CWF-PLN-MON-01 · Completed fictional example · Owner role: Process safety and COMAH lead
Risk based inspection and assurance schedule
Crownway Fuels Ltd. CWF-PLN-MON-01. Version 1.0. Prepared 10 November 2026.
COMPLETED FICTIONAL ARRANGEMENT. This Crownway example supports adaptation and learning. It represents no actual company issue, site approval, signature or completed operational evidence.
Provide the site/task-specific risk based inspection and assurance schedule and retain its controlled output.
Purpose scope and accountable roles
BULK; HQ; RETAIL. Apply where the site/activity/hazard is present; confirm in the site applicability assessment. Ten English petrol/diesel forecourts and convenience shops, HQ and mobile support. The additional bulk establishment is a separate illustrative scenario. Inventory, regulatory applicability, permissions and site-specific acceptance are unresolved.
Process safety and COMAH lead owns delivery of this plan. Operations secures staffing and resources; engineering, the HSE lead and relevant competent specialists confirm technical and legal prerequisites. The board resolves constraints affecting critical controls.
Planned arrangements
Choose indicators from the major risks and critical-control functions, with an owner, definition, numerator, denominator, source, response threshold and review frequency. Include both failures and evidence that preventive work is completed effectively.
Shift staff check current operating conditions and record impairments. Area management challenges a sample in the field; the independent audit programme tests whether the monitoring system itself is reliable.
Required planning outputs
Control: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Location: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Competent inspector: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Frequency/rationale: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Escalation and independent sampling: the owner establishes the actual requirement and retains the evidence, accepted limits and unresolved actions in the linked site or task record. The example supplies no local layout, contact, inventory or technical value.
Delivery verification and review
Investigate missed tests, bypasses, repeated alarms, weak handovers and overdue actions. A favourable injury rate or completed-checklist percentage must not conceal unavailable process protection.
| Stage | Example management arrangement |
| Before the activity | Owner confirms the scope, competent people, current information and permissions. Open critical prerequisites prevent release. |
| At implementation | Site supervisor verifies the physical arrangement and understanding. Engineering checks the accepted technical criteria for the affected equipment. |
| After change or failure | Suspend the affected scope, assess the changed risk, update information and brief people before a new decision. |
| Planned review | Owner reviews at a justified risk-based interval. Area management challenges evidence and independent assurance samples effectiveness. |
Stop escalation and return
Escalate any red-limit breach or failed critical barrier immediately; restrict affected work rather than waiting for a monthly dashboard meeting.
The person controlling the activity makes it safe and informs the site manager. The relevant competent specialist verifies the failed or uncertain safeguard. Operations authorises any restart separately after technical acceptance, applicable permissions, work coordination and a fresh briefing. Record all continuing restrictions.
Worked decision
The dashboard shows all inspections completed, but one test record contains only a work-order closure. The HSE lead removes the unsupported effectiveness claim, engineering checks the actual protection and management reviews the data definition and similar records.
This invented case illustrates a decision and any continuing hold. It is not evidence that Crownway has completed an inspection, test, exposure evaluation or regulatory submission.
Guidance and related arrangements
Primary guidance 1
Process Safety Objectives, Targets and Indicators
Crownway document overview
Primary guidance checked 10 November 2026 for the described arrangements. Linked legal-register entries keep their own review dates and territorial conditions. Guidance, ACOPs, company controls and direct statutory duties are distinct.
Primary references: hsg254