Tank integrity overfill prevention and containment procedure

CWF-PRO-TANK · Completed fictional example · Owner role: Engineering and asset integrity manager

Fictional arrangement or blank working master. No actual approval, site authorisation or completed evidence is supplied.

Tank integrity overfill prevention and containment procedure

Crownway Fuels Ltd. CWF-PRO-TANK. Version 1.0. Prepared 10 November 2026.

COMPLETED FICTIONAL ARRANGEMENT. This Crownway example supports adaptation and learning. It represents no actual company issue, site approval, signature or completed operational evidence.

Explain who does what, in what sequence, the control rationale, evidence, escalation and safe restart conditions.

Scope and responsibility

BULK; RETAIL. Apply where the site/activity/hazard is present; confirm in the site applicability assessment. Ten English petrol/diesel forecourts and convenience shops, HQ and mobile support. The additional bulk establishment is a separate illustrative scenario. Inventory, regulatory applicability, permissions and site-specific acceptance are unresolved.

Responsible roleRequired action
Engineering and asset integrity managerOwn the arrangement, its current scope and escalation.
Site manager and shift supervisorVerify worksite conditions, coordination, briefing and authorised limits.
Engineering and competent specialistsResolve technical uncertainties, verify protection and retain acceptance evidence.
Workers and contractor performing authorityCheck the agreed method, report change, stop loss of control and provide safe handback.

Information before release

Review current site and equipment information, assessments, permissions, competence, contractor interfaces and emergency readiness. The branch records identify the detailed evidence fields. Missing technical values are resolved from competent site information; do not copy values from teaching models.

Preparation and operation

1 Prepare the activity

Engineering identifies tanks, pipework, vents, containment, level systems and overfill protection by stable asset references. Obtain the actual design basis, safe working capacity, degradation mechanisms and inspection history.

2 Carry out and control the work

Set competent inspection and proof-test requirements from risk, design and applicable duties. Control bund drainage, penetrations and changes; assess vapour and liquid consequences separately. Never fill to an example quantity.

Control rationale

Corrosion, overfill and ineffective secondary containment turn a controllable equipment fault into a major fire or pollution event.

Stop escalation and return

Remove affected tank/transfer from service for failed high-level protection, integrity loss, unassessed defects, unsuitable containment or an overdue safety-critical test without a competent approved safe basis.

The person controlling the activity makes it safe and informs the site manager. The relevant competent specialist verifies the failed or uncertain safeguard. Operations authorises any restart separately after technical acceptance, applicable permissions, work coordination and a fresh briefing. Record all continuing restrictions.

Verification and follow through

Trace a test to the actual sensor, logic, final element and response criteria, including bypasses and restoration. Record failures and restrictions. Visual cleanliness of a bund is not proof of integrity or adequate firewater capacity.

Worked decision

A tank test record names the instrument but gives no result for the final shutdown element. Engineering declines the complete-loop test claim and retains the relevant receiving restriction until a competent test and controlled restoration provide the missing evidence.

This invented case illustrates a decision and any continuing hold. It is not evidence that Crownway has completed an inspection, test, exposure evaluation or regulatory submission.

Connected documents

ReferenceUse in this branch
CWF-REG-TANK-01Tank pipework and containment asset register (Register)
CWF-PLN-TANK-01Tank integrity inspection and examination plan (Plan)
CWF-CHK-TANK-01Overfill alarm and independent trip proof test (Checklist)
CWF-CHK-TANK-02Bund drainage valve and containment inspection (Checklist)
CWF-RA-TANK-01Firewater and environmental containment assessment (Risk assessment)
CWF-FRM-TANK-01Integrity defect fitness for service and repair decision (Form)

Retain stable record IDs, actual site or asset, template revision, competent author, date and time, findings, actions, owner, due date and evidence. Set the applicable record-specific retention and access rules before operational use. A review date does not authorise deletion; preserve legal holds.

Guidance and related arrangements

Primary guidance 1

Primary guidance 2

Asset integrity and mechanical integrity

Crownway document overview

Primary guidance checked 10 November 2026 for the described arrangements. Linked legal-register entries keep their own review dates and territorial conditions. Guidance, ACOPs, company controls and direct statutory duties are distinct.

Primary references: hsg176 | prevent groundwater pollution from underground fuel storage tanks