Crownway Fuels

SHAREhub · Company management system · v1.0

← All Crownway resources

Construction and maintenance project CDM arrangements

CWF-PLN-MOC-01 · Completed fictional example · Owner role: Process safety and COMAH lead

Fictional arrangement or blank working master. No actual approval, site authorisation or completed evidence is supplied.

Construction and maintenance project CDM arrangements

Crownway Fuels Ltd. CWF-PLN-MOC-01. Version 1.0. Prepared 10 November 2026.

COMPLETED FICTIONAL ARRANGEMENT. This Crownway example supports adaptation and learning. It represents no actual company issue, site approval, signature or completed operational evidence.

Provide the site/task-specific construction and maintenance project cdm arrangements and retain its controlled output.

Purpose scope and accountable roles

BULK; HQ; RETAIL. Apply where the site/activity/hazard is present; confirm in the site applicability assessment. Ten English petrol/diesel forecourts and convenience shops, HQ and mobile support. The additional bulk establishment is a separate illustrative scenario. Inventory, regulatory applicability, permissions and site-specific acceptance are unresolved.

Process safety and COMAH lead owns delivery of this plan. Operations secures staffing and resources; engineering, the HSE lead and relevant competent specialists confirm technical and legal prerequisites. The board resolves constraints affecting critical controls.

Planned arrangements

Screen permanent and temporary changes to product, equipment, software, layout, staffing, contractors and operating method. Compare with the existing accepted design and identify legal, environmental and human interfaces.

Obtain competent multidisciplinary review, resolve actions, update technical information and permissions, train affected people and complete a pre-startup review. An emergency repair still needs a controlled change route proportionate to its urgency.

Required planning outputs

Client/designer/contractor roles: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.

Information: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.

Plan: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.

Welfare: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.

Live-site interface and handover duties: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.

Delivery verification and review

Temporary changes have a named owner, expiry and restoration plan. Review overdue or extended changes before they continue. Verify installed reality and later operating effectiveness against the approved change intent.

StageExample management arrangement
Before the activityOwner confirms the scope, competent people, current information and permissions. Open critical prerequisites prevent release.
At implementationSite supervisor verifies the physical arrangement and understanding. Engineering checks the accepted technical criteria for the affected equipment.
After change or failureSuspend the affected scope, assess the changed risk, update information and brief people before a new decision.
Planned reviewOwner reviews at a justified risk-based interval. Area management challenges evidence and independent assurance samples effectiveness.

Stop escalation and return

No commissioning or changed operation before critical actions, statutory notices/consents, verification and trained operating coverage are complete.

The person controlling the activity makes it safe and informs the site manager. The relevant competent specialist verifies the failed or uncertain safeguard. Operations authorises any restart separately after technical acceptance, applicable permissions, work coordination and a fresh briefing. Record all continuing restrictions.

Worked decision

An EV charging installation changes vehicle queues and emergency access. The change owner reviews electrical, DSEAR, traffic, accessibility and responder interfaces before construction and opening. A civil layout drawing alone does not release the change.

This invented case illustrates a decision and any continuing hold. It is not evidence that Crownway has completed an inspection, test, exposure evaluation or regulatory submission.

Guidance and related arrangements

Primary guidance 1

Primary guidance 2

Health and Safety Management Systems

Crownway document overview

Primary guidance checked 10 November 2026 for the described arrangements. Linked legal-register entries keep their own review dates and territorial conditions. Guidance, ACOPs, company controls and direct statutory duties are distinct.

Primary references: comah | official requirements

Related resources

Primary guidance