Contractor selection, onboarding and coordination procedure

BOUK-PRO-SUB · v1.0 · Completed fictional example · DOCX

Evaluate capability, agree responsibilities and RAMS, monitor performance and change subcontractors safely.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PRO-SUB | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Evaluate capability, agree responsibilities and RAMS, monitor performance and change subcontractors safely.

Scope and operating responsibility

We apply this procedure to Scaffolding, asbestos or demolition subcontractor. Evidence includes Package scope; capability assessment; procurement specification; mobilisation checks; monitoring findings; technical hand-back. The role controlling the task checks applicability before mobilisation and whenever the scope changes.

RoleRequired action
Contracts / operations managerOwn this arrangement, confirm competent support and maintain its evidence trail.
Project manager and Site managerCoordinate the actual package, provide resources and verify prerequisites before release; resolve occupied and subcontractor interfaces.
Trade supervisor and workersUse the accepted current method, demonstrate understanding, report changes and stop when critical safeguards are uncertain.
Competent specialist and H&S adviserProvide technical advice within competence; challenge evidence and identify limitations. Management retains the operating decision.

Inputs before using the procedure

Use the current project risk register, relevant survey and design revisions, equipment or product information, worker consultation and the task-specific records listed below. Resolve conflicting or missing information before relying on it. Do not fill missing technical values from an example.

How we carry out the arrangement

1 Plan and obtain reliable information

Contracts Managers specify the actual package risks and assess a subcontractor’s competence, organisational capability, resources, supervision and relevant previous performance. Insurance or an accreditation alone is insufficient.

2 Verify capability and prerequisites

Design responsibility, RAMS, specialist licences where applicable, plant suitability, inspection evidence and emergency interfaces are agreed before mobilisation. Subcontracting onward requires equivalent checks.

3 Control work and interfaces

The Site Manager coordinates simultaneous work, occupied boundaries, deliveries, isolations and permits, and observes compliance at the work front. Selection does not transfer Build Out’s coordination duties.

4 Review change and safe handback

Purchasing considers safe use, maintenance access, compatibility, exposure information and lifecycle costs. A substitution or changed package is reviewed before acceptance.

Stop restrict and restart

Hold appointment, delivery or work when necessary competence, safeguards, technical information or coordinated arrangements cannot be demonstrated.

The person controlling the work makes the affected area safe and notifies the Site Manager. Restart requires the competent technical decision for the actual control, the authorised work-release decision and a fresh briefing of affected people. Record unresolved limits; an updated date or a completed form does not remove a hold.

Practical control detail

Scope, capability, shared hazards, site method, monitored work and hand-back are connected decisions. A change of scope or subcontractor can reopen an earlier gate.

Use the contractor RAMS and any required permits to coordinate a verified method. The Site Manager checks the actual isolation, barriers and competent team at the workface before release; a contractor signature alone does not demonstrate those controls.

Evidence follow up and learning

Worked decision trail

Fictional situationDecision and evidence
What changesA contractor proposes a different subcontractor for a safety-critical package.
ResponseThe Contracts Manager holds mobilisation while capability, supervision, scope and interfaces are reassessed.
VerificationMatch the personnel and method at the workface to the accepted package evidence.

Supporting arrangement documents

ReferenceHow the document is used
BOUK-CHK-SUB-01
Contractor prequalification and capability review
Assess competence, resources, previous performance and scope-specific controls.
BOUK-FRM-SUB-01
Subcontractor scope and safety-interface agreement
Define supplied information, shared facilities, supervision and emergency responsibilities.
BOUK-CHK-SUB-02
Supplier and hired-equipment acceptance checklist
Verify specifications, operating instructions, inspection evidence and support.
BOUK-FRM-SUB-02
Contractor performance and escalation review
Record performance, recurring concerns and corrective actions.
BOUK-CHK-SUB-03
Material/product substitution safety review
Check changed hazards, installation method and compatibility before substitution.

Retain the record ID, task, location, competent author, revision, date, decision, restrictions, action owner and separate effectiveness evidence. Restrict personal and health information and apply the relevant retention rule. File genuine results separately from teaching examples.

Guidance How should contractors and supply chains be managed safely? · Provision and Use of Work Equipment (PUWER)

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.