BOUK-PLN-COMP-01 · v1.0 · Completed fictional example · DOCX

Prioritise competence gaps and mandatory/specialist training by actual activities.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PLN-COMP-01 | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Prioritise competence gaps and mandatory/specialist training by actual activities.

Example project context

This plan belongs to the fictional 2027 BuildOut portfolio: Eastfield commercial refurbishment, Harbour retail fit out, Foundry light-industrial build and Meadow residential development. Apply the stated arrangements only to the relevant task and phase. The example has no real site address, named staff or technical certification. Project-specific engineering, exposure and rescue information remains a prerequisite to genuine work release.

Plan controlCompleted example arrangement
Accountable rolePeople / training coordinator coordinates the plan and confirms competent deputies.
Activities and interfacesUpcoming demolition project and first-aid cover
Risk and policy linkBOUK-POL-COMP and the current task register; map affected work packages before release.
Resources and timingProject manager confirms competent people, equipment, welfare, time and specialist input before the relevant phase. Site manager reviews the next eight weeks at weekly coordination.
Change routeChanged scope, equipment, sequence, people or site conditions reopen the affected plan and task release.

Delivery stages responsibilities and evidence

When and ownerCompleted arrangementEvidence required
Before appointment
People / training coordinator
HR and the Project Manager define the capability needed for each role, including design, supervision, excavator operation, slinging and signalling, temporary works and asbestos-related work. Qualifications, practical experience, current knowledge and supervision are considered together.Role competence matrix; appointment and licence checks where relevant; observed task assessments; familiarisation; supervision and reassessment records
Before mobilisation
Project manager and competent specialist
Task authorisation is limited to the actual plant, configuration and activity. The Site Manager verifies familiarisation and observed performance; attendance on a course alone does not authorise independent work.Role competence matrix; appointment and licence checks where relevant; observed task assessments; familiarisation; supervision and reassessment records
At each relevant work stage
Site manager and Trade supervisor
New starters, apprentices, agency staff and unfamiliar subcontractors receive induction, task instruction and proportionate supervision. Accessible briefings address language and literacy needs without assuming comprehension.Role competence matrix; appointment and licence checks where relevant; observed task assessments; familiarisation; supervision and reassessment records
After change or before handback
Site manager and competent reviewer
A changed machine, task, role, absence, incident or poor performance prompts reassessment. A manager names a capable replacement before an essential role holder is absent.Role competence matrix; appointment and licence checks where relevant; observed task assessments; familiarisation; supervision and reassessment records

Hold points and safe release

Do not allocate unsupervised work when competence or authority is uncertain; maintain a supervised learning arrangement or appoint a competent alternative.

At a failed prerequisite, the supervisor holds the affected work and protects people. The Site Manager records the boundary and communicates it to adjacent teams. The competent specialist resolves technical conditions; the authorised operating role checks implementation, briefs changes and records the release conditions. Recheck a later change rather than extending an expired acceptance automatically.

Specific plan arrangements

Mobilisation review

Each Project manager maps roles to actual packages and equipment before mobilisation. The People coordinator records qualifications, current knowledge, relevant experience, practical assessment and required supervision; certificates alone do not establish task capability.

January to March

Prioritise groundworks service locating, plant/attachment familiarisation, temporary works and refurbishment survey boundaries. Supervisors check new starters and changed plant before unsupervised allocation.

April to June

Review frame and lifting roles, access equipment, rescue readiness, occupied fit-out coordination and commissioning authority. Plan competent deputies before leave or absence creates a gap.

July to September

Assess incoming subcontractor and agency teams at the actual task. Revisit roof, finishing, exposure-control and handover competence when packages change.

October to December

Review winter tasks, emergency cover, services commissioning and long-shift driving. Use audit failures and observed practice to set the next programme rather than renewing attendance automatically.

Effectiveness and restrictions

The competent assessor observes a representative task and records the capability demonstrated, limits and next review trigger. No unsupervised authorisation is issued where required evidence is missing; supervised learning has an explicit capable supervisor and safe task boundary.

Practical application and review

Worked decision trail

Fictional situationDecision and evidence
What changesAn experienced operator receives an unfamiliar attachment.
ResponseThe Site Manager limits operation until equipment-specific familiarisation and observed capability are demonstrated.
VerificationRetain the assessor evidence and confirm the authorisation names the actual attachment and task.

How can the ISO 45001 hierarchy of controls reduce risks for young and inexperienced workers

Remove or reduce the hazard through task choice, safer methods and physical safeguards before relying on supervision or personal protective equipment. Check the young-person restrictions separately; ordinary adult arrangements may not be enough.

How do we manage and review young worker controls

A management system should assign control owners, resource supervision, involve the young person and check that safeguards work as tasks change. A system document does not make a restricted task lawful.

Assurance and update cycle

Supervisors check the controls before relevant work and after change. The Site Manager samples implementation during actual work; the H&S adviser challenges recurring gaps and the plan owner reviews the resulting evidence. Specialist and statutory inspections retain their own competent methods and required intervals. Actions need both completion evidence and a separate effectiveness check; reopen a failed change.

Related SHARE guidance

Guidance How should competence, training, information and supervision be managed? · Young Worker

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.