SHAREhub home

Construction phase plan

BOUK-PLN-CDM-01 · v1.0 · Completed fictional example · DOCX

Set project health and safety arrangements, site rules and specific high-risk measures before construction starts.

Download editable DOCXView this policy branch

Read-only preview. Use the downloaded native file for your own working copy. Examples are fictional; signatures, work releases and operational evidence remain separate.

BOUK-PLN-CDM-01 | Version 1.0 | 23 October 2026 | GB baseline

COMPLETED FICTIONAL EXAMPLE. BuildOut UK Ltd is an illustrative construction business. The arrangements and cases below are examples for adaptation; no actual work, approval or signature is represented.

Set project health and safety arrangements, site rules and specific high-risk measures before construction starts.

Example project context

This plan belongs to the fictional 2027 BuildOut portfolio: Eastfield commercial refurbishment, Harbour retail fit out, Foundry light-industrial build and Meadow residential development. Apply the stated arrangements only to the relevant task and phase. The example has no real site address, named staff or technical certification. Project-specific engineering, exposure and rescue information remains a prerequisite to genuine work release.

Plan controlCompleted example arrangement
Accountable roleProject manager coordinates the plan and confirms competent deputies.
Activities and interfacesSmall single-contractor job or multi-contractor fit-out
Risk and policy linkBOUK-POL-CDM and the current task register; map affected work packages before release.
Resources and timingProject manager confirms competent people, equipment, welfare, time and specialist input before the relevant phase. Site manager reviews the next eight weeks at weekly coordination.
Change routeChanged scope, equipment, sequence, people or site conditions reopen the affected plan and task release.

Delivery stages responsibilities and evidence

When and ownerCompleted arrangementEvidence required
Before appointment
Project manager
For every job the Project Manager records who is client, designer, principal designer, principal contractor and contractor as applicable. Build Out accepts only the roles actually appointed and within its organisational capability.Appointment and capability checks; pre-construction information; construction phase plan; coordination minutes; design-change and handover records
Before mobilisation
Project manager and competent specialist
Pre-construction information, design risks, asbestos information, services, access and occupied-building constraints are reviewed before the construction phase plan and package methods are released.Appointment and capability checks; pre-construction information; construction phase plan; coordination minutes; design-change and handover records
At each relevant work stage
Site manager and Trade supervisor
The whole project is considered when deciding whether more than one contractor is involved, including sequential trades. Notification, building-control duties and the construction phase plan are distinct decisions; one does not substitute for another.Appointment and capability checks; pre-construction information; construction phase plan; coordination minutes; design-change and handover records
After change or before handback
Site manager and competent reviewer
Work-front reviews coordinate subcontractors and design changes, keep welfare and public separation effective, and pass necessary residual information into handover and the health and safety file where required.Appointment and capability checks; pre-construction information; construction phase plan; coordination minutes; design-change and handover records

Hold points and safe release

Do not start construction without an adequate project-specific plan, confirmed dutyholder arrangements and the information and resources necessary for safe delivery.

At a failed prerequisite, the supervisor holds the affected work and protects people. The Site Manager records the boundary and communicates it to adjacent teams. The competent specialist resolves technical conditions; the authorised operating role checks implementation, briefs changes and records the release conditions. Recheck a later change rather than extending an expired acceptance automatically.

Specific plan arrangements

Project and programme

Harbour is an invented occupied retail fit-out, S02, active January to June 2027. Enabling work and evening fit-out run January to April, commissioning in May and client handover in June. The principal contractor role is assumed for this teaching scenario only; real appointments and project scope must be confirmed.

Dutyholders and information

The example client retains control of trading areas; BuildOut coordinates the construction phase. The Project manager checks client and design appointments, actual contractor count, surveys, services and design constraints before mobilisation. Keep the principal designer and client informed of residual risks and changes; do not infer a dutyholder appointment from this example.

Site zones and access

Zone A is the controlled work area, Zone B the protected occupier route, Zone C welfare and Zone D the booked receiving area. The Site manager walks the boundaries with the occupier before each phase. These labels are fictional layout references; a real plan needs the current site drawing, access dimensions and emergency-service location.

People and supervision

The Site manager appoints a competent Trade supervisor for each active package and confirms evening cover. Visitors are authorised and accompanied. Induction explains current boundaries, occupied routes, asbestos uncertainty, reporting, welfare and emergency actions. Supervisors test understanding at the actual workface.

Surveys and intrusive work

Ceiling, wall, floor and service penetration packages remain held until survey and design coverage match the exact footprint. Uninspected voids are not treated as asbestos-free. Unknown structural elements or services stop the affected stage and return to competent review.

High-risk stages

Separate releases cover intrusive work, temporary stability, work at height, lifting, hazardous-energy isolation, hot work and commissioning as applicable. Each requires its specific assessment, method and competent evidence. A general RAMS review or F10 decision does not release these stages.

Deliveries and trade coordination

Deliveries use booked slots and a receiving supervisor; a delivery waits only in an agreed safe location. Separate pedestrians physically from unloading and avoid unnecessary reversing. The evening coordination meeting checks ceiling work, mobile access, service work and occupier movements together.

Health exposure control

Specify safer products and lower-dust processes before purchase. Drilling and cutting use suitable source controls and residual RPE where required; noise, vibration, handling and skin exposure are assessed for the actual duration and method. Stop failed extraction or an unassessed product substitution.

Welfare and work environment

Usable toilets, washing, drinking water, rest/changing arrangements as required, lighting, safe access and cleaning are available from the start of construction. The Site manager checks provision for the actual numbers and evening shift; relocation cannot leave a gap.

Fire occupied interfaces and emergencies

The Site manager and occupier agree escape routes, alarm arrangements, assistance, responder access and temporary impairments before each phase. The construction team raises the alarm, moves to the designated safe assembly arrangement and accounts for workers; emergency assistance uses the verified site address and access information. No universal fire-watch period is specified.

Consultation and change

Workers can raise concerns during daily briefings and coordination meetings; urgent risks are acted on immediately. A changed layout, shift, scope or service state returns to the affected assessment and CPP section before use. The manager communicates the decision to all affected trades and the occupier.

Monitoring and learning

Supervisors check live tasks before work and after change. The Site manager completes weekly field inspections and monthly risk-led observations; the assurance plan schedules an April full site/interface audit and June closeout. Failed critical controls are restricted immediately; lasting action needs an effectiveness test.

Commissioning and handover

May commissioning is staged through competent isolation, testing and controlled energisation. The June closeout checks residual hazards, as-built services, safe maintenance access, specialist handback and the agreed health and safety file information. Outstanding safety-critical items retain named owners and restrictions.

Practical application and review

Worked decision trail

Fictional situationDecision and evidence
What changesHarbour retail fit out shares escape routes with an occupied trading area.
ResponseThe Project Manager agrees phased segregation and escape arrangements with the client before ceiling works start. Notification is assessed separately.
VerificationWalk the route during the planned evening shift and reconcile the CPP with the current trade sequence.

Coordinate the project before work begins

Client information, design coordination and construction-phase planning form a connected route. Notification is a separate check, rather than permission to start unsafe work.

Match the plan to current work

A useful small-job plan connects people, sequence, controls, welfare and emergency access to the actual site. Update it when conditions change.

Assurance and update cycle

Supervisors check the controls before relevant work and after change. The Site Manager samples implementation during actual work; the H&S adviser challenges recurring gaps and the plan owner reviews the resulting evidence. Specialist and statutory inspections retain their own competent methods and required intervals. Actions need both completion evidence and a separate effectiveness check; reopen a failed change.

Related SHARE guidance

Guidance What are the Construction Design and Management Regulations? · What should a construction phase plan include?

Content basis

Built from the BuildOut policy and arrangement register, the SHARE policy/risk/routine-checklist/audit databases and the linked SHAREknowledge topics.

Register legal summaries retain their own review dates. No actual inspection, clinical record, specialist certificate or company approval is represented.