Underground tank and pipework monitoring history

CWF-REG-WET-01 · Blank register with separate fictional worked entries · Owner role: Engineering and asset integrity manager

Fictional arrangement or blank working master. No actual approval, site authorisation or completed evidence is supplied.

This preview shows saved worksheet values. Edit the downloaded workbook to use its formulas, filters and validation.

Register

Underground tank and pipework monitoring history
Crownway Fuels Ltd. CWF-REG-WET-01. Version 1.0. Blank working master. Enter actual facts and evidence.
OwnerEngineering and asset integrity managerAs at date
Records0Rows with alerts0
Editable A:H. Calculated I lists missing fields, invalid dates/status, duplicate IDs and passed review dates. A clear alert cell does not verify a control or authorise work.
Record required detail in column C: Integrity reports; Alarms; Repairs; Reconciliations and decommissioning information
Read Guide before use. Set a valid As at date. Twenty rows are available; the default blank print view shows six. Keep stable IDs and evidence together when sorting.
Record IDActual site asset and subjectRequired technical or decision detailsDecision restriction and actionEvidence reference and ownerReview dueAction statusVerification evidence and limitsRecord alerts
Keep the actual retention rule and access class with the evidence. Preserve statutory minima, permit conditions and legal holds. Extend the table, formulas, validation, summaries and print area together and test the new last row.
SHARE homeGuide and worked examples are separate from real records. Save your own operational copy before entering data.

Worked examples

Underground tank and pipework monitoring history
Crownway Fuels Ltd. CWF-REG-WET-01. Version 1.0. Fictional examples. No operational evidence.
OwnerEngineering and asset integrity manager2026-11-10 00:00:00As at date
Records2Rows with alerts2
Editable A:H. Calculated I lists missing fields, invalid dates/status, duplicate IDs and passed review dates. A clear alert cell does not verify a control or authorise work.
Record required detail in column C: Integrity reports; Alarms; Repairs; Reconciliations and decommissioning information
Read Guide before use. Set a valid As at date. Twenty rows are available; the default blank print view shows six. Keep stable IDs and evidence together when sorting.
Record IDActual site asset and subjectRequired technical or decision detailsDecision restriction and actionEvidence reference and ownerReview dueAction statusVerification evidence and limitsRecord alerts
EX-WET-01Illustrative Underground tank and pipework monitoring historyHold. Actual details and evidence not established.Engineering and asset integrity manager; invented reference EX-012026-11-17 00:00:00OpenMissing C;
EX-WET-02Second illustrative decisionIntegrity reports; Alarms; Repairs; Reconciliations and decommissioning informationImplemented change awaiting review; no release asserted.Engineering and asset integrity manager; invented reference EX-022026-11-09 00:00:00ImplementedEffectiveness remains unverified.Review date passed;
Keep the actual retention rule and access class with the evidence. Preserve statutory minima, permit conditions and legal holds. Extend the table, formulas, validation, summaries and print area together and test the new last row.
SHARE homeGuide and worked examples are separate from real records. Save your own operational copy before entering data.

Guide

Underground tank and pipework monitoring history guide
PurposeProvide the site/task-specific underground tank and pipework monitoring history and retain its controlled output.
ScopeRETAIL. Apply where the site/activity/hazard is present; confirm in the site applicability assessment. Ten English petrol/diesel forecourts and convenience shops, HQ and mobile support. The additional bulk establishment is a separate illustrative scenario. Inventory, regulatory applicability, permissions and site-specific acceptance are unresolved.
ResponsibilityEngineering and asset integrity manager maintains current entries, unresolved restrictions and supporting evidence. No named person is appointed by this example.
Required detailsIntegrity reports; Alarms; Repairs; Reconciliations and decommissioning information
How to useRegister is blank. Worked examples contains two invented open records, including missing details and a passed review date. Complete actual A:H inputs and retain the detailed technical record separately.
Preparing the activityRecord opening stock, deliveries, sales and closing stock on a consistent basis for each tank and grade. Check gauge quality, units, temperature basis and meter information; maintain traceable corrections.
Operating arrangementEvaluate trends and unexplained loss promptly against site-specific triggers and leak-detection information. Investigate possible measurement errors without using that possibility to dismiss a credible release.
VerificationThe site manager checks exceptions every operating day in this example arrangement and escalates a credible leak immediately. Engineering and environmental leads verify containment, pollution pathways and safe return before a restriction is removed.
Worked decisionSeveral reconciliations show unexplained loss and the gauge has intermittent faults. The site manager escalates both issues, restricts the affected system as assessed and obtains engineering and environmental investigation. The loss is not reset to zero by changing the spreadsheet.
Stop and escalationSuspend affected tank/line where a leak alarm or credible unexplained loss cannot be safely resolved; protect drains, control ignition and activate incident escalation.
Record alertsAlerts identify gaps A=ID, B=scope/subject, C=required detail, D=decision/action, E=evidence/owner, F=review due, G=status. Validity checks support record quality only. Human decisions and genuine evidence remain necessary.
Date controlsSet As at date on each working sheet. Dates must be numeric whole days from 1 to 73050. Text, zero, negatives and fractional dates remain invalid even if pasted. A passed review date prompts review; it is not an automatic legal expiry.
Status and verificationUse the exact categories below. Verified effective also needs a specific H entry describing the competent verifier, test, evidence and limits. A populated field or an empty alert cell does not prove those claims.
Keeping and extending recordsTwenty rows are prepared. To extend, enlarge the table and all bounded A10:A29 and I10:I29 summaries/duplicate ranges, copy formulas, validation and conditional formatting, update the print area and test the new last row. Keep IDs and evidence together when sorting.
Privacy and retentionSet the approved record-specific retention period before operational use, including applicable statutory minimum, permit conditions and legal holds; review is not permission to delete. Access class in the catalogue: Project team. Keep clinical and personal information in authorised restricted custody.
Primary guidance checked 10 November 2026. Legal and permission registers retain their own detailed review dates, territories and unresolved decisions.
Bulk storage and tank farm safety
Allowed action status values
OpenOfficial guidance 1 from www.gov.uk
Implemented
Awaiting verification
Verified effective
Reopened
Not applicable