Traffic management and delivery logistics plan

BOUK-PLN-TRAF-01 · v1.0 · Completed fictional example · DOCX

Separate pedestrians/vehicles, control reversing, loading and route changes.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PLN-TRAF-01 | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Separate pedestrians/vehicles, control reversing, loading and route changes.

Example project context

This plan belongs to the fictional 2027 BuildOut portfolio: Eastfield commercial refurbishment, Harbour retail fit out, Foundry light-industrial build and Meadow residential development. Apply the stated arrangements only to the relevant task and phase. The example has no real site address, named staff or technical certification. Project-specific engineering, exposure and rescue information remains a prerequisite to genuine work release.

Plan controlCompleted example arrangement
Accountable roleSite manager coordinates the plan and confirms competent deputies.
Activities and interfacesRestricted urban fit-out delivery compound
Risk and policy linkBOUK-POL-TRAF and the current task register; map affected work packages before release.
Resources and timingProject manager confirms competent people, equipment, welfare, time and specialist input before the relevant phase. Site manager reviews the next eight weeks at weekly coordination.
Change routeChanged scope, equipment, sequence, people or site conditions reopen the affected plan and task release.

Delivery stages responsibilities and evidence

When and ownerCompleted arrangementEvidence required
Before appointment
Site manager
Plan restricted urban deliveries with the supplier, project team and occupier before booking. Prefer physical separation of people and vehicles, reduced reversing and controlled delivery times.Logistics plan; delivery booking and driver briefing; segregation checks; unloading method; public/occupier coordination and vehicle departure
Before mobilisation
Project manager and competent specialist
The Site Manager checks ground and access, pedestrian routes, public crossings, loading stability, overhead clearance, visibility and emergency access for the actual vehicle and load.Logistics plan; delivery booking and driver briefing; segregation checks; unloading method; public/occupier coordination and vehicle departure
At each relevant work stage
Site manager and Trade supervisor
A competent traffic marshal is used only within the planned method and safe position; visibility clothing or a banksman does not replace practicable physical segregation.Logistics plan; delivery booking and driver briefing; segregation checks; unloading method; public/occupier coordination and vehicle departure
After change or before handback
Site manager and competent reviewer
The driver and receiving supervisor agree unloading, lifting, restraint release and safe departure. Changes to public access or neighbouring activities reopen the logistics plan.Logistics plan; delivery booking and driver briefing; segregation checks; unloading method; public/occupier coordination and vehicle departure

Hold points and safe release

Stop movements or unloading when people enter the exclusion area, communication or visibility is lost, access is unsuitable or the planned receiving controls are absent.

At a failed prerequisite, the supervisor holds the affected work and protects people. The Site Manager records the boundary and communicates it to adjacent teams. The competent specialist resolves technical conditions; the authorised operating role checks implementation, briefs changes and records the release conditions. Recheck a later change rather than extending an expired acceptance automatically.

Specific plan arrangements

Route design

The Site manager separates pedestrians, public routes, delivery receiving and plant circulation before booking vehicles. Prefer a workable one-way arrangement and eliminate unnecessary reversing where practicable.

Booking and waiting

The delivery coordinator confirms vehicle/load details, receiving capacity and a safe permitted waiting location. Full unloading space means a hold or revised slot, not an unassessed public-road queue.

Physical checks

Verify actual ground, structural support, overhead clearance, visibility, lighting, pedestrian barriers, crossings and responder access. A marshal or high-visibility clothing does not replace practicable physical segregation.

Unloading

Driver and receiving supervisor agree stable positioning, load restraint release, suitable equipment and exclusions. The competent marshal uses the planned safe position and communication.

Change and stop

Stop movement when people enter an exclusion, visibility/communication fails or a route becomes unsuitable. Any revised route is assessed, installed, briefed and checked before use.

Effectiveness

Observe busy receiving periods and different shifts. The March route finding in the assurance plan requires representative delivery checks after the revised physical arrangement is installed.

Practical application and review

Worked decision trail

Fictional situationDecision and evidence
What changesAn unloading vehicle blocks the protected pedestrian route.
ResponseThe Site Manager stops that unloading arrangement and changes physical routing and delivery coordination.
VerificationObserve two representative deliveries on different days and reopen the action if segregation fails.

How can the ISO 45001 hierarchy of controls prevent vehicle collisions during workplace transport and work journeys

Remove the hazard where reasonably practicable. If it remains, consider a safer method, engineering controls and safe work arrangements before personal protective equipment for residual risk.

When must mobile plant or lift truck work stop

Stop if a person is in the operating zone, the route or ground is unsafe, visibility fails, a load is unstable or a critical vehicle defect is unresolved.

Assurance and update cycle

Supervisors check the controls before relevant work and after change. The Site Manager samples implementation during actual work; the H&S adviser challenges recurring gaps and the plan owner reviews the resulting evidence. Specialist and statutory inspections retain their own competent methods and required intervals. Actions need both completion evidence and a separate effectiveness check; reopen a failed change.

Related SHARE guidance

Guidance Workplace Transport and Work-Related Driving · Mobile plant and vehicles · Loading, Unloading and Transfer Operations

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.