SHAREhub home

Lift planning, equipment acceptance and examination procedure

BOUK-PRO-LIFT · v1.0 · Completed fictional example · DOCX

Categorise lifts, plan load/path/ground/interface controls and verify examination evidence.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PRO-LIFT | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Categorise lifts, plan load/path/ground/interface controls and verify examination evidence.

Scope and operating responsibility

We apply this procedure to Crane lift of rooftop air-handling equipment. Evidence includes Lift plan; ground and load information; equipment and accessory examinations; appointed roles; pre-lift briefing and hand-back. The role controlling the task checks applicability before mobilisation and whenever the scope changes.

RoleRequired action
Authorised specialist / appointed personOwn this arrangement, confirm competent support and maintain its evidence trail.
Project manager and Site managerCoordinate the actual package, provide resources and verify prerequisites before release; resolve occupied and subcontractor interfaces.
Trade supervisor and workersUse the accepted current method, demonstrate understanding, report changes and stop when critical safeguards are uncertain.
Competent specialist and H&S adviserProvide technical advice within competence; challenge evidence and identify limitations. Management retains the operating decision.

Inputs before using the procedure

Use the current project risk register, relevant survey and design revisions, equipment or product information, worker consultation and the task-specific records listed below. Resolve conflicting or missing information before relying on it. Do not fill missing technical values from an example.

How we carry out the arrangement

1 Plan and obtain reliable information

A competent lifting planner establishes the load, lifting points, radius, configuration, ground and support conditions, route and landing area for rooftop plant and other lifts. Unknown load weight is resolved before lifting.

2 Verify capability and prerequisites

The appointed supervisory and slinging/signalling roles are defined for the lift. Equipment and accessories have appropriate inspection and thorough-examination evidence and are suitable for the actual configuration.

3 Control work and interfaces

The team coordinates overhead and buried services, public and occupied-building boundaries, weather, communications and exclusion. Nobody improvises a lifting point or stands beneath a suspended load.

4 Review change and safe handback

Changes to crane position, load, ground, path or wind conditions reopen the lifting plan and authorisation. The responsible person checks safe landing and release before removing restraints.

Stop restrict and restart

Stop a lift when load information, ground capacity, accessory suitability, communication, exclusion or a critical condition differs from the accepted plan.

The person controlling the work makes the affected area safe and notifies the Site Manager. Restart requires the competent technical decision for the actual control, the authorised work-release decision and a fresh briefing of affected people. Record unresolved limits; an updated date or a completed form does not remove a hold.

Practical control detail

Plan the load, route, equipment, people and failure response before anyone attaches a hook or starts a truck.

Remove the need for hazardous handling where feasible, then select equipment and controls for the residual lift.

Evidence follow up and learning

Worked decision trail

Fictional situationDecision and evidence
What changesFoundry receives a plant load whose weight differs from the lift plan.
ResponseThe lifting supervisor holds the lift and returns the load and equipment configuration to the competent planner.
VerificationVerify the revised load information, ground basis, accessories and team briefing before lifting.

Supporting arrangement documents

ReferenceHow the document is used
BOUK-PLN-LIFT-01
Lifting operation plan
Define load, equipment, configuration, ground support, people, communications and exclusion zones.
BOUK-RA-LIFT-01
Lifting interface and ground-bearing assessment
Assess overturn, suspended loads, public interfaces, weather and adjacent structures.
BOUK-REG-LIFT-01
Lifting equipment and accessory examination register
Track identification, examination reports, intervals and defects.
BOUK-CHK-LIFT-01
Lift readiness and pre-use equipment check
Verify the agreed plan, competent team, load path and equipment before lifting.
BOUK-FRM-LIFT-01
Lift briefing, deviation and completion record
Record authorisation, unexpected changes and handback.
BOUK-RAMS-LIFT-01
Structural steel erection and bolting RAMS
Lift sequence, stability, temporary bracing, work at height and falling objects.
BOUK-RAMS-LIFT-02
Glazing, windows and large doors RAMS
Fragile loads, mechanical handling, suction equipment, cuts and falling objects.
BOUK-RAMS-LIFT-03
Mechanical plant and HVAC installation RAMS
Load movement, supports, overhead work, manual handling and commissioning interfaces.

Retain the record ID, task, location, competent author, revision, date, decision, restrictions, action owner and separate effectiveness evidence. Restrict personal and health information and apply the relevant retention rule. File genuine results separately from teaching examples.

Guidance Load-Handling Equipment and Lifting Operations

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.