Leading and lagging process safety indicators

CWF-REG-MON-01 · Blank register with separate fictional worked entries · Owner role: Process safety and COMAH lead

Fictional arrangement or blank working master. No actual approval, site authorisation or completed evidence is supplied.

This preview shows saved worksheet values. Edit the downloaded workbook to use its formulas, filters and validation.

Register

Leading and lagging process safety indicators
Crownway Fuels Ltd. CWF-REG-MON-01. Version 1.0. Blank working master. Enter actual facts and evidence.
OwnerProcess safety and COMAH leadAs at date
Records0Rows with alerts0
Editable A:H. Calculated I lists missing fields, invalid dates/status, duplicate IDs and passed review dates. A clear alert cell does not verify a control or authorise work.
Record required detail in column C: Definition; Numerator/denominator; Data source; Accountable owner; Threshold and required response
Read Guide before use. Set a valid As at date. Twenty rows are available; the default blank print view shows six. Keep stable IDs and evidence together when sorting.
Record IDActual site asset and subjectRequired technical or decision detailsDecision restriction and actionEvidence reference and ownerReview dueAction statusVerification evidence and limitsRecord alerts
Keep the actual retention rule and access class with the evidence. Preserve statutory minima, permit conditions and legal holds. Extend the table, formulas, validation, summaries and print area together and test the new last row.
SHARE homeGuide and worked examples are separate from real records. Save your own operational copy before entering data.

Worked examples

Leading and lagging process safety indicators
Crownway Fuels Ltd. CWF-REG-MON-01. Version 1.0. Fictional examples. No operational evidence.
OwnerProcess safety and COMAH lead2026-11-10 00:00:00As at date
Records2Rows with alerts2
Editable A:H. Calculated I lists missing fields, invalid dates/status, duplicate IDs and passed review dates. A clear alert cell does not verify a control or authorise work.
Record required detail in column C: Definition; Numerator/denominator; Data source; Accountable owner; Threshold and required response
Read Guide before use. Set a valid As at date. Twenty rows are available; the default blank print view shows six. Keep stable IDs and evidence together when sorting.
Record IDActual site asset and subjectRequired technical or decision detailsDecision restriction and actionEvidence reference and ownerReview dueAction statusVerification evidence and limitsRecord alerts
EX-MON-01Illustrative Leading and lagging process safety indicatorsHold. Actual details and evidence not established.Process safety and COMAH lead; invented reference EX-012026-11-17 00:00:00OpenMissing C;
EX-MON-02Second illustrative decisionDefinition; Numerator/denominator; Data source; Accountable owner; Threshold and required responseImplemented change awaiting review; no release asserted.Process safety and COMAH lead; invented reference EX-022026-11-09 00:00:00ImplementedEffectiveness remains unverified.Review date passed;
Keep the actual retention rule and access class with the evidence. Preserve statutory minima, permit conditions and legal holds. Extend the table, formulas, validation, summaries and print area together and test the new last row.
SHARE homeGuide and worked examples are separate from real records. Save your own operational copy before entering data.

Guide

Leading and lagging process safety indicators guide
PurposeProvide the site/task-specific leading and lagging process safety indicators and retain its controlled output.
ScopeBULK; HQ; RETAIL. Apply where the site/activity/hazard is present; confirm in the site applicability assessment. Ten English petrol/diesel forecourts and convenience shops, HQ and mobile support. The additional bulk establishment is a separate illustrative scenario. Inventory, regulatory applicability, permissions and site-specific acceptance are unresolved.
ResponsibilityProcess safety and COMAH lead maintains current entries, unresolved restrictions and supporting evidence. No named person is appointed by this example.
Required detailsDefinition; Numerator/denominator; Data source; Accountable owner; Threshold and required response
How to useRegister is blank. Worked examples contains two invented open records, including missing details and a passed review date. Complete actual A:H inputs and retain the detailed technical record separately.
Preparing the activityChoose indicators from the major risks and critical-control functions, with an owner, definition, numerator, denominator, source, response threshold and review frequency. Include both failures and evidence that preventive work is completed effectively.
Operating arrangementShift staff check current operating conditions and record impairments. Area management challenges a sample in the field; the independent audit programme tests whether the monitoring system itself is reliable.
VerificationInvestigate missed tests, bypasses, repeated alarms, weak handovers and overdue actions. A favourable injury rate or completed-checklist percentage must not conceal unavailable process protection.
Worked decisionThe dashboard shows all inspections completed, but one test record contains only a work-order closure. The HSE lead removes the unsupported effectiveness claim, engineering checks the actual protection and management reviews the data definition and similar records.
Stop and escalationEscalate any red-limit breach or failed critical barrier immediately; restrict affected work rather than waiting for a monthly dashboard meeting.
Record alertsAlerts identify gaps A=ID, B=scope/subject, C=required detail, D=decision/action, E=evidence/owner, F=review due, G=status. Validity checks support record quality only. Human decisions and genuine evidence remain necessary.
Date controlsSet As at date on each working sheet. Dates must be numeric whole days from 1 to 73050. Text, zero, negatives and fractional dates remain invalid even if pasted. A passed review date prompts review; it is not an automatic legal expiry.
Status and verificationUse the exact categories below. Verified effective also needs a specific H entry describing the competent verifier, test, evidence and limits. A populated field or an empty alert cell does not prove those claims.
Keeping and extending recordsTwenty rows are prepared. To extend, enlarge the table and all bounded A10:A29 and I10:I29 summaries/duplicate ranges, copy formulas, validation and conditional formatting, update the print area and test the new last row. Keep IDs and evidence together when sorting.
Privacy and retentionSet the approved record-specific retention period before operational use, including applicable statutory minimum, permit conditions and legal holds; review is not permission to delete. Access class in the catalogue: Project team. Keep clinical and personal information in authorised restricted custody.
Primary guidance checked 10 November 2026. Legal and permission registers retain their own detailed review dates, territories and unresolved decisions.
Process Safety Objectives, Targets and Indicators
Allowed action status values
OpenOfficial guidance 1 from www.hse.gov.uk
Implemented
Awaiting verification
Verified effective
Reopened
Not applicable