Temporary works coordination and permit procedure

BOUK-PRO-TW · v1.0 · Completed fictional example · DOCX

Maintain a register and design briefs, confirm checks and release hold points before loading or striking.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PRO-TW | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Maintain a register and design briefs, confirm checks and release hold points before loading or striking.

Scope and operating responsibility

We apply this procedure to Propping, scaffold, hoarding and excavation support. Evidence includes Temporary-works register; brief; design and check evidence; erection inspection; load/alter/dismantle release; change record. The role controlling the task checks applicability before mobilisation and whenever the scope changes.

RoleRequired action
Temporary works coordinatorOwn this arrangement, confirm competent support and maintain its evidence trail.
Project manager and Site managerCoordinate the actual package, provide resources and verify prerequisites before release; resolve occupied and subcontractor interfaces.
Trade supervisor and workersUse the accepted current method, demonstrate understanding, report changes and stop when critical safeguards are uncertain.
Competent specialist and H&S adviserProvide technical advice within competence; challenge evidence and identify limitations. Management retains the operating decision.

Inputs before using the procedure

Use the current project risk register, relevant survey and design revisions, equipment or product information, worker consultation and the task-specific records listed below. Resolve conflicting or missing information before relying on it. Do not fill missing technical values from an example.

How we carry out the arrangement

1 Plan and obtain reliable information

The Temporary Works Coordinator maintains a register covering propping, formwork, falsework, scaffold, hoarding, excavation support and working platforms as applicable to the project.

2 Verify capability and prerequisites

The brief defines loading, ground or supporting structure, sequence, interfaces and duration. A competent design and required checking are accepted before erection or use.

3 Control work and interfaces

Erection is checked against the accepted design, with formal permission to load, alter or dismantle where the project process requires it. Trade supervisors do not accept field alterations without design review.

4 Review change and safe handback

Inspection and change controls consider weather, impact, adjacent excavation and changed loading. The permanent and temporary conditions remain stable at every stage.

Stop restrict and restart

Hold loading, alteration or dismantling when a design, check, foundation, bracing, connection or sequence requirement is uncertain or no longer met.

The person controlling the work makes the affected area safe and notifies the Site Manager. Restart requires the competent technical decision for the actual control, the authorised work-release decision and a fresh briefing of affected people. Record unresolved limits; an updated date or a completed form does not remove a hold.

Practical control detail

Higher-risk construction work should pass through clear control gates before work starts, when conditions change and before work is handed back.

For temporary works, connect each register item to its current design, checking evidence, erection inspection and permission to load, alter or dismantle. The coordinator checks that the installed arrangement and loading sequence match the accepted revision before the next stage is released.

Evidence follow up and learning

Worked decision trail

Fictional situationDecision and evidence
What changesA trade wants to remove a prop to improve delivery access.
ResponseThe Temporary Works Coordinator prohibits alteration until the competent designer and checking route resolve stability and sequence.
VerificationCheck installed configuration against the accepted revision before the altered stage is released.

Supporting arrangement documents

ReferenceHow the document is used
BOUK-REG-TW-01
Temporary works register and design-category record
Identify each temporary works item, design/check needs and status.
BOUK-FRM-TW-01
Temporary works design brief and check certificate
Capture loads, assumptions, interfaces, design/check responsibilities and approval.
BOUK-CHK-TW-01
Temporary works erection/conformance inspection
Verify constructed work matches design and required inspections.
BOUK-PTW-TW-01
Temporary works permit to load / bring into use
Record competent release after prerequisites and hold points are satisfied.
BOUK-PTW-TW-02
Temporary works permit to strike / dismantle
Confirm strength/stability, sequencing and authority before removal.
BOUK-RAMS-TW-01
Concrete placement, pumping and formwork RAMS
Temporary support, hose-whip/pressure, cement contact, access and concrete placement sequence.

Retain the record ID, task, location, competent author, revision, date, decision, restrictions, action owner and separate effectiveness evidence. Restrict personal and health information and apply the relevant retention rule. File genuine results separately from teaching examples.

Guidance Foundations of Construction Health and Safety Management · Scaffolding Safety

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.