CWF-PLN-SCOPE-01 · Completed fictional example · Owner role: Health safety and environmental lead
Site layout drainage receptors and emergency access plan
Crownway Fuels Ltd. CWF-PLN-SCOPE-01. Version 1.0. Prepared 10 November 2026.
COMPLETED FICTIONAL ARRANGEMENT. This Crownway example supports adaptation and learning. It represents no actual company issue, site approval, signature or completed operational evidence.
Provide the site/task-specific site layout drainage receptors and emergency access plan and retain its controlled output.
Purpose scope and accountable roles
BULK; HQ; RETAIL. Apply where the site/activity/hazard is present; confirm in the site applicability assessment. Ten English petrol/diesel forecourts and convenience shops, HQ and mobile support. The additional bulk establishment is a separate illustrative scenario. Inventory, regulatory applicability, permissions and site-specific acceptance are unresolved.
Health safety and environmental lead owns delivery of this plan. Operations secures staffing and resources; engineering, the HSE lead and relevant competent specialists confirm technical and legal prerequisites. The board resolves constraints affecting critical controls.
Planned arrangements
Build a site-by-site inventory of the operator, activities, nation, maximum dangerous-substance holdings and wastes. Use classifications from current safety data and competent advice; sales throughput is not the COMAH inventory.
The environmental, engineering and process-safety leads determine independent permission routes. Record petroleum certification, environmental permitting, planning and hazardous-substances consent separately, including changes and pre-start requirements.
Required planning outputs
Tank/fill/vent points: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Hazardous areas: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Isolations: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Drains: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Receptors: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Access and drawing version: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Delivery verification and review
Reconcile the inventory against purchase limits, tank capacity, process holdings and credible temporary storage. Have a competent reviewer check Schedule 1 classification and aggregation before assigning any COMAH tier.
| Stage | Example management arrangement |
| Before the activity | Owner confirms the scope, competent people, current information and permissions. Open critical prerequisites prevent release. |
| At implementation | Site supervisor verifies the physical arrangement and understanding. Engineering checks the accepted technical criteria for the affected equipment. |
| After change or failure | Suspend the affected scope, assess the changed risk, update information and brief people before a new decision. |
| Planned review | Owner reviews at a justified risk-based interval. Area management challenges evidence and independent assurance samples effectiveness. |
Stop escalation and return
No new fuel, capacity increase, boundary change or activity starts with an unresolved tier, permit, certificate or material-change notification decision.
The person controlling the activity makes it safe and informs the site manager. The relevant competent specialist verifies the failed or uncertain safeguard. Operations authorises any restart separately after technical acceptance, applicable permissions, work coordination and a fresh briefing. Record all continuing restrictions.
Worked decision
The bulk teaching scenario is described as lower tier but its product maxima are absent. The process-safety lead records an unresolved applicability decision and holds design and operating decisions that depend on the tier. A label in the catalogue does not establish the legal outcome.
This invented case illustrates a decision and any continuing hold. It is not evidence that Crownway has completed an inspection, test, exposure evaluation or regulatory submission.
Guidance and related arrangements
Primary guidance 1
Primary guidance 2
UK Legal Framework
Crownway document overview
Primary guidance checked 10 November 2026 for the described arrangements. Linked legal-register entries keep their own review dates and territorial conditions. Guidance, ACOPs, company controls and direct statutory duties are distinct.
Primary references: comah15 | owner petrol station