographs and permit sketch.

Row 4

Control

Trial holes

Good practice

Expose services carefully to confirm location.

Evidence

Trial-hole record and revised markings.

Row 5

Control

Safe digging

Good practice

Use hand tools or controlled methods near services.

Evidence

Briefing and supervisor checks.

Row 6

Control

Stop-work trigger

Good practice

Stop when plans do not match reality or an unknown service appears.

Evidence

Change log and revised permit.

Read the complete comparison table
Buried service controls
RowControlGood practiceEvidence
1Service plansObtain and review current utility information before work.Plans and service enquiry records.
2Site scanUse suitable locating devices repeatedly as work progresses.CAT and Genny check record.
3MarkingMark service routes clearly on the ground.Photographs and permit sketch.
4Trial holesExpose services carefully to confirm location.Trial-hole record and revised markings.
5Safe diggingUse hand tools or controlled methods near services.Briefing and supervisor checks.
6Stop-work triggerStop when plans do not match reality or an unknown service appears.Change log and revised permit.
Edge and material controls

Table ID: excavation-edge-and-material-controls

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Issue

Open edges

Control

Guardrails, barriers or covers.

Inspection point

Continuous protection and no gaps.

Row 2

Issue

Access

Control

Suitable secured ladders, steps or ramps.

Inspection point

Stable base and safe landing.

Row 3

Issue

Crossings

Control

Designed crossing points with handrails where needed.

Inspection point

Condition, width and load rating.

Row 4

Issue

Spoil

Control

Spoil set back from edges and controlled.

Inspection point

No surcharge or loose material falling.

Row 5

Issue

Plant loads

Control

Plant and vehicles kept away from edge.

Inspection point

Exclusion distances and traffic plan.

Row 6

Issue

Lighting

Control

Adequate lighting for routes and edges.

Inspection point

Night or poor-weather checks.

Read the complete comparison table
Edge and material controls
RowIssueControlInspection point
1Open edgesGuardrails, barriers or covers.Continuous protection and no gaps.
2AccessSuitable secured ladders, steps or ramps.Stable base and safe landing.
3CrossingsDesigned crossing points with handrails where needed.Condition, width and load rating.
4SpoilSpoil set back from edges and controlled.No surcharge or loose material falling.
5Plant loadsPlant and vehicles kept away from edge.Exclusion distances and traffic plan.
6LightingAdequate lighting for routes and edges.Night or poor-weather checks.
Water and ground risk controls

Table ID: excavation-water-and-ground-risk-controls

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Condition

Rainfall

Risk

Softens or erodes sides and increases collapse risk.

Control

Weather trigger inspection and support review.

Row 2

Condition

Groundwater

Risk

Causes inflow and loading on support.

Control

Dewatering design and monitored pumping.

Row 3

Condition

Surface water

Risk

Runs into excavation and undermines edges.

Control

Drainage, bunding and diversion.

Row 4

Condition

Made ground

Risk

Unpredictable strength and contamination.

Control

Ground investigation and conservative support.

Row 5

Condition

Vibration

Risk

Destabilises sides and adjacent structures.

Control

Plant exclusion and monitoring.

Row 6

Condition

Adjacent structures

Risk

Excavation may undermine walls, roads or scaffolds.

Control

Structural assessment and temporary works.

Read the complete comparison table
Water and ground risk controls
RowConditionRiskControl
1RainfallSoftens or erodes sides and increases collapse risk.Weather trigger inspection and support review.
2GroundwaterCauses inflow and loading on support.Dewatering design and monitored pumping.
3Surface waterRuns into excavation and undermines edges.Drainage, bunding and diversion.
4Made groundUnpredictable strength and contamination.Ground investigation and conservative support.
5VibrationDestabilises sides and adjacent structures.Plant exclusion and monitoring.
6Adjacent structuresExcavation may undermine walls, roads or scaffolds.Structural assessment and temporary works.
Atmosphere and confined-space controls

Table ID: excavation-atmosphere-and-confined-space-controls

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Risk

Low oxygen

How it can arise

Displacement by gases or poor ventilation.

Control

Atmosphere assessment and ventilation.

Row 2

Risk

Toxic gas

How it can arise

Sewer gases, contamination or industrial residues.

Control

Testing, isolation and specialist advice.

Row 3

Risk

Exhaust fumes

How it can arise

Plant, generators or compressors near excavation.

Control

Keep engines away and duct fumes safely.

Row 4

Risk

Flammable gas

How it can arise

Gas service damage or contaminated ground.

Control

Stop work, isolate sources and emergency response.

Row 5

Risk

Flooding

How it can arise

Water ingress in restricted access area.

Control

Rescue plan and water control.

Row 6

Risk

Engulfment

How it can arise

Loose material or collapse traps people.

Control

Support and no-entry methods.

Read the complete comparison table
Atmosphere and confined-space controls
RowRiskHow it can ariseControl
1Low oxygenDisplacement by gases or poor ventilation.Atmosphere assessment and ventilation.
2Toxic gasSewer gases, contamination or industrial residues.Testing, isolation and specialist advice.
3Exhaust fumesPlant, generators or compressors near excavation.Keep engines away and duct fumes safely.
4Flammable gasGas service damage or contaminated ground.Stop work, isolate sources and emergency response.
5FloodingWater ingress in restricted access area.Rescue plan and water control.
6EngulfmentLoose material or collapse traps people.Support and no-entry methods.
Plant interface controls

Table ID: excavation-plant-interface-controls

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Interface

Slew radius

Risk

People struck by excavator or bucket.

Control

Exclusion zone and banksman where needed.

Row 2

Interface

Edge loading

Risk

Vehicle weight triggers collapse.

Control

Setback distances and route planning.

Row 3

Interface

Spoil movement

Risk

Falling material or unstable edge.

Control

Designated spoil areas.

Row 4

Interface

Reversing

Risk

Groundworkers struck by vehicles.

Control

One-way routes, reversing controls and visibility.

Row 5

Interface

Service exposure

Risk

Bucket damages cables or pipes.

Control

Hand dig or controlled methods near services.

Row 6

Interface

Emergency access

Risk

Plant blocks rescue or emergency routes.

Control

Access route kept clear.

Read the complete comparison table
Plant interface controls
RowInterfaceRiskControl
1Slew radiusPeople struck by excavator or bucket.Exclusion zone and banksman where needed.
2Edge loadingVehicle weight triggers collapse.Setback distances and route planning.
3Spoil movementFalling material or unstable edge.Designated spoil areas.
4ReversingGroundworkers struck by vehicles.One-way routes, reversing controls and visibility.
5Service exposureBucket damages cables or pipes.Hand dig or controlled methods near services.
6Emergency accessPlant blocks rescue or emergency routes.Access route kept clear.
Excavation inspection triggers

Table ID: excavation-excavation-inspection-triggers

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

When

Start of shift

What to inspect

Support, sides, edges, access, water, spoil, services and barriers.

Action

Confirm safe before work starts.

Row 2

When

After rain or weather change

What to inspect

Water ingress, erosion, softening and support loading.

Action

Reassess controls.

Row 3

When

After collapse or fall of earth

What to inspect

Stability, support damage and need for redesign.

Action

Stop work until safe.

Row 4

When

After plant impact

What to inspect

Support, edge loading and service damage.

Action

Inspect and repair.

Row 5

When

After design or method change

What to inspect

Whether controls still match the work.

Action

Revise RAMS and permit.

Row 6

When

Before re-entry

What to inspect

Whether previous defects have been corrected.

Action

Record close-out.

Read the complete comparison table
Excavation inspection triggers
RowWhenWhat to inspectAction
1Start of shiftSupport, sides, edges, access, water, spoil, services and barriers.Confirm safe before work starts.
2After rain or weather changeWater ingress, erosion, softening and support loading.Reassess controls.
3After collapse or fall of earthStability, support damage and need for redesign.Stop work until safe.
4After plant impactSupport, edge loading and service damage.Inspect and repair.
5After design or method changeWhether controls still match the work.Revise RAMS and permit.
6Before re-entryWhether previous defects have been corrected.Record close-out.
Emergency scenarios

Table ID: excavation-emergency-scenarios

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Scenario

Collapse

Immediate priority

Do not create additional casualties.

Planning need

Rescue plan, emergency services access and support assessment.

Row 2

Scenario

Gas strike

Immediate priority

Stop work, evacuate and control ignition.

Planning need

Utility contact and exclusion zone.

Row 3

Scenario

Cable strike

Immediate priority

Keep clear of live danger and seek emergency help.

Planning need

Electrical emergency briefing and isolation route.

Row 4

Scenario

Flooding

Immediate priority

Evacuate and prevent entry.

Planning need

Water monitoring and pump contingency.

Row 5

Scenario

Hazardous atmosphere

Immediate priority

Do not enter without controls.

Planning need

Atmosphere testing, rescue and ventilation plan.

Row 6

Scenario

Public interface

Immediate priority

Protect public and secure the area.

Planning need

Barriers, signage and communication plan.

Read the complete comparison table
Emergency scenarios
RowScenarioImmediate priorityPlanning need
1CollapseDo not create additional casualties.Rescue plan, emergency services access and support assessment.
2Gas strikeStop work, evacuate and control ignition.Utility contact and exclusion zone.
3Cable strikeKeep clear of live danger and seek emergency help.Electrical emergency briefing and isolation route.
4FloodingEvacuate and prevent entry.Water monitoring and pump contingency.
5Hazardous atmosphereDo not enter without controls.Atmosphere testing, rescue and ventilation plan.
6Public interfaceProtect public and secure the area.Barriers, signage and communication plan.
Source comparison

Table ID: excavation-ericpd-controls-for-excavation

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Column 1

Eliminate

Column 2

Redesign the route or use suitable existing ducts so the excavation beside live services is unnecessary.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Task owner verifies that the proposed change removes the named hazardous step, including foreseeable cleaning, maintenance and work transferred elsewhere.

Column 4

If the hazardous step remains, keep it within the task assessment and select the stronger feasible remaining controls.

Row 2

Column 1

Reduce, including substitution

Column 2

Assess a suitable trenchless or lower-disturbance installation method; confirm launch pits, service crossings and ground risks before accepting it.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Competent task/process owner validates suitability, compatibility and new hazards against the actual operating requirements before the alternative is adopted.

Column 4

Reject an alternative if its performance is unproved or its new hazards are unresolved.

Row 3

Column 1

Isolate

Column 2

Have relevant services made safe by their owners where practicable and segregate plant, pedestrians and exposed excavation edges.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Supervisor checks the actual boundary, affected people and connected work; verify separation or isolation before allowing access.

Column 4

Hold or stop for unidentified service, ground movement, water ingress, damaged support or changed plant loading.

Row 4

Column 1

Control: physical safeguards

Column 2

Provide designed support or battering, safe access and appropriate service-location and exposure methods before people enter.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Competent equipment/process owner checks service information and location checks, ground/support design, edge loads, access and current inspection.

Column 4

Hold or stop for unidentified service, ground movement, water ingress, damaged support or changed plant loading.

Row 5

Column 1

Control: work method and response

Column 2

Combine current plans, locating, marking and safe excavation in the digging plan; agree permits, inspections and immediate action for an unexpected service.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Supervisor confirms the work limits, competent cover, communication and stop/restart authority with the people doing this activity.

Column 4

Hold work when the agreed limits, competent cover or effective communication cannot be maintained.

Row 6

Column 1

PPE

Column 2

Select head, foot, visibility and other assessed protection. PPE cannot protect someone from a trench collapse or uncontrolled service strike.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Assessor confirms whether personal protection is needed and checks suitability, condition, compatibility and any required fit evidence.

Column 4

Do not use unsuitable protection or rely on PPE to continue after an essential source control fails.

Row 7

Column 1

Discipline

Column 2

Inspect at the required times and after changes affecting stability; keep people out until defects, water or service uncertainty are resolved.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Release only after competent excavation owner accepts the revised safe method and inspection. Retain verification and unresolved restrictions at handover.

Column 4

Keep the task on hold until required reinstatement evidence and unresolved defects are accepted by the responsible owner.

Read the complete comparison table
Source comparison
RowColumn 1Column 2Column 3Column 4
1EliminateRedesign the route or use suitable existing ducts so the excavation beside live services is unnecessary.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceTask owner verifies that the proposed change removes the named hazardous step, including foreseeable cleaning, maintenance and work transferred elsewhere.If the hazardous step remains, keep it within the task assessment and select the stronger feasible remaining controls.
2Reduce, including substitutionAssess a suitable trenchless or lower-disturbance installation method; confirm launch pits, service crossings and ground risks before accepting it.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceCompetent task/process owner validates suitability, compatibility and new hazards against the actual operating requirements before the alternative is adopted.Reject an alternative if its performance is unproved or its new hazards are unresolved.
3IsolateHave relevant services made safe by their owners where practicable and segregate plant, pedestrians and exposed excavation edges.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceSupervisor checks the actual boundary, affected people and connected work; verify separation or isolation before allowing access.Hold or stop for unidentified service, ground movement, water ingress, damaged support or changed plant loading.
4Control: physical safeguardsProvide designed support or battering, safe access and appropriate service-location and exposure methods before people enter.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceCompetent equipment/process owner checks service information and location checks, ground/support design, edge loads, access and current inspection.Hold or stop for unidentified service, ground movement, water ingress, damaged support or changed plant loading.
5Control: work method and responseCombine current plans, locating, marking and safe excavation in the digging plan; agree permits, inspections and immediate action for an unexpected service.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceSupervisor confirms the work limits, competent cover, communication and stop/restart authority with the people doing this activity.Hold work when the agreed limits, competent cover or effective communication cannot be maintained.
6PPESelect head, foot, visibility and other assessed protection. PPE cannot protect someone from a trench collapse or uncontrolled service strike.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceAssessor confirms whether personal protection is needed and checks suitability, condition, compatibility and any required fit evidence.Do not use unsuitable protection or rely on PPE to continue after an essential source control fails.
7DisciplineInspect at the required times and after changes affecting stability; keep people out until defects, water or service uncertainty are resolved.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceRelease only after competent excavation owner accepts the revised safe method and inspection. Retain verification and unresolved restrictions at handover.Keep the task on hold until required reinstatement evidence and unresolved defects are accepted by the responsible owner.
Source comparison

Table ID: excavation-ericpd-controls-for-excavation-eseap

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Column 1

Elimination

Column 2

Redesign the route or use suitable existing ducts so the excavation beside live services is unnecessary.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Task owner verifies that the proposed change removes the named hazardous step, including foreseeable cleaning, maintenance and work transferred elsewhere.

Column 4

If the hazardous step remains, keep it within the task assessment and select the stronger feasible remaining controls.

Row 2

Column 1

Substitution

Column 2

Assess a suitable trenchless or lower-disturbance installation method; confirm launch pits, service crossings and ground risks before accepting it.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Competent task/process owner validates suitability, compatibility and new hazards against the actual operating requirements before the alternative is adopted.

Column 4

Reject an alternative if its performance is unproved or its new hazards are unresolved.

Row 3

Column 1

Engineering controls

Column 2

Have relevant services made safe by their owners where practicable and segregate plant, pedestrians and exposed excavation edges.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Supervisor checks the actual boundary, affected people and connected work; verify separation or isolation before allowing access.

Column 4

Hold or stop for unidentified service, ground movement, water ingress, damaged support or changed plant loading.

Row 4

Column 1

Engineering controls

Column 2

Provide designed support or battering, safe access and appropriate service-location and exposure methods before people enter.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Competent equipment/process owner checks service information and location checks, ground/support design, edge loads, access and current inspection.

Column 4

Hold or stop for unidentified service, ground movement, water ingress, damaged support or changed plant loading.

Row 5

Column 1

Administrative controls

Column 2

Combine current plans, locating, marking and safe excavation in the digging plan; agree permits, inspections and immediate action for an unexpected service.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Supervisor confirms the work limits, competent cover, communication and stop/restart authority with the people doing this activity.

Column 4

Hold work when the agreed limits, competent cover or effective communication cannot be maintained.

Row 6

Column 1

PPE

Column 2

Select head, foot, visibility and other assessed protection. PPE cannot protect someone from a trench collapse or uncontrolled service strike.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Assessor confirms whether personal protection is needed and checks suitability, condition, compatibility and any required fit evidence.

Column 4

Do not use unsuitable protection or rely on PPE to continue after an essential source control fails.

Row 7

Column 1

Administrative controls

Column 2

Inspect at the required times and after changes affecting stability; keep people out until defects, water or service uncertainty are resolved.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidance

Column 3

Release only after competent excavation owner accepts the revised safe method and inspection. Retain verification and unresolved restrictions at handover.

Column 4

Keep the task on hold until required reinstatement evidence and unresolved defects are accepted by the responsible owner.

Read the complete comparison table
Source comparison
RowColumn 1Column 2Column 3Column 4
1EliminationRedesign the route or use suitable existing ducts so the excavation beside live services is unnecessary.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceTask owner verifies that the proposed change removes the named hazardous step, including foreseeable cleaning, maintenance and work transferred elsewhere.If the hazardous step remains, keep it within the task assessment and select the stronger feasible remaining controls.
2SubstitutionAssess a suitable trenchless or lower-disturbance installation method; confirm launch pits, service crossings and ground risks before accepting it.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceCompetent task/process owner validates suitability, compatibility and new hazards against the actual operating requirements before the alternative is adopted.Reject an alternative if its performance is unproved or its new hazards are unresolved.
3Engineering controlsHave relevant services made safe by their owners where practicable and segregate plant, pedestrians and exposed excavation edges.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceSupervisor checks the actual boundary, affected people and connected work; verify separation or isolation before allowing access.Hold or stop for unidentified service, ground movement, water ingress, damaged support or changed plant loading.
4Engineering controlsProvide designed support or battering, safe access and appropriate service-location and exposure methods before people enter.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceCompetent equipment/process owner checks service information and location checks, ground/support design, edge loads, access and current inspection.Hold or stop for unidentified service, ground movement, water ingress, damaged support or changed plant loading.
5Administrative controlsCombine current plans, locating, marking and safe excavation in the digging plan; agree permits, inspections and immediate action for an unexpected service.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceSupervisor confirms the work limits, competent cover, communication and stop/restart authority with the people doing this activity.Hold work when the agreed limits, competent cover or effective communication cannot be maintained.
6PPESelect head, foot, visibility and other assessed protection. PPE cannot protect someone from a trench collapse or uncontrolled service strike.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceAssessor confirms whether personal protection is needed and checks suitability, condition, compatibility and any required fit evidence.Do not use unsuitable protection or rely on PPE to continue after an essential source control fails.
7Administrative controlsInspect at the required times and after changes affecting stability; keep people out until defects, water or service uncertainty are resolved.Basis: HSE HSG47 avoiding danger from underground services · HSE excavations guidanceRelease only after competent excavation owner accepts the revised safe method and inspection. Retain verification and unresolved restrictions at handover.Keep the task on hold until required reinstatement evidence and unresolved defects are accepted by the responsible owner.
Source tables and records 3
Illustrative seven-step decision route

Table ID: excavation-worked-route

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Step

Eliminate

Action

Consider trenchless construction or route change before digging.

Check

Designer checks service and ground interfaces.

Failure mode

A bore can still strike a buried service.

Hold point

Do not assume trenchless is hazard-free.

Row 2

Step

Reduce

Action

Minimise open length and exposure time with a staged sequence.

Check

Planner verifies support and access for each stage.

Failure mode

A short unsupported pit can still collapse.

Hold point

No entry before stable support.

Row 3

Step

Isolate

Action

Keep plant, traffic and spoil away from excavation edges.

Check

Supervisor checks barriers and set-back each shift.

Failure mode

Edge surcharge can defeat support.

Hold point

Stop plant near a suspect edge.

Row 4

Step

Engineer

Action

Install suitable trench box, shoring or designed battering.

Check

Competent person checks design and installation.

Failure mode

Changing soil or water can invalidate it.

Hold point

No entry until support is adequate.

Row 5

Step

Control

Action

Locate services using plans, detection and safe digging.

Check

Crew repeats locator checks as cover is removed.

Failure mode

Plans can be inaccurate or incomplete.

Hold point

Stop on an unexpected service.

Row 6

Step

Protect

Action

Provide guarded edges, access and appropriate PPE for residual hazards.

Check

Supervisor checks barriers, ladder and falling-material controls.

Failure mode

PPE cannot prevent collapse.

Hold point

Close access if edge protection fails.

Row 7

Step

Assure

Action

Inspect before work and after stability-affecting events.

Check

Competent person records findings and defect closure.

Failure mode

Paper checks miss a changed face.

Hold point

No work until excavation is safe.

Read the complete comparison table
Illustrative seven-step decision route
RowStepActionCheckFailure modeHold point
1EliminateConsider trenchless construction or route change before digging.Designer checks service and ground interfaces.A bore can still strike a buried service.Do not assume trenchless is hazard-free.
2ReduceMinimise open length and exposure time with a staged sequence.Planner verifies support and access for each stage.A short unsupported pit can still collapse.No entry before stable support.
3IsolateKeep plant, traffic and spoil away from excavation edges.Supervisor checks barriers and set-back each shift.Edge surcharge can defeat support.Stop plant near a suspect edge.
4EngineerInstall suitable trench box, shoring or designed battering.Competent person checks design and installation.Changing soil or water can invalidate it.No entry until support is adequate.
5ControlLocate services using plans, detection and safe digging.Crew repeats locator checks as cover is removed.Plans can be inaccurate or incomplete.Stop on an unexpected service.
6ProtectProvide guarded edges, access and appropriate PPE for residual hazards.Supervisor checks barriers, ladder and falling-material controls.PPE cannot prevent collapse.Close access if edge protection fails.
7AssureInspect before work and after stability-affecting events.Competent person records findings and defect closure.Paper checks miss a changed face.No work until excavation is safe.
Where / Instrument or rule

Table ID: excavation-jurisdiction-law

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Where

Great Britain

Instrument or rule

Construction (Design and Management) Regulations 2015

Practical boundary

GB construction duties, excavation precautions and inspection.

Row 2

Where

Northern Ireland

Instrument or rule

Construction (Design and Management) Regulations (Northern Ireland) 2016

Practical boundary

NI construction duties, excavation precautions and inspection.

Row 3

Where

Great Britain

Instrument or rule

Health and Safety at Work etc. Act 1974

Practical boundary

GB general work-safety duties

Row 4

Where

Northern Ireland

Instrument or rule

Health and Safety at Work (Northern Ireland) Order 1978

Practical boundary

NI general work-safety duties

Row 5

Where

Great Britain

Instrument or rule

Management of Health and Safety at Work Regulations 1999

Practical boundary

GB risk assessment and prevention arrangements

Row 6

Where

Northern Ireland

Instrument or rule

Management of Health and Safety at Work Regulations (Northern Ireland) 2000

Practical boundary

NI risk assessment and prevention arrangements

Row 7

Where

Great Britain

Instrument or rule

Confined Spaces Regulations 1997

Practical boundary

GB confined-space avoidance, safe work and rescue where applicable.

Row 8

Where

Northern Ireland

Instrument or rule

Confined Spaces Regulations (Northern Ireland) 1999

Practical boundary

NI confined-space avoidance, safe work and rescue where applicable.

Read the complete comparison table
Where / Instrument or rule
RowWhereInstrument or rulePractical boundary
1Great BritainConstruction (Design and Management) Regulations 2015GB construction duties, excavation precautions and inspection.
2Northern IrelandConstruction (Design and Management) Regulations (Northern Ireland) 2016NI construction duties, excavation precautions and inspection.
3Great BritainHealth and Safety at Work etc. Act 1974GB general work-safety duties
4Northern IrelandHealth and Safety at Work (Northern Ireland) Order 1978NI general work-safety duties
5Great BritainManagement of Health and Safety at Work Regulations 1999GB risk assessment and prevention arrangements
6Northern IrelandManagement of Health and Safety at Work Regulations (Northern Ireland) 2000NI risk assessment and prevention arrangements
7Great BritainConfined Spaces Regulations 1997GB confined-space avoidance, safe work and rescue where applicable.
8Northern IrelandConfined Spaces Regulations (Northern Ireland) 1999NI confined-space avoidance, safe work and rescue where applicable.
Excavation risk register fields

Table ID: excavation-excavation-risk-register-fields

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Field

Scenario

What to record

Specific excavation activity and location.

Example

2 metre drainage trench near live services.

Row 2

Field

Ground and depth

What to record

Soil, made ground, water, depth and duration.

Example

Made ground, 2 metres, groundwater expected.

Row 3

Field

Services

What to record

Known, suspected and verified services.

Example

Gas main and LV cable shown on plans.

Row 4

Field

Controls

What to record

Support, barriers, access, plant segregation and safe digging.

Example

Trench box, CAT scan, trial holes and barriers.

Row 5

Field

Owner

What to record

Person responsible for control implementation.

Example

Site manager and temporary works supervisor.

Row 6

Field

Inspection

What to record

Competent inspection frequency and triggers.

Example

Start of shift and after rain.

Row 7

Field

Emergency

What to record

Specific response arrangements.

Example

Service strike and collapse plan briefed.

Read the complete comparison table
Excavation risk register fields
RowFieldWhat to recordExample
1ScenarioSpecific excavation activity and location.2 metre drainage trench near live services.
2Ground and depthSoil, made ground, water, depth and duration.Made ground, 2 metres, groundwater expected.
3ServicesKnown, suspected and verified services.Gas main and LV cable shown on plans.
4ControlsSupport, barriers, access, plant segregation and safe digging.Trench box, CAT scan, trial holes and barriers.
5OwnerPerson responsible for control implementation.Site manager and temporary works supervisor.
6InspectionCompetent inspection frequency and triggers.Start of shift and after rain.
7EmergencySpecific response arrangements.Service strike and collapse plan briefed.
BuildOut Ltd excavation controls

Table ID: excavation-buildout-ltd-excavation-controls

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Management activity

Assess and analyse

How buildout would apply it

Review ground, services, structures, water, public interface and confined-space risk.

Evidence produced

Pre-construction information review and excavation risk register.

Row 2

Management activity

Plan and design

How buildout would apply it

Select trenchless option, support, battering or trench box where appropriate.

Evidence produced

Temporary works design brief and method statement.

Row 3

Management activity

Train and brief

How buildout would apply it

Train supervisors in inspection, CAT and Genny limits, permit to dig and emergency response.

Evidence produced

Training matrix and briefing records.

Row 4

Management activity

Implement

How buildout would apply it

Use permits, service marking, trial holes, barriers, access and plant segregation.

Evidence produced

Permit to dig, photos and supervisor checks.

Row 5

Management activity

Check and audit

How buildout would apply it

Inspect daily and audit against HSG47 and HSE excavation guidance.

Evidence produced

Inspection reports, audit findings and action close-out.

Row 6

Management activity

Contractor management

How buildout would apply it

Pre-qualify groundwork contractors and set excavation rules in contracts.

Evidence produced

Contractor assessment and site induction evidence.

Row 7

Management activity

Learn and improve

How buildout would apply it

Review strikes, near misses, inspection defects and worker feedback.

Evidence produced

Lessons learned and revised excavation standard.

Read the complete comparison table
BuildOut Ltd excavation controls
RowManagement activityHow buildout would apply itEvidence produced
1Assess and analyseReview ground, services, structures, water, public interface and confined-space risk.Pre-construction information review and excavation risk register.
2Plan and designSelect trenchless option, support, battering or trench box where appropriate.Temporary works design brief and method statement.
3Train and briefTrain supervisors in inspection, CAT and Genny limits, permit to dig and emergency response.Training matrix and briefing records.
4ImplementUse permits, service marking, trial holes, barriers, access and plant segregation.Permit to dig, photos and supervisor checks.
5Check and auditInspect daily and audit against HSG47 and HSE excavation guidance.Inspection reports, audit findings and action close-out.
6Contractor managementPre-qualify groundwork contractors and set excavation rules in contracts.Contractor assessment and site induction evidence.
7Learn and improveReview strikes, near misses, inspection defects and worker feedback.Lessons learned and revised excavation standard.
Role / Learning

Table ID: excavation-competence-matrix

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Role

Client

Learning

Supply ground and service information

Demonstration

Review preconstruction pack

Assessor

Principal designer

Record

Information issue

Reassess when

New survey

Row 2

Role

Designer

Learning

Reduce need and specify support

Demonstration

Challenge sequence and ground

Assessor

Technical lead

Record

Design basis

Reassess when

Change

Row 3

Role

Supervisor

Learning

Check face, barriers and services

Demonstration

Walk site before entry

Assessor

Site manager

Record

Daily brief

Reassess when

Weather

Row 4

Role

Competent inspector

Learning

Inspect support and battering

Demonstration

Document shift check

Assessor

Principal contractor

Record

Inspection report

Reassess when

Instability

Row 5

Role

Plant operator

Learning

Keep clear of edge and services

Demonstration

Demonstrate set-back

Assessor

Supervisor

Record

Authorisation

Reassess when

Route change

Row 6

Role

Worker

Learning

Use access and stop on change

Demonstration

Explain stop point

Assessor

Supervisor

Record

Briefing

Reassess when

Unexpected service

Read the complete comparison table
Role / Learning
RowRoleLearningDemonstrationAssessorRecordReassess when
1ClientSupply ground and service informationReview preconstruction packPrincipal designerInformation issueNew survey
2DesignerReduce need and specify supportChallenge sequence and groundTechnical leadDesign basisChange
3SupervisorCheck face, barriers and servicesWalk site before entrySite managerDaily briefWeather
4Competent inspectorInspect support and batteringDocument shift checkPrincipal contractorInspection reportInstability
5Plant operatorKeep clear of edge and servicesDemonstrate set-backSupervisorAuthorisationRoute change
6WorkerUse access and stop on changeExplain stop pointSupervisorBriefingUnexpected service
CN1-04 study prompts

Table ID: excavation-cn1-04-study-prompts

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Cn1 area

4.1 Excavation hazards and assessment

What to know

Collapse, buried services, falls, water, contamination, atmospheres, plant and structures.

Scenario application

Identify hazards specific to the trench, depth and location.

Row 2

Cn1 area

4.2 Excavation control measures

What to know

Support, battering, access, barriers, spoil control, dewatering, service avoidance and inspections.

Scenario application

Select controls and explain why they fit the risk.

Row 3

Cn1 area

4.3 Confined spaces

What to know

Restricted access plus specified risks such as gases, low oxygen, flooding or engulfment.

Scenario application

Decide whether confined-space controls and rescue are needed.

Row 4

Cn1 area

Evidence

What to know

Records and site observations that prove controls are working.

Scenario application

Inspection report, permit, service plan, trial-hole record and briefing.

Row 5

Cn1 area

Management failure

What to know

Poor planning, weak supervision or missing competent inspection.

Scenario application

Explain underlying causes, not just worker error.

Row 6

Cn1 area

Improvement

What to know

Action planning and review after change or incident.

Scenario application

Assign owners, deadlines and verification.

Read the complete comparison table
CN1-04 study prompts
RowCn1 areaWhat to knowScenario application
14.1 Excavation hazards and assessmentCollapse, buried services, falls, water, contamination, atmospheres, plant and structures.Identify hazards specific to the trench, depth and location.
24.2 Excavation control measuresSupport, battering, access, barriers, spoil control, dewatering, service avoidance and inspections.Select controls and explain why they fit the risk.
34.3 Confined spacesRestricted access plus specified risks such as gases, low oxygen, flooding or engulfment.Decide whether confined-space controls and rescue are needed.
4EvidenceRecords and site observations that prove controls are working.Inspection report, permit, service plan, trial-hole record and briefing.
5Management failurePoor planning, weak supervision or missing competent inspection.Explain underlying causes, not just worker error.
6ImprovementAction planning and review after change or incident.Assign owners, deadlines and verification.
Framework / Status and scope

Table ID: excavation-framework-scope

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Framework

HSE HSG65

Status and scope

GB regulator management guidance

Contribution

Plan, do, check and act with evidence of current control

Limit

Apply to the actual high-consequence scenario.

Read the complete comparison table
Framework / Status and scope
RowFrameworkStatus and scopeContributionLimit
1HSE HSG65GB regulator management guidancePlan, do, check and act with evidence of current controlApply to the actual high-consequence scenario.
Excavation warning signs and consequences

Table ID: excavation-excavation-warning-signs-and-consequences

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Warning sign

Unsupported vertical sides

How it can cause harm

Collapse can bury or crush workers.

Response

Stop entry and install support or redesign.

Row 2

Warning sign

Spoil at edge

How it can cause harm

Adds load and can fall into trench.

Response

Move spoil and inspect stability.

Row 3

Warning sign

No service markings

How it can cause harm

Excavator or tool may strike cable or gas pipe.

Response

Stop, locate, mark and trial-hole.

Row 4

Warning sign

Water in excavation

How it can cause harm

Sides weaken and flooding risk increases.

Response

Inspect, dewater and review support.

Row 5

Warning sign

No safe access

How it can cause harm

Falls, slips and delayed escape.

Response

Provide suitable ladder, steps or ramp.

Row 6

Warning sign

Plant close to edge

How it can cause harm

Edge collapse or struck-by risk.

Response

Set exclusion distance and revise traffic route.

Row 7

Warning sign

Missing inspection report

How it can cause harm

Unsafe condition may be unrecognised.

Response

Competent inspection before work continues.

Row 8

Warning sign

Diesel equipment in or near trench

How it can cause harm

Fumes may accumulate in low area.

Response

Remove source, ventilate and assess atmosphere.

Read the complete comparison table
Excavation warning signs and consequences
RowWarning signHow it can cause harmResponse
1Unsupported vertical sidesCollapse can bury or crush workers.Stop entry and install support or redesign.
2Spoil at edgeAdds load and can fall into trench.Move spoil and inspect stability.
3No service markingsExcavator or tool may strike cable or gas pipe.Stop, locate, mark and trial-hole.
4Water in excavationSides weaken and flooding risk increases.Inspect, dewater and review support.
5No safe accessFalls, slips and delayed escape.Provide suitable ladder, steps or ramp.
6Plant close to edgeEdge collapse or struck-by risk.Set exclusion distance and revise traffic route.
7Missing inspection reportUnsafe condition may be unrecognised.Competent inspection before work continues.
8Diesel equipment in or near trenchFumes may accumulate in low area.Remove source, ventilate and assess atmosphere.
Official guidance and legislation

Table ID: excavation-official-guidance-and-legislation

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Authority

HSE

Direct source

HSE excavations guidance

Jurisdiction

Great Britain

Claim

Support/batter, service, edge, water and shift-inspection controls.

Row 2

Authority

HSE

Direct source

HSE HSG47 avoiding danger from underground services

Jurisdiction

Great Britain

Claim

Plan, locate and identify buried services, then excavate safely.

Row 3

Authority

HSENI

Direct source

HSENI CDM 2016 guidance

Jurisdiction

Northern Ireland

Claim

NI construction duty-holder route.

Row 4

Authority

Legislation

Direct source

Construction (Design and Management) Regulations 2015

Jurisdiction

Great Britain

Claim

GB construction duties, excavation precautions and inspection.

Row 5

Authority

Legislation

Direct source

Construction (Design and Management) Regulations (Northern Ireland) 2016

Jurisdiction

Northern Ireland

Claim

NI construction duties, excavation precautions and inspection.

Row 6

Authority

Legislation

Direct source

Health and Safety at Work etc. Act 1974

Jurisdiction

Great Britain

Claim

GB general work-safety duties

Row 7

Authority

Legislation

Direct source

Health and Safety at Work (Northern Ireland) Order 1978

Jurisdiction

Northern Ireland

Claim

NI general work-safety duties

Row 8

Authority

Legislation

Direct source

Management of Health and Safety at Work Regulations 1999

Jurisdiction

Great Britain

Claim

GB risk assessment and prevention arrangements

Row 9

Authority

Legislation

Direct source

Management of Health and Safety at Work Regulations (Northern Ireland) 2000

Jurisdiction

Northern Ireland

Claim

NI risk assessment and prevention arrangements

Row 10

Authority

Legislation

Direct source

Confined Spaces Regulations 1997

Jurisdiction

Great Britain

Claim

GB confined-space avoidance, safe work and rescue where applicable.

Row 11

Authority

Legislation

Direct source

Confined Spaces Regulations (Northern Ireland) 1999

Jurisdiction

Northern Ireland

Claim

NI confined-space avoidance, safe work and rescue where applicable.

Row 12

Authority

HSE

Direct source

HSE Managing for health and safety (HSG65)

Jurisdiction

Great Britain guidance

Claim

HSE Plan–Do–Check–Act guidance; no licensed-standard clauses.

Row 13

Authority

HSE

Direct source

HSE managing for health and safety

Jurisdiction

Great Britain guidance

Claim

HSE Plan–Do–Check–Act guidance; no licensed-standard clauses.

Row 14

Authority

HSE

Direct source

HSE confined spaces guidance

Jurisdiction

Great Britain

Claim

Confined-space risk, avoidance, safe work and rescue where the legal definition is met.

Read the complete comparison table
Official guidance and legislation
RowAuthorityDirect sourceJurisdictionClaim
1HSEHSE excavations guidanceGreat BritainSupport/batter, service, edge, water and shift-inspection controls.
2HSEHSE HSG47 avoiding danger from underground servicesGreat BritainPlan, locate and identify buried services, then excavate safely.
3HSENIHSENI CDM 2016 guidanceNorthern IrelandNI construction duty-holder route.
4LegislationConstruction (Design and Management) Regulations 2015Great BritainGB construction duties, excavation precautions and inspection.
5LegislationConstruction (Design and Management) Regulations (Northern Ireland) 2016Northern IrelandNI construction duties, excavation precautions and inspection.
6LegislationHealth and Safety at Work etc. Act 1974Great BritainGB general work-safety duties
7LegislationHealth and Safety at Work (Northern Ireland) Order 1978Northern IrelandNI general work-safety duties
8LegislationManagement of Health and Safety at Work Regulations 1999Great BritainGB risk assessment and prevention arrangements
9LegislationManagement of Health and Safety at Work Regulations (Northern Ireland) 2000Northern IrelandNI risk assessment and prevention arrangements
10LegislationConfined Spaces Regulations 1997Great BritainGB confined-space avoidance, safe work and rescue where applicable.
11LegislationConfined Spaces Regulations (Northern Ireland) 1999Northern IrelandNI confined-space avoidance, safe work and rescue where applicable.
12HSEHSE Managing for health and safety (HSG65)Great Britain guidanceHSE Plan–Do–Check–Act guidance; no licensed-standard clauses.
13HSEHSE managing for health and safetyGreat Britain guidanceHSE Plan–Do–Check–Act guidance; no licensed-standard clauses.
14HSEHSE confined spaces guidanceGreat BritainConfined-space risk, avoidance, safe work and rescue where the legal definition is met.
Acronyms and terms

Table ID: excavation-acronyms-and-terms

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Term

CAT

Meaning

Cable avoidance tool.

Why it matters

Used to locate buried services, with limitations.

Row 2

Term

CDM

Meaning

Construction (Design and Management) Regulations.

Why it matters

Main construction planning and dutyholder framework.

Row 3

Term

CN1-04

Meaning

IOSH Construction syllabus element covering excavation.

Why it matters

Useful study reference.

Row 4

Term

Genny

Meaning

Signal generator used with a locator to help trace services.

Why it matters

Supports service location but does not replace plans or safe digging.

Row 5

Term

HSG47

Meaning

HSE guidance on avoiding danger from underground services.

Why it matters

Core buried-service reference.

Row 6

Term

RAMS

Meaning

Risk assessment and method statement.

Why it matters

Common site document for planned controls.

Row 7

Term

RPE

Meaning

Respiratory protective equipment.

Why it matters

May be needed for contaminated ground, dust or fumes.

Row 8

Term

Temporary works

Meaning

Temporary structures or support needed for construction work.

Why it matters

Includes excavation support and edge stability controls.

Row 9

Term

SHEQ

Meaning

Safety, health, environment and quality.

Why it matters

Organisation function label, not a statutory dutyholder.

Read the complete comparison table
Acronyms and terms
RowTermMeaningWhy it matters
1CATCable avoidance tool.Used to locate buried services, with limitations.
2CDMConstruction (Design and Management) Regulations.Main construction planning and dutyholder framework.
3CN1-04IOSH Construction syllabus element covering excavation.Useful study reference.
4GennySignal generator used with a locator to help trace services.Supports service location but does not replace plans or safe digging.
5HSG47HSE guidance on avoiding danger from underground services.Core buried-service reference.
6RAMSRisk assessment and method statement.Common site document for planned controls.
7RPERespiratory protective equipment.May be needed for contaminated ground, dust or fumes.
8Temporary worksTemporary structures or support needed for construction work.Includes excavation support and edge stability controls.
9SHEQSafety, health, environment and quality.Organisation function label, not a statutory dutyholder.
Potential SHARE documents

Table ID: excavation-potential-share-documents

Source: https://www.sharehub.ltd/knowledge-hub/excavation.html

Row 1

Document

Planned example: Excavation pre-start checklist

Purpose

Checks services, support, access, edge protection, plant and emergency arrangements.

Likely user

Supervisors and site managers.

Row 2

Document

Planned example: Permit to dig template

Purpose

Authorises excavation only after critical controls are confirmed.

Likely user

Principal contractors and supervisors.

Row 3

Document

Planned example: Daily excavation inspection form

Purpose

Records competent inspection findings and actions.

Likely user

Competent inspectors.

Row 4

Document

Planned example: Buried services briefing sheet

Purpose

Explains HSG47-style plan, locate and safe excavation steps.

Likely user

Groundworkers and plant operators.

Row 5

Document

Planned example: Excavation emergency response card

Purpose

Summarises response to collapse, service strike, flooding and atmosphere risk.

Likely user

Site teams.

Row 6

Document

Planned example: CN1-04 study worksheet

Purpose

Supports learners with excavation hazards, controls and confined-space scenarios.

Likely user

IOSH Construction learners.

Read the complete comparison table
Potential SHARE documents
RowDocumentPurposeLikely user
1Planned example: Excavation pre-start checklistChecks services, support, access, edge protection, plant and emergency arrangements.Supervisors and site managers.
2Planned example: Permit to dig templateAuthorises excavation only after critical controls are confirmed.Principal contractors and supervisors.
3Planned example: Daily excavation inspection formRecords competent inspection findings and actions.Competent inspectors.
4Planned example: Buried services briefing sheetExplains HSG47-style plan, locate and safe excavation steps.Groundworkers and plant operators.
5Planned example: Excavation emergency response cardSummarises response to collapse, service strike, flooding and atmosphere risk.Site teams.
6Planned example: CN1-04 study worksheetSupports learners with excavation hazards, controls and confined-space scenarios.IOSH Construction learners.