Demolition / dismantling written arrangements

BOUK-PLN-DEM-01 · v1.0 · Completed fictional example · DOCX

Set competent method, sequence, stability, exclusion, services, dust and emergency controls.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PLN-DEM-01 | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Set competent method, sequence, stability, exclusion, services, dust and emergency controls.

Example project context

This plan belongs to the fictional 2027 BuildOut portfolio: Eastfield commercial refurbishment, Harbour retail fit out, Foundry light-industrial build and Meadow residential development. Apply the stated arrangements only to the relevant task and phase. The example has no real site address, named staff or technical certification. Project-specific engineering, exposure and rescue information remains a prerequisite to genuine work release.

Plan controlCompleted example arrangement
Accountable roleProject manager coordinates the plan and confirms competent deputies.
Activities and interfacesInternal soft strip and structural wall removal
Risk and policy linkBOUK-POL-DEM and the current task register; map affected work packages before release.
Resources and timingProject manager confirms competent people, equipment, welfare, time and specialist input before the relevant phase. Site manager reviews the next eight weeks at weekly coordination.
Change routeChanged scope, equipment, sequence, people or site conditions reopen the affected plan and task release.

Delivery stages responsibilities and evidence

When and ownerCompleted arrangementEvidence required
Before appointment
Project manager
The Project Manager obtains competent structural and services information, asbestos survey information and the required written demolition or alteration arrangements before disturbance.Survey and structural information; written sequence; temporary support; isolation; monitoring and exclusion checks; change and completion handover
Before mobilisation
Project manager and competent specialist
The sequence maintains stability of the structure and adjacent areas, including temporary support, load paths and occupied boundaries. A removed wall or altered connection is not assumed non-structural.Survey and structural information; written sequence; temporary support; isolation; monitoring and exclusion checks; change and completion handover
At each relevant work stage
Site manager and Trade supervisor
Isolation, dust control, waste handling, exclusion and access are coordinated through the work stages. Mechanical methods and plant are selected for the actual reach, loading and collapse conditions.Survey and structural information; written sequence; temporary support; isolation; monitoring and exclusion checks; change and completion handover
After change or before handback
Site manager and competent reviewer
An unexpected material, structural detail, live service or visible movement triggers withdrawal, restriction and competent redesign of the sequence.Survey and structural information; written sequence; temporary support; isolation; monitoring and exclusion checks; change and completion handover

Hold points and safe release

Stop demolition or alteration at an unexplained structural condition, uncontrolled exposure, failed isolation, loss of exclusion or deviation from the accepted sequence.

At a failed prerequisite, the supervisor holds the affected work and protects people. The Site Manager records the boundary and communicates it to adjacent teams. The competent specialist resolves technical conditions; the authorised operating role checks implementation, briefs changes and records the release conditions. Recheck a later change rather than extending an expired acceptance automatically.

Specific plan arrangements

Survey and scope

The Eastfield example separates non-structural strip out from structural alteration. Competent structural, asbestos and service information must cover the exact stage before disturbance.

Written sequence

The competent method defines stable intermediate conditions, temporary support, equipment positions, debris loading, access and occupied/public exclusion. Each released stage has a defined stopping point.

Preparation

Verify service isolation, accepted support, controlled access, dust prevention, waste routes and emergency arrangements before the team starts. Unknown connections or material remain held.

During dismantling

Work only within the accepted method and stage. The supervisor checks stability, movement, interfaces and loading. A field alteration is referred back to competent design rather than improvised.

Emergency and change

Withdraw from unexpected movement, failed isolation, suspect asbestos or loss of exclusion. Protect surrounding areas and seek the relevant specialist response; avoid entering unstable areas for an improvised rescue.

Stage closeout

Competent inspection confirms the safe residual structure and remaining restrictions before the next stage or handover. Retain the actual sequence revision and release evidence.

Practical application and review

Worked decision trail

Fictional situationDecision and evidence
What changesSoft strip exposes an unexpected structural connection.
ResponseWork stops at that stage; the structure is protected and competent structural advice revises the dismantling sequence.
VerificationVerify the revised support, isolation and exclusion before briefing and releasing the next stage.

Check the changing load path and occupied boundary

A demolition stage can affect adjoining structures, debris loading and public access. A changed condition returns to competent review rather than an assumed next step.

How should demolition be planned under CDM

Demolition should be planned as a construction project with competent duty holders, adequate information and a written safe system of work.

Assurance and update cycle

Supervisors check the controls before relevant work and after change. The Site Manager samples implementation during actual work; the H&S adviser challenges recurring gaps and the plan owner reviews the resulting evidence. Specialist and statutory inspections retain their own competent methods and required intervals. Actions need both completion evidence and a separate effectiveness check; reopen a failed change.

Related SHARE guidance

Guidance Demolition and dismantling safety

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.