CWF-PLN-EMERG-02 · Completed fictional example · Owner role: Operations director and area manager
Lower tier COMAH major accident emergency arrangements
Crownway Fuels Ltd. CWF-PLN-EMERG-02. Version 1.0. Prepared 10 November 2026.
COMPLETED FICTIONAL ARRANGEMENT. This Crownway example supports adaptation and learning. It represents no actual company issue, site approval, signature or completed operational evidence.
Provide the site/task-specific lower tier comah major accident emergency arrangements and retain its controlled output.
Purpose scope and accountable roles
BULK only: requested additional lower-tier COMAH establishment. HQ supports governance and other sites may receive relevant learning; they are not thereby COMAH establishments. Ten English petrol/diesel forecourts and convenience shops, HQ and mobile support. The additional bulk establishment is a separate illustrative scenario. Inventory, regulatory applicability, permissions and site-specific acceptance are unresolved.
Operations director and area manager owns delivery of this plan. Operations secures staffing and resources; engineering, the HSE lead and relevant competent specialists confirm technical and legal prerequisites. The board resolves constraints affecting critical controls.
Planned arrangements
Plan for credible fuel releases, fire, exposure, vehicle incidents, utility failures and adverse weather. Establish alarm, safe withdrawal, customer evacuation, accountability, responder access and communication for every operating period.
People raise the alarm and summon emergency assistance promptly. Isolate or contain only within their training and from a safe position. Prevent re-entry and unplanned rescue; give responders current substance and site information.
Required planning outputs
Credible major accidents: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Resources: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Neighbouring interfaces: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Environmental mitigation and liaison proportionate to risk: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Delivery verification and review
Exercise representative scenarios and check night-shift and contractor arrangements. Recovery requires engineering, environmental and operational checks for the actual damage, contamination and failed protection before a separate restart decision.
| Stage | Example management arrangement |
| Before the activity | Owner confirms the scope, competent people, current information and permissions. Open critical prerequisites prevent release. |
| At implementation | Site supervisor verifies the physical arrangement and understanding. Engineering checks the accepted technical criteria for the affected equipment. |
| After change or failure | Suspend the affected scope, assess the changed risk, update information and brief people before a new decision. |
| Planned review | Owner reviews at a justified risk-based interval. Area management challenges evidence and independent assurance samples effectiveness. |
Stop escalation and return
Raise the alarm, stop operations remotely if safe, keep people away/upwind as appropriate and call emergency services; do not enter vapour/fire zones or attempt response beyond training and equipment.
The person controlling the activity makes it safe and informs the site manager. The relevant competent specialist verifies the failed or uncertain safeguard. Operations authorises any restart separately after technical acceptance, applicable permissions, work coordination and a fresh briefing. Record all continuing restrictions.
Worked decision
A night-shift exercise shows that the nominated controller is unavailable and the access gate key cannot be located. Operations retains the readiness gap, provides a workable interim arrangement and repeats the access and communication exercise before accepting cover.
This invented case illustrates a decision and any continuing hold. It is not evidence that Crownway has completed an inspection, test, exposure evaluation or regulatory submission.
Guidance and related arrangements
Primary guidance 1
Primary guidance 2
Health and Safety Management Systems
Crownway document overview
Primary guidance checked 10 November 2026 for the described arrangements. Linked legal-register entries keep their own review dates and territorial conditions. Guidance, ACOPs, company controls and direct statutory duties are distinct.
Primary references: comah | fireandexplosion