Crownway Fuels

SHAREhub · Company management system · v1.0

← All Crownway resources

Management of change and project design procedure

CWF-PRO-MOC · Completed fictional example · Owner role: Process safety and COMAH lead

Fictional arrangement or blank working master. No actual approval, site authorisation or completed evidence is supplied.

Management of change and project design procedure

Crownway Fuels Ltd. CWF-PRO-MOC. Version 1.0. Prepared 10 November 2026.

COMPLETED FICTIONAL ARRANGEMENT. This Crownway example supports adaptation and learning. It represents no actual company issue, site approval, signature or completed operational evidence.

Explain who does what, in what sequence, the control rationale, evidence, escalation and safe restart conditions.

Scope and responsibility

BULK; HQ; RETAIL. Apply where the site/activity/hazard is present; confirm in the site applicability assessment. Ten English petrol/diesel forecourts and convenience shops, HQ and mobile support. The additional bulk establishment is a separate illustrative scenario. Inventory, regulatory applicability, permissions and site-specific acceptance are unresolved.

Responsible roleRequired action
Process safety and COMAH leadOwn the arrangement, its current scope and escalation.
Site manager and shift supervisorVerify worksite conditions, coordination, briefing and authorised limits.
Engineering and competent specialistsResolve technical uncertainties, verify protection and retain acceptance evidence.
Workers and contractor performing authorityCheck the agreed method, report change, stop loss of control and provide safe handback.

Information before release

Review current site and equipment information, assessments, permissions, competence, contractor interfaces and emergency readiness. The branch records identify the detailed evidence fields. Missing technical values are resolved from competent site information; do not copy values from teaching models.

Preparation and operation

1 Prepare the activity

Screen permanent and temporary changes to product, equipment, software, layout, staffing, contractors and operating method. Compare with the existing accepted design and identify legal, environmental and human interfaces.

2 Carry out and control the work

Obtain competent multidisciplinary review, resolve actions, update technical information and permissions, train affected people and complete a pre-startup review. An emergency repair still needs a controlled change route proportionate to its urgency.

Control rationale

Small changes to software, staffing, products or plant can invalidate safe limits, hazardous areas and emergency arrangements.

Stop escalation and return

No commissioning or changed operation before critical actions, statutory notices/consents, verification and trained operating coverage are complete.

The person controlling the activity makes it safe and informs the site manager. The relevant competent specialist verifies the failed or uncertain safeguard. Operations authorises any restart separately after technical acceptance, applicable permissions, work coordination and a fresh briefing. Record all continuing restrictions.

Verification and follow through

Temporary changes have a named owner, expiry and restoration plan. Review overdue or extended changes before they continue. Verify installed reality and later operating effectiveness against the approved change intent.

Worked decision

An EV charging installation changes vehicle queues and emergency access. The change owner reviews electrical, DSEAR, traffic, accessibility and responder interfaces before construction and opening. A civil layout drawing alone does not release the change.

This invented case illustrates a decision and any continuing hold. It is not evidence that Crownway has completed an inspection, test, exposure evaluation or regulatory submission.

Connected documents

ReferenceUse in this branch
CWF-FRM-MOC-01Technical organisational and temporary change assessment (Form)
CWF-REG-MOC-01Change actions and temporary change expiry register (Register)
CWF-CHK-MOC-01Design review and hazard study screen (Checklist)
CWF-PLN-MOC-01Construction and maintenance project CDM arrangements (Plan)
CWF-CHK-MOC-02Pre startup safety and environmental review (Checklist)
CWF-FRM-MOC-02Decommissioning closure and contaminated land review (Form)

Retain stable record IDs, actual site or asset, template revision, competent author, date and time, findings, actions, owner, due date and evidence. Set the applicable record-specific retention and access rules before operational use. A review date does not authorise deletion; preserve legal holds.

Guidance and related arrangements

Primary guidance 1

Primary guidance 2

Health and Safety Management Systems

Crownway document overview

Primary guidance checked 10 November 2026 for the described arrangements. Linked legal-register entries keep their own review dates and territorial conditions. Guidance, ACOPs, company controls and direct statutory duties are distinct.

Primary references: comah | official requirements

Related resources

Primary guidance